Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) in Preston, Idaho

Required for new commercial construction, commercial additions, and commercial remodels or tenant improvements within Preston city limits. Preston publishes no distinct commercial-building-permit or tenant-improvement application, fee schedule, or review process: the City's Building Permit Application Instructions describe one generic document checklist, and Resolution #178 prices the underlying Building Permit itself ('set by city inspector, based on valuation') the same way regardless of occupancy. Applications go through the same CloudPermit online system used for residential work. The one confirmed gap: Resolution #178's flat Building Permit Application Fee lists only Single/Multi Family Dwelling ($150.00), Additions ($50.00), and Accessory Building ($25.00) — no Commercial line item exists, so an applicant should contact the Building Department for a quote on that flat fee rather than assume one of the residential figures applies. Separate from the Building Permit itself, Resolution #178's utility connection-fee schedule does distinguish commercial from residential: a sewer or water tap larger than a standard 1-inch residential service, and a fire-suppression water line for a sprinkler system, are priced on their own commercial-labeled tiers. Idaho Code 39-4117 also gives Preston a longer statutory clock to determine a commercial application complete — 20 business days versus 10 for residential — a statewide rule, not a city policy.

Verified 2026-08-25 · Source

When you need this permit

  • Land Survey of the lot prepared by an Idaho licensed engineer or land surveyor (a stamped plat map for a platted subdivision is acceptable if the lot is clearly identified) — the same document checklist used for residential projects, per the Building Permit Application Instructions
  • Copy of deed showing ownership and legal description
  • Detailed Site Plan showing lot dimensions, proposed and existing structures, setbacks, easements, finish contours/drainage, floor elevation, street/sewer elevations, utility line locations, use of each building, and a North arrow
  • Complete Building Plans meeting current building code specifications, reviewed by the city Building Inspector; no specific adopted code edition (such as a numbered IBC year) is named anywhere in the Building Permit Application Instructions, the Building Department's webpages, or Idaho DOPL's Building Code page — Idaho's statewide code-adoption framework governs absent a city-specific figure
  • Cut Permit (Encroachment/Cut Permit) if the project requires cutting a city street, including a licensed contractor to dig and locate city services Contractor
  • Current Preston City Business License for any contractor or other non-owner service provider working on the project
  • Preston has no distinct commercial-building-permit or tenant-improvement/TI permit product: commercial new construction, additions, and remodels use this same Building Permit application, document checklist, and CloudPermit portal used for residential work
  • Resolution #178's flat Building Permit Application Fee sub-categories (Single/Multi Family Dwelling, Additions, Accessory Building) do not include a Commercial line item; contact the Building Department for the applicable fee before budgeting a commercial project
  • A sewer or water connection larger than a standard 1-inch service, or a fire-suppression water line for a sprinkler system, is billed on Resolution #178's separate utility connection-fee schedule in addition to the Building Permit fee itself
  • Per Idaho Code 39-4117 (statewide, added 2025): for a commercial building permit application, Preston must, within 20 business days of receipt, provide written notice if the application is incomplete, and must issue a written completeness determination within 20 business days of a submission or revised submission — 20 business days for commercial versus 10 business days for residential. A completeness determination is not approval; it only authorizes the application to proceed to plan review.
  • No fire-district or state fire marshal plan-review requirement for privately owned commercial construction was found: the Idaho State Fire Marshal's Plan Reviews program is scoped to state-owned and state-leased buildings, and the Franklin County Fire District's own published materials cover burn permits and emergency response rather than a building-plan-review process — confirm directly with the Building Department and the Franklin County Fire District whether either applies to a given project

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 6 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit (base)Resolution #178 (effective 2026-02-01): 'Building Permits (set by city inspector, based on valuation)' — the same generic line used for residential and commercial projects; no separate percentage or table is published for either.
Set by city inspector, based on valuation
Building Permit Application Fee — Commercial
Resolution #178's 'BUILDING AND DEVELOPMENT' Building Permit Application Fee sub-categories list only Single/Multi Family Dwelling ($150.00), Additions ($50.00), and Accessory Building ($25.00) — no… Show full citationResolution #178's 'BUILDING AND DEVELOPMENT' Building Permit Application Fee sub-categories list only Single/Multi Family Dwelling ($150.00), Additions ($50.00), and Accessory Building ($25.00) — no 'Commercial' line item exists anywhere in the document. The prior fee resolution, #174 (passed April 14, 2025, effective May 1, 2025), lists the identical three sub-categories with no Commercial line either, so the omission predates #178 and is not a one-time drafting gap. No resolution between #178 and the current numbering (#182, an Employee Salary resolution, appears on the August 24, 2026 council agenda) touches the license/fee schedule; the city's own Forms & Applications page still links Resolution #178 as its current fee schedule. Ordinance 2026-3 (adopted January 26, 2026) repealed and replaced Title 15 (Buildings and Construction) but only to remove obsolete building-code-edition references and align with Idaho State codes — it does not touch fees. Contact Building Inspector Curt Fuller (curtf@prestonid.us, 208-540-0417) for the applicable Application Fee amount for a specific commercial project.
Not separately published
Sewer Connection Fee — Commercial (4-inch)Resolution #178, SEWER CONNECTION FEES section, Commercial category.
$9,000.00
Sewer Connection Fee — Commercial (6-inch)Resolution #178, SEWER CONNECTION FEES section, Commercial category.
$9,000.00
Water Connection Fee — Commercial (1-inch)Resolution #178, WATER CONNECTION FEES section, Commercial category.
$9,000.00
Water Connection Fee — Commercial (2-inch)Resolution #178, WATER CONNECTION FEES section, Commercial category.
$9,000.00
Water Connection Fee — Commercial (4-inch)Resolution #178, WATER CONNECTION FEES section, Commercial category.
$36,000.00
Water Connection Fee — Fire Suppression Line / Non-Consumptive UseResolution #178, WATER CONNECTION FEES section, Commercial category — the fee for a dedicated water line serving a fire-suppression (sprinkler) system rather than domestic/process use.
$28,000.00
Hot Tap Inspection Fee (sewer or water)Resolution #178, SEWER CONNECTION FEES and WATER CONNECTION FEES sections. The Inspection Fee for a Main Line Tap within a subdivision or PUD is paid by the developer directly rather than as a flat city fee, per the same sections.
$1,000.00, plus $200.00 per lot
Preston City Business License (per contractor)Resolution #178, BUSINESS LICENSES section. Required per the Building Permit Application Instructions for anyone but the property owner performing work under the permit.
$50.00
Encroachment/Cut PermitResolution #178, plus a bond 'based on square footage of trench' (amount not published as a flat figure); applies only if the project requires cutting a city street.
$200.00

Review timeline

Plan reviewPreston’s published plan-review target
30+ business days

How long did your Commercial Building Permit (New Construction, Additions, Remodels & Tenant Improvements) permit actually take in Preston?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full Preston inspection guide — scheduling & re-inspection fees →

    Tips

    • Preston has no separate commercial-building-permit or tenant-improvement (TI) permit: commercial new construction, additions, and remodels go through the same Building Permit process, document checklist, and CloudPermit portal as residential work.
    • Resolution #178's flat Building Permit Application Fee lists only Single/Multi Family Dwelling ($150.00), Additions ($50.00), and Accessory Building ($25.00) categories — there is no Commercial line item. Contact Building Inspector Curt Fuller (curtf@prestonid.us, 208-540-0417) for a fee quote before budgeting a commercial project.
    • A commercial project needing a sewer or water tap larger than a standard 1-inch residential service, or a dedicated fire-suppression water line for a sprinkler system, is billed on Resolution #178's separate utility connection-fee schedule — as much as $36,000.00 for a 4-inch water connection — in addition to, not instead of, the valuation-based Building Permit fee.
    • Neither the Building Permit Application Instructions, the Building Department's webpages, Resolution #178, nor Idaho DOPL's Building Code page names a specific adopted code edition (such as a numbered IBC year) for Preston; Idaho's statewide code-adoption framework governs absent a city-specific figure, so confirm the current edition directly with the Building Department or the Idaho Division of Occupational and Professional Licenses.
    • A commercial building permit application gets a longer statutory completeness-review clock than residential under Idaho Code 39-4117: 20 business days for Preston to determine the application complete, versus 10 business days for residential.
    • No published fire-district or state fire marshal plan-review requirement was found for privately owned commercial construction in Preston — the Idaho State Fire Marshal's Plan Reviews program covers only state-owned and state-leased buildings — so confirm directly with the Franklin County Fire District and the Building Department whether a specific project needs their sign-off.
    • Preston publishes no list of required construction inspections (such as footing, framing, or final) for the Building Permit, commercial or residential: the Building Permit Application Instructions, both Building Department web pages, and Resolution #178 describe no inspection sequence or sign-off checklist. The Inspection Fee lines in Resolution #178 (Hot Tap Inspection Fee, Inspection Fee for a Main Line Tap) belong to the separate Sewer and Water Connection fee schedule and cover a Public Works inspection of the utility tap itself, not an inspection of the building. Contact Building Inspector Curt Fuller (curtf@prestonid.us, 208-540-0417) to confirm what inspections a specific commercial project will need and when to schedule them.

    Frequently asked questions

    Preston requires a commercial building permit (new construction, additions, remodels & tenant improvements) for: Land Survey of the lot prepared by an Idaho licensed engineer or land surveyor (a stamped plat map for a platted subdivision is acceptable if the lot is clearly identified) — the same document checklist used for residential projects, per the Building Permit Application Instructions; Copy of deed showing ownership and legal description; Detailed Site Plan showing lot dimensions, proposed and existing structures, setbacks, easements, finish contours/drainage, floor elevation, street/sewer elevations, utility line locations, use of each building, and a North arrow; Complete Building Plans meeting current building code specifications, reviewed by the city Building Inspector; no specific adopted code edition (such as a numbered IBC year) is named anywhere in the Building Permit Application Instructions, the Building Department's webpages, or Idaho DOPL's Building Code page — Idaho's statewide code-adoption framework governs absent a city-specific figure; Cut Permit (Encroachment/Cut Permit) if the project requires cutting a city street, including a licensed contractor to dig and locate city services; Current Preston City Business License for any contractor or other non-owner service provider working on the project; Preston has no distinct commercial-building-permit or tenant-improvement/TI permit product: commercial new construction, additions, and remodels use this same Building Permit application, document checklist, and CloudPermit portal used for residential work; Resolution #178's flat Building Permit Application Fee sub-categories (Single/Multi Family Dwelling, Additions, Accessory Building) do not include a Commercial line item; contact the Building Department for the applicable fee before budgeting a commercial project; A sewer or water connection larger than a standard 1-inch service, or a fire-suppression water line for a sprinkler system, is billed on Resolution #178's separate utility connection-fee schedule in addition to the Building Permit fee itself; Per Idaho Code 39-4117 (statewide, added 2025): for a commercial building permit application, Preston must, within 20 business days of receipt, provide written notice if the application is incomplete, and must issue a written completeness determination within 20 business days of a submission or revised submission — 20 business days for commercial versus 10 business days for residential. A completeness determination is not approval; it only authorizes the application to proceed to plan review.; No fire-district or state fire marshal plan-review requirement for privately owned commercial construction was found: the Idaho State Fire Marshal's Plan Reviews program is scoped to state-owned and state-leased buildings, and the Franklin County Fire District's own published materials cover burn permits and emergency response rather than a building-plan-review process — confirm directly with the Building Department and the Franklin County Fire District whether either applies to a given project. If your project isn't listed, confirm with City of Preston Building Department at (208) 852-1817 before starting work.

    The Building Permit itself is set by the city inspector based on the project's valuation, the same as for residential work — no flat percentage is published. Resolution #178's flat Building Permit Application Fee, however, lists only Single/Multi Family Dwelling ($150.00), Additions ($50.00), and Accessory Building ($25.00) categories, with no Commercial line item; contact the Building Department for a quote on that fee. Separately, a commercial project needing a sewer or water connection larger than a standard 1-inch residential service, or a fire-suppression water line, is billed on Resolution #178's utility connection-fee schedule ($9,000.00 to $36,000.00 depending on size and type).

    Preston's published plan-review target for a commercial building permit (new construction, additions, remodels & tenant improvements) is 30+ business days.

    You'll need: Building Permit Application Instructions; Land Survey or stamped Plat Map; Copy of Deed; Site Plan (PDF); Building Plans (PDF); Preston City Business License. Depending on your project, Preston may also ask for: Encroachment/Cut Permit. See the required-documents checklist on this page for details on each.

    Apply through City of Preston Building Department at 70 West Oneida, Preston, ID 83263. Phone: (208) 852-1817, email: curtf@prestonid.us. Office hours: Monday–Friday, 8:00 AM to 5:00 PM, per prestonidaho.net main contact info. Building Inspector: Curt Fuller (208-540-0417, curtf@prestonid.us). Permit Administrator: Shawn Oliverson (208-852-1817, shawno@prestonid.us), per the city's Building Department page and Employee Directory. Note: the city's Employee Directory lists Shawn Oliverson's title as 'Director of City Planning and Land Use' rather than 'Permit Administrator' — both titles appear on different city-published pages and are reported here without resolving the discrepancy. No separate 'City Engineer' position appears in the Employee Directory despite being referenced in the Building Permit Application Instructions document; Public Works Director is Scott Montgomery..

    Preston's own published materials — the Building Permit Application Instructions, the Building Department's webpages, Resolution #178, and Idaho DOPL's Building Code page — do not name a specific adopted code edition or year. Idaho's statewide code-adoption framework, administered by the Idaho Building Code Board, governs in the absence of a city-specific figure; contact the Building Department or Idaho DOPL to confirm the edition currently in force for a specific project.

    No. Preston does not publish a distinct commercial-building-permit or TI-permit product. Commercial new construction, additions, and remodel/tenant-improvement work use the same Building Permit application, the same document checklist (Land Survey, Deed, Site Plan, Building Plans, and a Cut Permit if applicable), and the same CloudPermit online system as residential projects.

    No published requirement was found. The Idaho State Fire Marshal's Plan Reviews program is limited to state-owned and state-leased buildings, and the Franklin County Fire District's own published materials describe burn permits and emergency response services rather than a commercial building-plan-review process. Confirm directly with the Building Department and the Franklin County Fire District whether either reviews a given commercial project.

    Sources & verification

    Verified against official sources. Last reviewed 2026-08-25.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Preston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

    This one’s complicated · Get an expediter

    Tell us about your project and we’ll connect you with a permit expediter who works in Preston.

    PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.