Solar PV Permit (State-Issued Electrical + City Building Permit) — Preston, Idaho · Requirements sheet
Verified 2026-07-19 · Source: https://dopl.idaho.gov/ele/ele-permits-and-inspections/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit (State-Issued Electrical + City Building Permit) in Preston, Idaho
Required for installation of rooftop or ground-mounted solar photovoltaic systems within Preston city limits. Idaho does not allow cities to administer their own electrical permitting: the electrical-connection scope of a solar install is permitted directly by the Idaho Division of Occupational and Professional Licenses (DOPL, formerly the Division of Building Safety / Idaho Bureau of Occupational Licenses), while the structural/roof-mounting scope requires a City of Preston Building Permit using the same process and fee structure as other construction on file for this jurisdiction.
Verified 2026-07-19 · Source
When you need this permit
- Electrical work on a solar PV system must be performed by an Idaho-licensed electrical contractor whose electrician holds (or is supervised by someone holding) the Solar Photovoltaic limited electrical license category, which requires proof of NABCEP (North American Board of Certified Energy Practitioners) installer certification or equivalent, per IDAPA 24.39.10.153.09
- Grid-tied renewable energy systems require a mandatory electrical plan review by DOPL before the installation permit can be purchased, billed at the state's standard plan-review rate
- All PV electrical work must comply with the applicable provisions of the National Electrical Code as adopted by Idaho (IDAPA 24.39.10.250)
- The structural/roof-mounting scope requires a City of Preston Building Permit: Land Survey or stamped plat map, Site Plan, complete Building Plans meeting current code, and (per the City's standard Building Permit Application Instructions) a Preston City Business License for any contractor other than the property owner
- Separate permits are required for electrical work in addition to the City building permit — the City does not issue electrical permits itself
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Rough-In
Grounding and listing of all components verified before the system is covered or energized (DOPL electrical inspection)
- 2
Electrical Final
Wiring methods, labeling at the shut-off, working clearances, and system operation verified (DOPL electrical inspection)
- 3
Building Final
Panel mounting and roof penetrations verified against approved plans (City of Preston building inspection)
See the full Preston inspection guide — scheduling & re-inspection fees →
Tips
- Idaho does not allow the City of Preston to issue its own electrical permits — the electrical scope of any solar installation is a STATE permit through DOPL, not a city permit, regardless of jurisdiction size.
- Because grid-tied systems require a passing DOPL plan review before the installation permit itself can be purchased, budget the plan-review fee ($65/hour, one-hour minimum) and lead time separately from the installation permit fee.
- The structural/roof-mounting scope still requires the City of Preston's standard Building Permit process (Land Survey, Site Plan, Building Plans) — contact Building Inspector Curt Fuller, (208) 540-0417, to confirm which fee category applies to a solar-only project, since the City's Resolution #178 fee schedule does not list a dedicated solar line item.
- A contractor performing the installation must hold Idaho's Solar Photovoltaic limited electrical license category (requiring NABCEP certification or equivalent), per the Idaho Electrical Board's own rules — homeowners may self-install on their own residence subject to Idaho Code Section 54-1016 exemptions.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Preston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Preston
Solar PV Permit (State-Issued Electrical + City Building Permit) in other cities
Compare solar pv permit (state-issued electrical + city building permit) fees across Idaho →
Look up this fee in a different city →
Now live
Build your Preston project checklist
Describe your project once and get every permit, document, and fee it triggers in Preston — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →