Commercial Building Permit (New Construction / Remodel Changing Outside Dimensions) in Unincorporated Franklin County, Idaho

Required for new construction of any commercial or industrial building or structure, or for a commercial remodel that changes a structure's outside dimensions, anywhere in unincorporated Franklin County. Franklin County Code § 150.015(A) requires a building permit for construction of 'any building, structure, or mobile home' without distinguishing residential from commercial use, and the county issues commercial permits through the same Building Permit Application used for residential work — the form itself lists 'Commercial' as one of its Type of Construction checkboxes, and no separate commercial application is published. The Building Permit Fee is 1% of the assessed value of the proposed building, per § 150.018, the same rate and valuation base the county applies to residential permits; no separate or higher commercial rate is published. Owners of industrial or commercial buildings who certify, in advance, that the project will create and fill five or more full-time positions within 24 months are instead exempt from the fees imposed by the International Building Codes under § 150.002(B), though they must still purchase a county building permit and pay a site inspection fee set by older ordinances whose current dollar amount is not published in the codified text.

Reviewed 2026-08-25 · Source

When you need this permit

  • New construction of any commercial or industrial building or structure, or a remodel changing a structure's outside dimensions, requires a building permit from the County Building Inspector, per Franklin County Code § 150.015(A) — the same occupancy-neutral requirement that covers residential construction, with no separate commercial permit type defined in the ordinance
  • Structures exceeding 200 square feet require a permit, per the county's Building Permit Information and Process document — the same threshold published for all building permits, not specific to commercial work
  • Reviewed under the International Building Code edition currently adopted by the state's Building Code Board, per Franklin County Code § 150.001(A)-(B), which adopts building codes by reference to the state's approved editions rather than naming a fixed edition in the county ordinance; the Idaho Division of Occupational and Professional Licenses' published adopted-codes list names the 2018 International Building Code, with amendments, as the current statewide edition, alongside the 2018 International Energy Conservation Code, 2018 International Mechanical Code, and 2018 International Fuel Gas Code
  • Owners of industrial or commercial buildings who certify, in advance, that the project will create and fill five or more full-time positions within the succeeding 24 months are exempt from the fees imposed by the International Building Codes, per § 150.002(B), but remain subject to all other building-code requirements and to purchasing a county building permit and paying a site inspection fee as required by Ord. 1984-3, 1995-1, 1995-2, and 1998-2 — the current dollar amount of that site inspection fee is not given in the codified text
  • Written approval from the Idaho Department of Health / Southeastern District Health Department required whenever culinary water, sanitary sewer, or septic system work is part of the project, per § 150.017(C)
  • Parcel must be an eligible 'building lot' (all county land is zoned agriculture by default; parcel-split history must be researched back to June 1993, or contact the Planning and Zoning Administrator to begin the rezone process)
  • The Building Permit Checklist requires sign-off from the Fire Department, School District, Road Department, and Post Office before a permit is issued, per the county's own Building Permit Checklist form — the same checklist used for residential permits

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee
Franklin County Code § 150.018, 'payable when the application is made for any construction defined in § 150.015' (Ord. Show full citationFranklin County Code § 150.018, 'payable when the application is made for any construction defined in § 150.015' (Ord. 2016-2-22, passed 2-22-2016) — the same rate and valuation base the county's own Building Permit Information and Process document applies to residential permits; no separate or higher commercial rate is published.
1% of the assessed value of the proposed building
Site Inspection Fee (job-creation fee exemption path)
Franklin County Code § 150.002(B): industrial or commercial buildings whose owners certify, in advance, that the project will create and fill five or more full-time positions within the succeeding 24… Show full citationFranklin County Code § 150.002(B): industrial or commercial buildings whose owners certify, in advance, that the project will create and fill five or more full-time positions within the succeeding 24 months are exempt from the fees imposed by the International Building Codes, but remain subject to purchasing a county building permit and paying a site inspection fee 'as required by Ord. 1984-3, 1995-1, 1995-2, and 1998-2.' Of those four, only Ord. 1995-1 (passed 2-27-1995, codified at § 150.017) and Ord. 1998-2 (passed 12-28-1998, codified at §§ 150.015, 150.019) appear anywhere in the county's own References to Ordinances disposition table, which runs from the county's earliest ordinances (1914) through the current 2025-09-08 supplement and includes items codified elsewhere (the Table of Special Ordinances) as well as Chapter 150 itself; Ord. 1984-3 and Ord. 1995-2 do not appear in that table under any code section or special-ordinance table, and neither number appears in the history line of any section of Chapter 150. Chapter 150 contains exactly one dollar-denominated fee anywhere in its text — § 150.018's 1% building permit fee — with no separate site inspection fee figure in any other section. No county budget document, consolidated fee schedule, or commissioner-minutes excerpt naming a site inspection fee dollar amount is available online, and Wayback Machine snapshots of the county's former stand-alone building-inspector webpage (10 captures, 2015-2024) carry no fee content beyond the Building Permit Fee already cited above. Both of the county's own building-permit PDFs (the Building Permit Information and Process document and its bundled Building Permit Application, Building Permit Checklist, Plan Submittal List, and Inspection Process pages) contain no site inspection fee dollar amount.
Not published in the current codified text
Fire Department Review / Sign-off
The county's own Building Permit Checklist lists 'Fire Department' as one of four sign-off lines (Fire Department, School District, Road Department, Post Office), each a blank signature/comment field… Show full citationThe county's own Building Permit Checklist lists 'Fire Department' as one of four sign-off lines (Fire Department, School District, Road Department, Post Office), each a blank signature/comment field paired with a named contact (Matt Gleed, 208-852-3111 for Fire) rather than a dollar figure — consistent across both the county-hosted and irp-cdn-hosted copies of the same document. Franklin County Fire District's own website (franklincountyfiredistrict.com) publishes no fee schedule of any kind; its only linked records resource is an open Google Drive folder holding a single upcoming Fire Commissioner meeting agenda, with no searchable historical minutes or budget documents. Based on the checklist's own layout, the Fire Department step reads as a sign-off confirming the applicant's plans rather than a distinct fee-bearing plan review, but that reading could not be cross-checked against the Fire District's own budget or governing ordinance, so it is offered as the best-supported interpretation rather than a settled fact.
No fee schedule published

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit (New Construction / Remodel Changing Outside Dimensions) permit actually take in Unincorporated Franklin County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Setback

    Excavation to proper depth (30 inches below final grade); excavation at least 80 feet from the center of the county road or 50 feet from the fence, whichever is furthest; rebar tied and lifted approximately 3 inches off the ground, with the UFER electrical ground in place; no frost in the ground; rebar dowels set 24 inches on center after concrete is poured. Per the county's own Inspection Process document — the same document that publishes the residential inspection sequence, titled for the county generally rather than for one occupancy type, and bundled with the same Building Permit Application that lists Commercial alongside House, Apartment, and other Types of Construction. The county publishes no separate inspection sequence for commercial work; the document names only the Building Inspector (208-221-6149) as the contact to schedule each of these five stages, giving 24 hours' notice, and names no other inspector or agency for them.

  2. 2

    Foundation

    Forms in place, rebar in position both horizontal and vertical (24 inches on center), any blockouts in place, cold joints doweled. Per the same Inspection Process document.

  3. 3

    Framing/Mechanical

    Sheathing inspection before house-wrap is applied; framing, fire-blocking, and bracing inspection made after the roof and windows are in but before insulation; rough electrical and plumbing inspected in place; rough mechanical (ducts, flues, appliances) in place. Per the same Inspection Process document.

  4. 4

    Sheetrock

    After sheetrock is installed, before taping. Per the same Inspection Process document.

  5. 5

    Final

    Prior to occupancy, with finish grade and the building completed; final electrical, plumbing, and mechanical inspections completed. Per the same Inspection Process document.

See the full Unincorporated Franklin County inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate commercial or Tenant Improvement building permit product in unincorporated Franklin County — commercial new construction and remodels changing outside dimensions use the same Building Permit Application, Building Permit Checklist, and Plan Submittal List published for residential work.
  • Franklin County Code § 150.001 adopts building codes by reference to whatever edition the state's Building Code Board currently approves rather than naming a fixed edition in the county ordinance; confirm the current edition and any state amendments with the Idaho Division of Occupational and Professional Licenses' Building Code Board before finalizing commercial plans.
  • If the project will create and fill five or more full-time positions within 24 months, ask the Building Inspector (Randy Henrie, 208-221-6149) whether it qualifies for the § 150.002(B) fee exemption before assuming the standard 1%-of-assessed-value fee applies.
  • The Franklin County Fire District (208-852-3111) must sign off on the Building Permit Checklist before a permit is issued; contact the district directly for any project-specific fire-code requirements, since it publishes no fee schedule or commercial plan-review process on its own website.
  • Confirm whether the project site is inside Preston city limits before applying — properties within the City of Preston are permitted through the City's own Building Department, not this county department.

Frequently asked questions

Unincorporated Franklin County requires a commercial building permit (new construction / remodel changing outside dimensions) for: New construction of any commercial or industrial building or structure, or a remodel changing a structure's outside dimensions, requires a building permit from the County Building Inspector, per Franklin County Code § 150.015(A) — the same occupancy-neutral requirement that covers residential construction, with no separate commercial permit type defined in the ordinance; Structures exceeding 200 square feet require a permit, per the county's Building Permit Information and Process document — the same threshold published for all building permits, not specific to commercial work; Reviewed under the International Building Code edition currently adopted by the state's Building Code Board, per Franklin County Code § 150.001(A)-(B), which adopts building codes by reference to the state's approved editions rather than naming a fixed edition in the county ordinance; the Idaho Division of Occupational and Professional Licenses' published adopted-codes list names the 2018 International Building Code, with amendments, as the current statewide edition, alongside the 2018 International Energy Conservation Code, 2018 International Mechanical Code, and 2018 International Fuel Gas Code; Owners of industrial or commercial buildings who certify, in advance, that the project will create and fill five or more full-time positions within the succeeding 24 months are exempt from the fees imposed by the International Building Codes, per § 150.002(B), but remain subject to all other building-code requirements and to purchasing a county building permit and paying a site inspection fee as required by Ord. 1984-3, 1995-1, 1995-2, and 1998-2 — the current dollar amount of that site inspection fee is not given in the codified text; Written approval from the Idaho Department of Health / Southeastern District Health Department required whenever culinary water, sanitary sewer, or septic system work is part of the project, per § 150.017(C); Parcel must be an eligible 'building lot' (all county land is zoned agriculture by default; parcel-split history must be researched back to June 1993, or contact the Planning and Zoning Administrator to begin the rezone process); The Building Permit Checklist requires sign-off from the Fire Department, School District, Road Department, and Post Office before a permit is issued, per the county's own Building Permit Checklist form — the same checklist used for residential permits. If your project isn't listed, confirm with Franklin County Building Department at (208) 221-6149 before starting work.

Per Franklin County Code § 150.018, the Building Permit Fee is 1% of the assessed value of the proposed building — the same rate applied to residential permits. Owners of industrial or commercial buildings that will create and fill five or more full-time positions within 24 months can instead qualify for an exemption from International Building Code fees under § 150.002(B), though a county building permit and an unpublished site inspection fee still apply.

Unincorporated Franklin County does not publish a plan-review timeline for this permit. Contact Franklin County Building Department at (208) 221-6149 for current turnaround.

You'll need: Franklin County Building Permit Application; Copy of Deed; Building plans (Site Plan, Foundation Plan, Floor Plans, Slice Plan, Elevation Plans, Electrical Plan, Roof Plan); Signature Checklist / Building Permit Checklist. Depending on your project, Unincorporated Franklin County may also ask for: Septic Permit. See the required-documents checklist on this page for details on each.

Unincorporated Franklin County requires 5 inspection(s) for a commercial building permit (new construction / remodel changing outside dimensions), in order: Footing/Setback, Foundation, Framing/Mechanical, Sheetrock, Final. Schedule each through Franklin County Building Department ((208) 221-6149).

Apply through Franklin County Building Department at 561 West Oneida, Preston, ID 83263. Phone: (208) 221-6149, email: plans@fcidaho.us. Office hours: Monday–Friday, 9:00 AM to 5:00 PM, per franklincountyidaho.org/departments/building_department.php. Building Inspector: Randy Henrie, who also serves as the county's Planning and Zoning Administrator, per the county's own Building Permit Information and Process document (fax: 208-852-1096)..

Franklin County Code § 150.001 adopts the International Building Code, International Energy Conservation Code, International Mechanical Code, International Fuel Gas Code, and International Fire Code by reference to whatever editions the state's Building Code Board currently approves, automatically superseded as the state adopts new editions. The Idaho Division of Occupational and Professional Licenses' published adopted-codes list currently names the 2018 International Building Code, with amendments, as the statewide edition.

No. Franklin County's Building Permit Application is used for both residential and commercial construction; the form itself lists 'Commercial' as one of its Type of Construction checkboxes, and no dedicated commercial-only application is published.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-25.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Franklin County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Franklin County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Commercial Building Permit (New Construction / Remodel Changing Outside Dimensions) in other cities

Compare commercial building permit (new construction / remodel changing outside dimensions) fees across Idaho

Look up this fee in a different city →

Embed this data card →

Now live

Build your Unincorporated Franklin County project checklist

Describe your project once and get every permit, document, and fee it triggers in Unincorporated Franklin County — in one checklist. Free, for any city and any number of projects.

Get started →