Rigby building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Rigby, Idaho.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
158 West Fremont Avenue, Rigby, ID 83442 (City Hall); building permit applications submitted via Jefferson County PZ&B, 210 Courthouse Way, Suite 170, Rigby, ID 83442
Phone
(208) 745-8111
Email
Office hours
Mon–Fri, City Hall business hours; Jefferson County PZ&B Mon–Fri 9:00 AM – 5:00 PM

Published scheduling rules

  • Minimum 24 hours' notice required to request an inspection (Solar Array Building Permit)
  • Minimum 24 hours' notice is required to schedule any county inspection. (Residential Building Permit (Single-Family Dwelling, Townhouse, New Construction & Additions))
  • Minimum 24 hours' notice is required for any county inspection request. (General)

Inspection sequence

Applies to: Residential Building Permit (Single-Family Dwelling, Townhouse, New Construction & Additions)

  1. 1

    Layout Inspection

    Verifies structure layout on the site matches the approved site plan

  2. 2

    Footing Inspection

    Must occur before concrete is poured

  3. 3

    Foundation Inspection

    Must occur before concrete is poured

  4. 4

    Water Service Pit / Water & Sewer Line Inspection (City of Rigby Public Works)

    City-specific inspection before water/sewer lines are covered; curb stop and service pit must be exposed for this inspection before final grade

  5. 5

    Sheathing Inspection

    Building cannot be wrapped/house-wrapped before this inspection

  6. 6

    Mechanical (HVAC) Rough-In Inspection

    Performed by Jefferson County PZ&B inspectors as of June 1, 2026 (previously Idaho DOPL)

  7. 7

    State Rough-In Inspections (Electrical, Plumbing)

    Performed by Idaho DOPL — required before framing/insulation cover; plumbing and electrical had not yet transitioned to county inspectors as of the March 2026 reporting on the joint powers agreement

  8. 8

    Framing Inspection

    After structural framing complete

  9. 9

    Insulation Inspection

    Before drywall/wall cover

  10. 10

    Drywall Inspection

    Seams cannot be taped or mudded before this inspection

  11. 11

    Sidewalk/Curb Base Inspection (City of Rigby Public Works)

    Sidewalk base must be inspected by city Public Works before concrete is poured

  12. 12

    State/County Final Inspections (Mechanical, Electrical, Plumbing)

    Final mechanical sign-off by Jefferson County PZ&B; final electrical/plumbing sign-off by Idaho DOPL pending further county transition

  13. 13

    Health Department Final

    If applicable — e.g., septic system final from Eastern Idaho Public Health

  14. 14

    Final Inspection by Jefferson County Building Department

    Final building-code sign-off by county inspectors under the Joint Powers Agreement. Minimum 24 hours' notice required to schedule any inspection.

  15. 15

    Final Grade and Certificate of Occupancy / Certificate of Completion Issuance (City of Rigby)

    Property must be brought to final grade before CO/CC issuance. Per Jefferson County's own process document: 'If the property is within incorporated city limits, the documentation will be forwarded to the city, and they will issue the CO or CC' — Rigby, not the county, issues the final CO/CC.

Applies to: EV Charging Station Permit (State-Issued Electrical Permit)

  1. 1

    Electrical Rough-In (if applicable)

    Required only if new circuit wiring is enclosed before final; conduit runs, wire sizing, and grounding verified (DOPL electrical inspection)

  2. 2

    Electrical Final

    EVSE circuit breaker sizing, GFCI protection (where applicable), working clearances, and charger mounting verified against NEC Article 625 (DOPL electrical inspection)

Applies to: Solar Array Building Permit

  1. 1

    Roof/Structural Inspection (roof-mount only)

    Verifies racking/mounting installation matches the approved engineered plans; minimum 24 hours' notice required to request

  2. 2

    Electrical Rough-In / Final (Idaho DOPL)

    Electrical connection work is inspected by the State of Idaho DOPL, since electrical permitting is not locally administered by Rigby or Jefferson County

Re-inspection fees

Residential Building Permit (Single-Family Dwelling, Townhouse, New Construction & Additions)Re-Inspection Fee · Jefferson County-Wide Fee Schedule 2026, Exhibit A
$90.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rigby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Rigby building permits

Get alerts for Rigby

We'll email you when Rigby's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.