Solar Array Building Permit in Rigby, Idaho

Required for rooftop or ground-mounted solar photovoltaic (solar array) installations within Rigby city limits. Despite a City of Rigby 'tipsAndGotchas' generalization elsewhere in this dataset describing Solar as one of the simpler permits obtained directly from City Hall (like Deck, Fence, Garage/Shed), Jefferson County's own dedicated 'Rigby Solar Array Building Permit' help document — which this entry is sourced from — directs applicants to submit through the shared Jefferson County Planning, Zoning & Building Cityworks public portal, the same co-administration model used for Rigby's Residential Building Permit. Electrical-connection work is permitted separately through the State of Idaho DOPL, since Rigby/Jefferson County do not locally administer electrical trade permits.

Verified 2026-07-19 · Source

When you need this permit

  • Submit through the Jefferson County Planning, Zoning & Building Permit & Application Portal (Cityworks), not a separate city-only process, per the county's own 'Rigby Solar Array Building Permit' help document
  • Application data required: Parcel Number, Parcel Size, City of Rigby Zoning, Location Address, Subdivision/Lot/Block (if applicable), flood zone status, height to top of gable, height to bottom of eave, distance eave extends from structure, setbacks (North/East/West/South), distance from other buildings on the property, and canal/irrigation information if applicable
  • All construction must comply with the 2018 IRC
  • City of Rigby Zoning Certificate and a Recorded Warranty Deed must be attached
  • Must attach a copy of an active Idaho Contractor License Contractor
  • Site Plan showing property lines, setbacks, North arrow, all structures (new/existing) with dimensions, driveway location, canals/rivers/roads, and parcel size
  • Roof or ground layout (plan view of the system and equipment)
  • Line diagram: detailed line wiring diagram of the solar energy system and all electrical equipment
  • Racking/Mounting plans: detailed plans for racking, mounting, grounding, and bonding, including manufacturer specifications for fasteners and hardware
  • Labelling: in-color details of all labels used for the solar energy system and equipment
  • Manufacturer specifications/cut-sheets for all solar equipment (electrical and structural) — installation manuals are not accepted in lieu of manufacturer spec sheets, UNLESS the submitted plans are stamped and signed by both an Idaho-licensed electrical engineer and an Idaho-licensed structural engineer
  • Engineer Letter (required if solar is installed on a roof): signed by an Idaho-licensed engineer, certifying the roof will support the load of the solar energy system
  • Flood Plain Development Permit Application and Elevation Certificate required if the property is in a mapped flood plain
  • Electrical-connection work is permitted separately through the State of Idaho DOPL, not through this City/County building permit
  • Minimum 24 hours' notice required to request an inspection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 6 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar Array Building Permit FeeNo solar-specific dollar figure or valuation bracket is published in the Jefferson County-Wide Fee Schedule 2026, Exhibit A, or in the county's Rigby Solar Array Building Permit help document — the help document describes the required application data and attachments but states no fee table. The City of Rigby's own separate 'City of Rigby Solar Permit' PDF (cityofrigby.gov/wp-content/uploads/2024/05/Solar-Permit.pdf) is not usable as a fee source: on direct inspection, it is a template document whose body text is entirely a Fence Permit form (it repeats 'ISSUANCE OF THIS FENCE PERMIT...' and 'This is a Permit for the construction of a fence only' throughout, with only the header retitled to 'Solar Permit') — an apparent city document/template error, not a real solar-specific fee or process. Contact Jefferson County PZ&B, (208) 745-9220, or Rigby City Hall, (208) 745-8111, for a current fee quote.
Not published — contact the department

Review timeline

Plan reviewRigby’s published plan-review target
15–15 business days

How long did your Solar Array Building Permit permit actually take in Rigby?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Roof/Structural Inspection (roof-mount only)

    Verifies racking/mounting installation matches the approved engineered plans; minimum 24 hours' notice required to request

  2. 2

    Electrical Rough-In / Final (Idaho DOPL)

    Electrical connection work is inspected by the State of Idaho DOPL, since electrical permitting is not locally administered by Rigby or Jefferson County

See the full Rigby inspection guide — scheduling & re-inspection fees →

Tips

  • Solar in Rigby goes through the SAME Jefferson County Cityworks portal used for the Residential Building Permit — do not assume it is a simple city-direct permit like Deck, Fence, or Garage/Shed; the county's own dedicated help document for Rigby solar applications directs applicants to the Cityworks portal.
  • The City of Rigby's own separately-hosted 'Solar Permit' PDF form is a mislabeled Fence Permit template (its body text is entirely fence-permit language) — do not rely on it; use the Jefferson County Cityworks portal and the county's Rigby Solar Array Building Permit help document instead.
  • An Engineer Letter certifying the roof can support the added load is required for any roof-mounted installation — budget for an Idaho-licensed engineer's review before applying.
  • Manufacturer cut-sheets can be skipped only if your plan set is stamped and signed by both an Idaho-licensed electrical engineer AND an Idaho-licensed structural engineer.
  • The electrical connection scope is a separate permit through Idaho DOPL — this county/city permit covers the structural, roof/ground-mount, and general building-code scope only.
  • Budget a minimum of 15 business days for plan review, the same figure documented for Rigby's general Residential Building Permit.

Frequently asked questions

Rigby requires a solar array building permit for: Submit through the Jefferson County Planning, Zoning & Building Permit & Application Portal (Cityworks), not a separate city-only process, per the county's own 'Rigby Solar Array Building Permit' help document; Application data required: Parcel Number, Parcel Size, City of Rigby Zoning, Location Address, Subdivision/Lot/Block (if applicable), flood zone status, height to top of gable, height to bottom of eave, distance eave extends from structure, setbacks (North/East/West/South), distance from other buildings on the property, and canal/irrigation information if applicable; All construction must comply with the 2018 IRC; City of Rigby Zoning Certificate and a Recorded Warranty Deed must be attached; Must attach a copy of an active Idaho Contractor License; Site Plan showing property lines, setbacks, North arrow, all structures (new/existing) with dimensions, driveway location, canals/rivers/roads, and parcel size; Roof or ground layout (plan view of the system and equipment); Line diagram: detailed line wiring diagram of the solar energy system and all electrical equipment; Racking/Mounting plans: detailed plans for racking, mounting, grounding, and bonding, including manufacturer specifications for fasteners and hardware; Labelling: in-color details of all labels used for the solar energy system and equipment; Manufacturer specifications/cut-sheets for all solar equipment (electrical and structural) — installation manuals are not accepted in lieu of manufacturer spec sheets, UNLESS the submitted plans are stamped and signed by both an Idaho-licensed electrical engineer and an Idaho-licensed structural engineer; Engineer Letter (required if solar is installed on a roof): signed by an Idaho-licensed engineer, certifying the roof will support the load of the solar energy system; Flood Plain Development Permit Application and Elevation Certificate required if the property is in a mapped flood plain; Electrical-connection work is permitted separately through the State of Idaho DOPL, not through this City/County building permit; Minimum 24 hours' notice required to request an inspection. If your project isn't listed, confirm with City of Rigby Building/Public Works Department (permit issuance & CO/CC) — building permit applications processed jointly with Jefferson County Planning, Zoning & Building under a Joint Powers Agreement at (208) 745-8111 before starting work.

Rigby's published plan-review target for a solar array building permit is 15–15 business days.

You'll need: Rigby Solar Array Building Permit Application; Complete Set of Plans (roof/ground layout, line diagram, racking/mounting); Idaho Contractor License (copy); Manufacturer Specifications/Cut-Sheets; Site Plan; Recorded Warranty Deed. Depending on your project, Rigby may also ask for: Engineer Letter (roof-mounted installations). See the required-documents checklist on this page for details on each.

Rigby requires 2 inspection(s) for a solar array building permit, in order: Roof/Structural Inspection (roof-mount only), Electrical Rough-In / Final (Idaho DOPL). Schedule each through City of Rigby Building/Public Works Department (permit issuance & CO/CC) — building permit applications processed jointly with Jefferson County Planning, Zoning & Building under a Joint Powers Agreement ((208) 745-8111).

Apply through City of Rigby Building/Public Works Department (permit issuance & CO/CC) — building permit applications processed jointly with Jefferson County Planning, Zoning & Building under a Joint Powers Agreement at 158 West Fremont Avenue, Rigby, ID 83442 (City Hall); building permit applications submitted via Jefferson County PZ&B, 210 Courthouse Way, Suite 170, Rigby, ID 83442. Phone: (208) 745-8111. Office hours: Mon–Fri, City Hall business hours; Jefferson County PZ&B Mon–Fri 9:00 AM – 5:00 PM. Official information: https://cityofrigby.gov/building-department/.

Rigby, Idaho has adopted: International Building Code (IBC), current Idaho State Edition — adopted by City of Rigby Ordinance 2011-551 (7-19-2011), amended by Ordinance 2021-619 (9-14-2021); City Code 9-1-1; International Residential Code (IRC), current Idaho State Edition — City Code 9-1-1; Jefferson County's own Rigby-specific application help documents state 'ALL CONSTRUCTION MUST COMPLY WITH THE 2018 IRC'; International Mechanical Code (IMC), current Idaho State Edition — City Code 9-1-1; International Fuel Gas Code (IFGC), current Idaho State Edition — City Code 9-1-1; International Energy Conservation Code (IECC), current Idaho State Edition — City Code 9-1-1; International Existing Building Code (IEBC), current Idaho State Edition — City Code 9-1-1; NFPA 70 National Electrical Code, as currently required by the State of Idaho — City Code 9-1-1; Idaho Plumbing Code, as currently required by the State of Idaho — City Code 9-1-1; governing electrical and plumbing code is 'that as most currently adopted by the State of Idaho Division of Building Safety' per 9-1-1(B)(2). Local amendments apply — see the Rigby overview page for the full list.

Yes — Jefferson County publishes a 'Rigby Solar Array Building Permit' help document specific to Rigby, submitted through the shared Jefferson County Cityworks portal. (A separately-hosted City of Rigby PDF titled 'Solar Permit' exists but its body text is actually a Fence Permit template and should not be used.)

The State of Idaho DOPL. Rigby and Jefferson County do not locally administer electrical permitting, so the electrical-connection scope of a solar array is a separate State of Idaho DOPL permit, distinct from this county-processed structural/building permit.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rigby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.