Solar Array Building Permit — Rigby, Idaho · Requirements sheet
Verified 2026-07-19 · Source: https://www.jcgov.us/DocumentCenter/View/3344/Rigby---Solar-Help-information
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Array Building Permit in Rigby, Idaho
Required for rooftop or ground-mounted solar photovoltaic (solar array) installations within Rigby city limits. Simpler permits such as deck, fence and garage/shed are obtained directly at City Hall, but solar is not: Jefferson County's dedicated 'Rigby Solar Array Building Permit' help document directs applicants to submit through the shared Jefferson County Planning, Zoning & Building Cityworks public portal, the same route used for Rigby's Residential Building Permit. Electrical-connection work is permitted separately through the State of Idaho DOPL, since Rigby and Jefferson County do not administer electrical trade permits locally.
Verified 2026-07-19 · Source
When you need this permit
- Submit through the Jefferson County Planning, Zoning & Building Permit & Application Portal (Cityworks), not a separate city-only process, per the county's own 'Rigby Solar Array Building Permit' help document
- Application data required: Parcel Number, Parcel Size, City of Rigby Zoning, Location Address, Subdivision/Lot/Block (if applicable), flood zone status, height to top of gable, height to bottom of eave, distance eave extends from structure, setbacks (North/East/West/South), distance from other buildings on the property, and canal/irrigation information if applicable
- All construction must comply with the 2018 IRC
- City of Rigby Zoning Certificate and a Recorded Warranty Deed must be attached
- Must attach a copy of an active Idaho Contractor License Contractor
- Site Plan showing property lines, setbacks, North arrow, all structures (new/existing) with dimensions, driveway location, canals/rivers/roads, and parcel size
- Roof or ground layout (plan view of the system and equipment)
- Line diagram: detailed line wiring diagram of the solar energy system and all electrical equipment
- Racking/Mounting plans: detailed plans for racking, mounting, grounding, and bonding, including manufacturer specifications for fasteners and hardware
- Labelling: in-color details of all labels used for the solar energy system and equipment
- Manufacturer specifications/cut-sheets for all solar equipment (electrical and structural) — installation manuals are not accepted in lieu of manufacturer spec sheets, UNLESS the submitted plans are stamped and signed by both an Idaho-licensed electrical engineer and an Idaho-licensed structural engineer
- Engineer Letter (required if solar is installed on a roof): signed by an Idaho-licensed engineer, certifying the roof will support the load of the solar energy system
- Flood Plain Development Permit Application and Elevation Certificate required if the property is in a mapped flood plain
- Electrical-connection work is permitted separately through the State of Idaho DOPL, not through this City/County building permit
- Minimum 24 hours' notice required to request an inspection
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 6 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No solar-specific dollar figure or valuation bracket is published in the Jefferson County-Wide Fee Schedule 2026, Exhibit A, or in the county's Rigby Solar Array Building Permit help document — the… Show full citationHide
No solar-specific dollar figure or valuation bracket is published in the Jefferson County-Wide Fee Schedule 2026, Exhibit A, or in the county's Rigby Solar Array Building Permit help document — the help document describes the required application data and attachments but states no fee table. The City of Rigby's own separate 'City of Rigby Solar Permit' PDF (cityofrigby.gov/wp-content/uploads/2024/05/Solar-Permit.pdf) is not usable as a fee source: on direct inspection, it is a template document whose body text is entirely a Fence Permit form (it repeats 'ISSUANCE OF THIS FENCE PERMIT...' and 'This is a Permit for the construction of a fence only' throughout, with only the header retitled to 'Solar Permit') — an apparent city document/template error, not a real solar-specific fee or process. Contact Jefferson County PZ&B, (208) 745-9220, or Rigby City Hall, (208) 745-8111, for a current fee quote.Review timeline
Inspection process
- 1
Roof/Structural Inspection (roof-mount only)
Verifies racking/mounting installation matches the approved engineered plans; minimum 24 hours' notice required to request
- 2
Electrical Rough-In / Final (Idaho DOPL)
Electrical connection work is inspected by the State of Idaho DOPL, since electrical permitting is not locally administered by Rigby or Jefferson County
See the full Rigby inspection guide — scheduling & re-inspection fees →
Tips
- Solar in Rigby goes through the SAME Jefferson County Cityworks portal used for the Residential Building Permit — do not assume it is a simple city-direct permit like Deck, Fence, or Garage/Shed; the county's own dedicated help document for Rigby solar applications directs applicants to the Cityworks portal.
- The City of Rigby's own separately-hosted 'Solar Permit' PDF form is a mislabeled Fence Permit template (its body text is entirely fence-permit language) — do not rely on it; use the Jefferson County Cityworks portal and the county's Rigby Solar Array Building Permit help document instead.
- An Engineer Letter certifying the roof can support the added load is required for any roof-mounted installation — budget for an Idaho-licensed engineer's review before applying.
- Manufacturer cut-sheets can be skipped only if your plan set is stamped and signed by both an Idaho-licensed electrical engineer AND an Idaho-licensed structural engineer.
- The electrical connection scope is a separate permit through Idaho DOPL — this county/city permit covers the structural, roof/ground-mount, and general building-code scope only.
- Budget a minimum of 15 business days for plan review, the same figure documented for Rigby's general Residential Building Permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rigby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Rigby's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Rigby yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Rigby lands. Privacy.
Other permits in Rigby
Solar Array Building Permit in other cities
Compare solar array building permit fees across Idaho →