Residential Building Permit (Single-Family Dwelling, Townhouse, New Construction & Additions) — Rigby, Idaho · Requirements sheet
Verified 2026-07-08 · Source: https://cityofrigby.gov/building-department/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (Single-Family Dwelling, Townhouse, New Construction & Additions) in Rigby, Idaho
Required for new single-family dwellings, townhouses, additions, and most accessory structures over 120 sq ft within Rigby city limits. Governed by Rigby City Code Title 9, Chapter 1 (adopting the IBC/IRC, current Idaho State Edition). Applications are submitted through the shared Jefferson County Planning, Zoning & Building Cityworks public portal using a Rigby-specific application help guide, and building inspections are performed by Jefferson County PZ&B inspectors under a Joint Powers Agreement with the city — but the City of Rigby retains its own Zoning Permit/Zoning Certificate requirement, handles water/sewer connection and sidewalk inspections directly, and issues the final Certificate of Occupancy or Certificate of Completion itself.
Verified 2026-07-08 · Source
When you need this permit
- Building permit required for new single-family dwellings, townhouses, additions, and accessory structures exceeding 120 sq ft within Rigby city limits (City Code 9-1-1; Rigby Zoning/Deck/Garage-Shed permit forms)
- All construction must comply with the current Idaho State Edition of the IRC (Jefferson County's Rigby-specific help document specifies the 2018 IRC)
- Register for and activate an account on the Jefferson County Cityworks public portal (Chrome or Firefox browser required) before applying
- City of Rigby Zoning Certificate must be obtained/attached as part of the building permit application (separate from, and a prerequisite to, the county-processed building permit)
- Submit Parcel Number, Parcel Size, City of Rigby Zoning, Location Address, flood zone status, full dimensional/square-footage data, and setback distances (N/E/W/S) as part of the online application
- Site Plan showing all property lines, setbacks, easements, North arrow, existing/proposed structures with dimensions, driveway location, and canals/rivers/roads
- Complete set of plans: floor plan(s) with room dimensions, footing/foundation details with steel requirements, truss layout, engineered truss design (stamped by an Idaho-licensed engineer), and all four building elevations
- Recorded warranty deed demonstrating ownership or authorization to build
- Idaho Contractor's License, or a completed Contractor Exemption form if owner-built Contractor
- Access Permit from Jefferson County Public Works (county roads) or Idaho Transportation Department (state highways), if applicable
- Septic Permit (approved) from Eastern Idaho Public Health, or an EIPH authorization-to-connect letter if tying into an existing/private sewer system, if applicable
- If in a mapped flood zone: Flood Plain Development Permit and Elevation Certificate
- Water and Sewer Connection Fees must be paid to the City of Rigby at time of building permit application; a water service pit is required for new construction and must pass city Public Works inspection before covering
- Mechanical (HVAC) permits and inspections for Rigby are processed by Jefferson County PZ&B as of June 1, 2026 (previously via Idaho DOPL). Plumbing and electrical permits/inspections remain with Idaho DOPL pending the county's build-out of journeyman-credentialed plumbing/electrical inspectors
- All required attachments must be individually labeled PDF files uploaded through the Cityworks portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 6 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Layout Inspection
Verifies structure layout on the site matches the approved site plan
- 2
Footing Inspection
Must occur before concrete is poured
- 3
Foundation Inspection
Must occur before concrete is poured
- 4
Water Service Pit / Water & Sewer Line Inspection (City of Rigby Public Works)
City-specific inspection before water/sewer lines are covered; curb stop and service pit must be exposed for this inspection before final grade
- 5
Sheathing Inspection
Building cannot be wrapped/house-wrapped before this inspection
- 6
Mechanical (HVAC) Rough-In Inspection
Performed by Jefferson County PZ&B inspectors as of June 1, 2026 (previously Idaho DOPL)
- 7
State Rough-In Inspections (Electrical, Plumbing)
Performed by Idaho DOPL — required before framing/insulation cover; plumbing and electrical had not yet transitioned to county inspectors as of the March 2026 reporting on the joint powers agreement
- 8
Framing Inspection
After structural framing complete
- 9
Insulation Inspection
Before drywall/wall cover
- 10
Drywall Inspection
Seams cannot be taped or mudded before this inspection
- 11
Sidewalk/Curb Base Inspection (City of Rigby Public Works)
Sidewalk base must be inspected by city Public Works before concrete is poured
- 12
State/County Final Inspections (Mechanical, Electrical, Plumbing)
Final mechanical sign-off by Jefferson County PZ&B; final electrical/plumbing sign-off by Idaho DOPL pending further county transition
- 13
Health Department Final
If applicable — e.g., septic system final from Eastern Idaho Public Health
- 14
Final Inspection by Jefferson County Building Department
Final building-code sign-off by county inspectors under the Joint Powers Agreement. Minimum 24 hours' notice required to schedule any inspection.
- 15
Final Grade and Certificate of Occupancy / Certificate of Completion Issuance (City of Rigby)
Property must be brought to final grade before CO/CC issuance. Per Jefferson County's own process document: 'If the property is within incorporated city limits, the documentation will be forwarded to the city, and they will issue the CO or CC' — Rigby, not the county, issues the final CO/CC.
See the full Rigby inspection guide — scheduling & re-inspection fees →
Tips
- Plan on a minimum of 15 business days for plan review after your application is submitted and confirmed complete — this is the county's official published figure from 'Building Permit Process: Plan Submittal to CO Issuance,' which governs the same Cityworks portal process Rigby applications go through. The same document separately commits to notifying you within 10 business days whether your application package is complete.
- Even though Jefferson County PZ&B processes the building permit application and performs building inspections, Rigby is NOT a pass-through jurisdiction: the city has its own City Code Title 9 (Building Code and Regulations), requires its own Zoning Permit/Zoning Certificate, handles water/sewer connection fees and inspections directly through its own Public Works Department, inspects sidewalks itself, and — critically — issues the final Certificate of Occupancy or Certificate of Completion itself rather than the county.
- As of June 1, 2026, Jefferson County PZ&B began processing new Mechanical (HVAC) permit applications for Rigby specifically, following a Joint Powers Agreement approved by Rigby City Council (discussed Feb. 19, 2026) and a subsequent public hearing/ordinance adoption (March 19, 2026) enabling the city to use county inspectors instead of state DOPL inspectors for this trade.
- Plumbing and electrical inspections for Rigby had NOT yet transitioned to Jefferson County as of the March 2026 reporting — the county had not yet hired inspectors meeting the state's journeyman-credential requirement for those trades. Budget for continued Idaho DOPL involvement on plumbing/electrical until further notice; confirm current status with Jefferson County PZ&B (208-745-9220) or Rigby City Hall (208-745-8111) before applying.
- You must register for and activate a Cityworks public portal account (Chrome or Firefox required) before you can submit any building permit application.
- Decks up to 120 sq ft only need a city-issued Deck Permit; decks over 120 sq ft require a full building permit through the county Cityworks process.
- Separate, simpler city-issued permits (obtained directly from Rigby City Hall, not the county Cityworks portal) exist for Fence, Garage/Shed, Sign, Solar (structural placement), and Sidewalk/Curb/Approach work — see cityofrigby.gov/building-department/.
- Water and Sewer Connection Fees are billed and collected by the City of Rigby directly, at the time of the building permit application — separate from the county's building permit fee invoice.
- Minimum 24 hours' notice is required to schedule any county inspection.
- The Plan Review Fee (15% of the building permit fee), GIS/Mapping Fee ($30), and Technology Fee ($30) must all be paid before departmental (zoning, floodplain, plan) review proceeds.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rigby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Rigby
Residential Building Permit (Single-Family Dwelling, Townhouse, New Construction & Additions) in other cities