Coeur d'Alene building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Coeur d'Alene, Idaho.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 710 E. Mullan Ave, Coeur d'Alene, ID 83814
- Phone
- (208) 769-2267
- Office hours
- Monday-Friday 8:00 a.m. to 5:00 p.m.; new building permit applications not accepted at the counter after 4:30 p.m. Inspection line (24 hours advance notice required): (208) 769-2391. Fax: (208) 769-2237.
- Website
- Official site
Published scheduling rules
- Call the inspection line at (208) 769-2391 at least 24 hours before the requested inspection. (Plumbing Permit)
Inspection sequence
Applies to: Re-Roof Permit
- 1
Roof Sheathing
Installation of new roof sheathing
- 2
Underlayment
Installation of underlayment after removal of existing roof covering and prior to installation of new roof covering
- 3
Existing Roof Covering (re-cover only)
Required prior to re-covering over an existing roof, if not stripping to sheathing
- 4
Final
After work is complete; schedule 24 hours in advance by calling (208) 769-2391
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before placing concrete or grout
- 2
Framing
Covering floor framing and interior sides of wall framing, rough electrical/plumbing/mechanical
- 3
Insulation/Gypsum
Taping gypsum wallboard of fire-resistive assemblies; applying stucco, E.I.F.S., and veneer finishes
- 4
Final Inspection / Certificate of Occupancy
Final inspection and issuance of Certificate of Occupancy required prior to occupying the building
Applies to: Plumbing Permit
- 1
Underground/Slab
Before concrete pour — pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed; backflow assemblies inspected
- 3
Final
All fixtures connected, no leaks, prior to Certificate of Occupancy
Applies to: Residential Addition / Remodel / Alteration Permit
- 1
Footing/Foundation
Required before placing concrete for deck posts, garage foundations, or addition footings
- 2
Framing
Structural framing, connection to existing structure, per approved plans
- 3
Final
All work complete per approved plans
Applies to: Demolition Permit
- 1
Sewer/Water Line Cap
Capped sewer and water lines must be inspected and signed off by the City Building Department before backfilling
- 2
Final
Final inspection required after the site is cleaned and graded
Applies to: Electrical Permit
- 1
Rough-In
Covering electrical work requires inspection approval first, per the FAQ's list of inspections required before covering work
- 2
Final
Final inspection required before issuance of Certificate of Occupancy; electrical service verified
Applies to: Fence and Retaining Wall Permit
- 1
Footing
Required for engineered retaining walls before backfill
- 2
Final
Completed fence/wall verified against approved plans
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and mechanical equipment rough-in before walls closed; gas piping pressure test before concealment
- 2
Final
Equipment operational; gas appliance shutoff and combustion air verified prior to Certificate of Occupancy
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Panel/racking attachment, roof penetration sealing, electrical connections, and interconnection point verified
Final inspection only: Electric Vehicle (EV) Charger / EVSE Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coeur d'Alene building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Coeur d'Alene building permits
Get alerts for Coeur d'Alene
We'll email you when Coeur d'Alene's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.