Electric Vehicle (EV) Charger / EVSE Permit — Coeur d'Alene, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://www.cdaid.org/government/departments/building-services/faq/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle (EV) Charger / EVSE Permit in Coeur d'Alene, Idaho
EVSE circuit installations in Coeur d'Alene are permitted under the City's standard Electrical Permit process. The City publishes no EV/EVSE-specific application or fee table separate from the general valuation-based Building Permit Fee Schedule — the Building Services Department's own FAQ page lists Electrical Permits as one of the Department's standard permit types but carries no EV/EVSE-specific content, mirroring the finding already documented for the solar-pv-permit entry.
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit required for new installations, alterations, extensions, and repairs of electrical wiring and equipment, including an EVSE circuit
- The City of Coeur d'Alene Building Services Department issues Electrical Permits directly (listed as one of the Department's own permit types on its FAQ)
- Electricians must hold a current State of Idaho electrical license issued through DOPL to obtain a City permit
- No EV-charger-specific application, checklist, or fee line item was located
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
City electrical inspection of the EVSE circuit and connection
See the full Coeur d'Alene inspection guide — scheduling & re-inspection fees →
Tips
- Coeur d'Alene has no EV/EVSE-specific fee -- an EVSE circuit is billed under the same general valuation-based Building Permit Fee Schedule used for any other electrical scope, with a $69.25 minimum.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coeur d'Alene building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Coeur d'Alene's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Coeur d'Alene yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Coeur d'Alene lands. Privacy.
Other permits in Coeur d'Alene
Electric Vehicle (EV) Charger / EVSE Permit in other cities
Compare electric vehicle (ev) charger / evse permit fees across Idaho →
Look up this fee in a different city →