Rexburg building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Rexburg, Idaho.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
35 N 1st East, Rexburg, ID 83440
Phone
(208) 372-2166
Office hours
City Hall Open Hours: M-Th 7:30 am - 5:30 pm, F 7:30 am - 12:30 pm. Main City switchboard: (208) 359-3020; Building Department direct line: (208) 372-2166.

Inspection sequence

Applies to: Residential Building Permit (Single Family Home / Townhome)

  1. 1

    Layout & Footing

    Lot corners staked before excavation; footing made after poles/piers set or trenched/basement excavated; forms and reinforcing in place

  2. 2

    Foundation

    Excavations for thickened slabs supporting bearing walls/partitions/structural supports/equipment; all forms and reinforcing steel in place

  3. 3

    Plumbing Underground

    Any plumbing under slab/concrete floor, inspected before concrete is poured; includes radon piping where applicable

  4. 4

    Plumbing Water & Sewer

    Checks city water and city sewer connections to the house

  5. 5

    Sheeting

    Inspected for nail separation, prior to plumbing/electrical/mechanical work

  6. 6

    Plumbing Rough-In

    Made prior to covering or concealment, before framing inspection

  7. 7

    HVAC (Mechanical) Rough-In & Gas Pressure Test

    Made prior to covering or concealment, before framing inspection

  8. 8

    Electrical Service

    Conductors/equipment delivering energy from the serving utility to the premises wiring system (not applicable to all projects)

  9. 9

    Electrical Rough-In

    Made prior to covering or concealment, before framing inspection

  10. 10

    Framing

    After roof, masonry, all framing, fire stopping, draft stopping, bracing, and house wrap are in place

  11. 11

    Insulation

    Outside envelope inspection for energy code compliance

  12. 12

    Drywall

    After interior wallboard is in place, before texture is applied and joints/fasteners are taped and finished

  13. 13

    Sidewalk

    6 inches of gravel fill in valley locations, 12 inches on hill locations; standard 5 ft width with broom finish; expansion joint filler at driveways and max 50 ft spacing

  14. 14

    Electrical Final

    Fixtures and wall covers in place, appliances in place, panel directory completed, ready for occupancy

  15. 15

    Plumbing Final

    All systems in place, fixtures set, ready for occupancy

  16. 16

    HVAC (Mechanical) Final

    All systems in place, fixtures set, ready for occupancy

  17. 17

    Building Final

    Made after all other finals have passed; building completed and ready for occupancy

Applies to: Multi-Family Residence / Commercial Building Permit

  1. 1

    Layout & Footing

    Lot corners staked before excavation; footing made after poles/piers set or trenched/basement excavated; forms and reinforcing in place

  2. 2

    Foundation

    Excavations for thickened slabs supporting bearing walls/partitions/structural supports/equipment; all forms and reinforcing steel in place

  3. 3

    Plumbing Underground

    Any plumbing under slab/concrete floor, inspected before concrete is poured

  4. 4

    Sheeting

    Inspected for nail separation, prior to plumbing/electrical/mechanical work

  5. 5

    Plumbing / HVAC / Electrical Rough-In

    Made prior to covering or concealment, before framing inspection

  6. 6

    Framing

    After roof, masonry, all framing, fire stopping, draft stopping, bracing, and house wrap are in place

  7. 7

    Insulation

    Outside envelope inspection for energy code compliance

  8. 8

    Drywall

    After interior wallboard is in place, before texture and taping/finishing

  9. 9

    Electrical / Plumbing / HVAC Final

    All systems in place, fixtures set, ready for occupancy

  10. 10

    Building Final

    Made after all other finals have passed; building completed and ready for occupancy

Applies to: Plumbing Permit

  1. 1

    Plumbing Underground

    Any plumbing under slab/concrete floor, inspected before concrete is poured; includes radon piping where applicable

  2. 2

    Plumbing Water & Sewer

    Checks city water and city sewer connections to the structure

  3. 3

    Plumbing Rough-In

    Made prior to covering or concealment, before framing inspection

  4. 4

    Plumbing Final

    All systems in place, fixtures set, ready for occupancy

Applies to: Electrical Permit

  1. 1

    Electrical Service

    Conductors/equipment delivering energy from the serving utility to the premises wiring system (not applicable to all projects)

  2. 2

    Electrical Rough-In

    Made prior to covering or concealment, before framing inspection

  3. 3

    Electrical Final

    Fixtures and wall covers in place, appliances in place, panel directory completed, ready for occupancy

Applies to: Solar Panels Permit

  1. 1

    Electrical Rough-In

    Wiring, grounding, and component listing verified before covering or energizing (City electrical inspector, not DOPL)

  2. 2

    Electrical Final

    Panel labeling, working clearances, and system operation verified (City electrical inspector)

  3. 3

    Building Final

    Roof-mounting and structural attachment verified against the stamped engineering plans (City building inspector)

Applies to: Duplex Conversion Permit

  1. 1

    Life Safety Inspection

    Verifies smoke/CO detectors, fire separation, fire extinguisher, egress windows, and other life-safety code items are met

  2. 2

    Building Final

    Made after all other finals have passed; verifies the converted structure meets current code for two-unit occupancy

Applies to: EV Charging Station Permit (City Electrical Permit)

  1. 1

    Electrical Rough-In (if applicable)

    Required only if new circuit wiring is enclosed before final; wiring, grounding, and component listing verified (City electrical inspector, not DOPL)

  2. 2

    Electrical Final

    EVSE breaker sizing, GFCI protection (where applicable), labeling, working clearances, and charger mounting verified against the 2023 NEC (City electrical inspector)

Applies to: Mechanical / HVAC Permit

  1. 1

    HVAC (Mechanical) Rough-In & Gas Pressure Test

    Made prior to covering or concealment, before framing inspection

  2. 2

    HVAC (Mechanical) Final

    All systems in place, fixtures set, ready for occupancy

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rexburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Rexburg building permits

Get alerts for Rexburg

We'll email you when Rexburg's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.