EV Charging Station Permit (City Electrical Permit) in Rexburg, Idaho
Required for installation of a Level 2 or higher electric vehicle charging station within Rexburg city limits. Rexburg's Building Department self-administers electrical permitting directly rather than routing it through the State of Idaho DOPL as most Idaho cities do, using its own 'Mechanical, Electrical or Plumbing Miscellaneous' permit application for installation or upgrade work that is not part of new construction. The same applies to solar PV work here.
Verified 2026-07-20 · Source
When you need this permit
- Submit the City's Mechanical, Electrical or Plumbing (MEP) Miscellaneous Project application via the Rexburg Public Permit Application Portal (apply.rexburg.org/publicapp)
- Electrical connection work is governed by the 2023 NEC (including Article 625, Electric Vehicle Power Transfer System) as adopted by the City and is inspected by the City's own dedicated electrical inspector, not Idaho DOPL
- A dedicated branch circuit sized to the EVSE manufacturer's specifications is required; GFCI protection applies per NEC 625 where the EVSE is cord-and-plug connected
- If the charger install requires a panel/service upgrade or accompanies new construction, that scope is submitted with the applicable new-construction Building Permit application instead of the standalone MEP Misc. application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No dedicated dollar figure for EV charger/EVSE circuits is published on the City's Building Permit Applications page, Electrical Information page, or either residential Fee Estimator — consistent… Show full citationHide
No dedicated dollar figure for EV charger/EVSE circuits is published on the City's Building Permit Applications page, Electrical Information page, or either residential Fee Estimator — consistent with the solar-pv-permit entry's identical finding that the standalone MEP Misc. Project fee is not published as a static figure online. Third-party permit-cost aggregators (not a primary source) estimate Rexburg electrical permits generally in the $37-$450 range depending on project scope and valuation. Contact the Building Department at (208) 372-2166 or building@rexburg.org for a current quote.Review timeline
Inspection process
- 1
Electrical Rough-In (if applicable)
Required only if new circuit wiring is enclosed before final; wiring, grounding, and component listing verified (City electrical inspector, not DOPL)
- 2
Electrical Final
EVSE breaker sizing, GFCI protection (where applicable), labeling, working clearances, and charger mounting verified against the 2023 NEC (City electrical inspector)
See the full Rexburg inspection guide — scheduling & re-inspection fees →
Tips
- EV charger electrical work in Rexburg is a City permit rather than a State of Idaho DOPL permit — the Building Department's own dedicated electrical inspector handles it in-house, as with solar PV work here. Apply to the City.
- Use the standalone MEP Miscellaneous Project application for a stand-alone EVSE circuit retrofit; for an EV charger installed with new construction, coordinate with the Single Family or Multi-Family Building Permit application instead.
- No fee table is published for MEP Miscellaneous electrical work — call the Building Department, (208) 372-2166, for a current cost estimate before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rexburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Rexburg's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Rexburg yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Rexburg lands. Privacy.
Other permits in Rexburg
EV Charging Station Permit (City Electrical Permit) in other cities
Compare ev charging station permit (city electrical permit) fees across Idaho →
Look up this fee in a different city →
Related guides
Now live
Build your Rexburg project checklist
Describe your project once and get every permit, document, and fee it triggers in Rexburg — in one checklist. Free, for any city and any number of projects.
Get started →