Multi-Family Residence / Commercial Building Permit in Rexburg, Idaho

Required for new multi-family residential (apartment) and commercial building construction in Rexburg, reviewed against the 2018 IBC and 2018 IECC (Commercial) as adopted by the City. Commercial plans must be stamped by a licensed Idaho architect or engineer.

Verified 2026-07-04 · Source

When you need this permit

  • Building permit required for new multi-family residential and commercial construction
  • Plans reviewed against the 2018 IBC and 2018 IECC (Commercial) as adopted by the City of Rexburg
  • Commercial project plans must be stamped by a licensed Idaho architect or engineer
  • Multi-family fee estimate is based on R-2 Occupancy and Type VB Construction per the IBC Building Valuation table
  • Plan submittals must meet the City's Digital Plan Submission Standards (vector-based PDF, bookmarked pages, architect/engineer stamps, title sheet with square footage/occupancy group/construction type/scope of work)
  • Create an account on the City's Public Portal (apply.rexburg.org/publicapp) to submit the application online

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Multi-Family Building Permit Fee (estimate) — 4-Plex, 3,600 sq ftCity of Rexburg Multi Family Residence Fee Estimator (building fees only, average estimate)
$3,500.00
Multi-Family Building Permit Fee (estimate) — 6-Plex, 6,000 sq ftCity of Rexburg Multi Family Residence Fee Estimator
$5,200.00
Multi-Family Building Permit Fee (estimate) — 12-Plex, 12,000 sq ftCity of Rexburg Multi Family Residence Fee Estimator
$8,700.00
Multi-Family Building Permit Fee (estimate) — 20-Unit, 20,000 sq ftCity of Rexburg Multi Family Residence Fee Estimator
$13,100.00
Multi-Family Building Permit Fee (estimate) — 30-Unit, 30,000 sq ftCity of Rexburg Multi Family Residence Fee Estimator
$18,700.00
Plan Review FeeCity of Rexburg Multi Family Residence Fee Estimator
10% of the calculated Building Permit fee
MEP Cost (per discipline: mechanical, electrical, plumbing) — 4 units + 1 buildingCity of Rexburg Multi Family Residence Fee Estimator; formula is $65.00 per unit + $130.00 per building
$390.00
MEP Cost (per discipline) — 6 units + 1 buildingCity of Rexburg Multi Family Residence Fee Estimator
$520.00
MEP Cost (per discipline) — 12 units + 1 buildingCity of Rexburg Multi Family Residence Fee Estimator
$910.00
MEP Cost (per discipline) — 20 units + 1 buildingCity of Rexburg Multi Family Residence Fee Estimator
$1,430.00
MEP Cost (per discipline) — 30 units + 1 buildingCity of Rexburg Multi Family Residence Fee Estimator
$2,080.00
Water Meter — 3/4 inchCity of Rexburg Multi Family Residence Fee Estimator
$732.00
Water Meter — 1 inchCity of Rexburg Multi Family Residence Fee Estimator
$936.00
Water Meter — 1.5 inch, outsideCity of Rexburg Multi Family Residence Fee Estimator
$1,489.00
Water Meter — 1.5 inch, insideCity of Rexburg Multi Family Residence Fee Estimator
$1,217.00
Water Meter — 2 inch, outsideCity of Rexburg Multi Family Residence Fee Estimator
$3,269.00
Water Meter — 2 inch, insideCity of Rexburg Multi Family Residence Fee Estimator
$2,927.00
Commercial Building Permit FeeThe City's Building Permit Fee Estimator page has a dedicated 'Commercial Building Fees (avg)' section, but the underlying dollar figures are rendered in an interactive/dynamic table that could not be extracted as static text from the page; contact the Building Department at (208) 372-2166 or building@rexburg.org for current commercial fee figures.
Not published — contact the department
Impact Fees (streets, parks/trails, police, fire) and Capacity Fees (water, sewer)Determined by Public Works; not published as a static figure on the Building Department's fee estimator pages ('IMPACT FEES TO BE DETERMINED BY PUBLIC WORKS'). Contact Public Works or the Chief Finance Officer (finance@rexburg.org, (208) 372-2343) for current amounts.
Not published — contact the department

Review timeline

Plan reviewRexburg’s published plan-review target
Up to 10 business days

How long did your Multi-Family Residence / Commercial Building Permit permit actually take in Rexburg?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Layout & Footing

    Lot corners staked before excavation; footing made after poles/piers set or trenched/basement excavated; forms and reinforcing in place

  2. 2

    Foundation

    Excavations for thickened slabs supporting bearing walls/partitions/structural supports/equipment; all forms and reinforcing steel in place

  3. 3

    Plumbing Underground

    Any plumbing under slab/concrete floor, inspected before concrete is poured

  4. 4

    Sheeting

    Inspected for nail separation, prior to plumbing/electrical/mechanical work

  5. 5

    Plumbing / HVAC / Electrical Rough-In

    Made prior to covering or concealment, before framing inspection

  6. 6

    Framing

    After roof, masonry, all framing, fire stopping, draft stopping, bracing, and house wrap are in place

  7. 7

    Insulation

    Outside envelope inspection for energy code compliance

  8. 8

    Drywall

    After interior wallboard is in place, before texture and taping/finishing

  9. 9

    Electrical / Plumbing / HVAC Final

    All systems in place, fixtures set, ready for occupancy

  10. 10

    Building Final

    Made after all other finals have passed; building completed and ready for occupancy

See the full Rexburg inspection guide — scheduling & re-inspection fees →

Tips

  • The multi-family fee estimate is explicitly based on R-2 Occupancy, Type VB Construction from the IBC Building Valuation table — a different occupancy/construction type will change the actual valuation-based fee.
  • Water meter fees for multi-family projects are itemized separately by meter size and inside/outside placement.
  • Commercial building fee figures are published on the City's Fee Estimator page but rendered in a dynamic table not extractable as static text; call the Building Department directly for current numbers.
  • Commercial project plans must be stamped by a licensed Idaho architect or engineer before submission.

Frequently asked questions

Rexburg requires a multi-family residence / commercial building permit for: Building permit required for new multi-family residential and commercial construction; Plans reviewed against the 2018 IBC and 2018 IECC (Commercial) as adopted by the City of Rexburg; Commercial project plans must be stamped by a licensed Idaho architect or engineer; Multi-family fee estimate is based on R-2 Occupancy and Type VB Construction per the IBC Building Valuation table; Plan submittals must meet the City's Digital Plan Submission Standards (vector-based PDF, bookmarked pages, architect/engineer stamps, title sheet with square footage/occupancy group/construction type/scope of work); Create an account on the City's Public Portal (apply.rexburg.org/publicapp) to submit the application online. If your project isn't listed, confirm with City of Rexburg Building Department at (208) 372-2166 before starting work.

In Rexburg, the published Multi-Family Building Permit Fee (estimate) — 4-Plex, 3,600 sq ft is: $3,500.00. Additional published fees: Multi-Family Building Permit Fee (estimate) — 6-Plex, 6,000 sq ft — $5,200.00; Multi-Family Building Permit Fee (estimate) — 12-Plex, 12,000 sq ft — $8,700.00; Multi-Family Building Permit Fee (estimate) — 20-Unit, 20,000 sq ft — $13,100.00; Multi-Family Building Permit Fee (estimate) — 30-Unit, 30,000 sq ft — $18,700.00; Plan Review Fee — 10% of the calculated Building Permit fee; MEP Cost (per discipline: mechanical, electrical, plumbing) — 4 units + 1 building — $390.00; MEP Cost (per discipline) — 6 units + 1 building — $520.00; MEP Cost (per discipline) — 12 units + 1 building — $910.00; MEP Cost (per discipline) — 20 units + 1 building — $1,430.00; MEP Cost (per discipline) — 30 units + 1 building — $2,080.00; Water Meter — 3/4 inch — $732.00; Water Meter — 1 inch — $936.00; Water Meter — 1.5 inch, outside — $1,489.00; Water Meter — 1.5 inch, inside — $1,217.00; Water Meter — 2 inch, outside — $3,269.00; Water Meter — 2 inch, inside — $2,927.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Rexburg's published plan-review target for a multi-family residence / commercial building permit is Up to 10 business days.

You'll need: Apartment Buildings / Commercial Buildings Permit Application; Full Construction Drawing Set (stamped). See the required-documents checklist on this page for details on each.

Rexburg requires 10 inspection(s) for a multi-family residence / commercial building permit, in order: Layout & Footing, Foundation, Plumbing Underground, Sheeting, Plumbing / HVAC / Electrical Rough-In, Framing, Insulation, Drywall, Electrical / Plumbing / HVAC Final, Building Final. Schedule each through City of Rexburg Building Department ((208) 372-2166).

Apply through City of Rexburg Building Department at 35 N 1st East, Rexburg, ID 83440. Phone: (208) 372-2166, email: building@rexburg.org. Office hours: City Hall Open Hours: M-Th 7:30 am - 5:30 pm, F 7:30 am - 12:30 pm. Main City switchboard: (208) 359-3020; Building Department direct line: (208) 372-2166.. Official information: https://www.rexburg.org/o/cor/page/building.

Rexburg, Idaho has adopted: The City of Rexburg operates its own Building Department, which handles ALL trade permitting (building, mechanical, electrical, plumbing, and fire) in-house — it is not a DOPL-administered jurisdiction for permit issuance. The Building Official 'enforces and interprets the building code,' 'supervises the mechanical, electrical, plumbing, and fire inspectors,' and the Building Department's stated scope explicitly covers mechanical, electrical, and plumbing programs as sub-programs of the Building Department itself, each with dedicated per-discipline permit fees. Source: City of Rexburg Building page (rexburg.org/o/cor/page/building).; 2018 International Building Code (IBC), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page (rexburg.org/o/cor/page/codes-standards).; 2018 International Residential Code (IRC), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2023 National Electrical Code (NEC / NFPA 70), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page; also referenced on the Electrical Information page.; 2018 International Mechanical Code (IMC), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2017 Idaho Plumbing Code (IAPMO), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2018 International Fuel Gas Code (IFGC), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2018 International Energy Conservation Code (IECC) — both the Commercial and Residential chapters, adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2018 International Existing Building Code (IEBC), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2018 International Fire Code (IFC), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; 2016 NFPA 72 (National Fire Alarm and Signaling Code), adopted by the City of Rexburg. Source: City of Rexburg Codes & Standards page.; Plans submitted for commercial projects must be stamped by a licensed Idaho architect or engineer. Source: City of Rexburg Codes & Standards page.; The permitting process takes up to 10 business days from initial application to issuance of the permit; the process can be longer depending on backlog; the permit process is on a first-come, first-served basis. Source: City of Rexburg Codes & Standards page.; Rexburg Development Code (Title/Code 1200) governs zoning, including short-term rental registration and duplex-conversion zoning eligibility (density-based lot-size minimums by zone). Source: Rexburg Development Code online, rexburg.municipalcodeonline.com/book?type=development.. Local amendments apply — see the Rexburg overview page for the full list.

This is addressed on the City's Building FAQ page, but the specific answer text is rendered as a JS-collapsed accordion not extractable as static text; generally, commercial project plans submitted to the City must be stamped by a licensed Idaho architect or engineer per the Codes & Standards page. Contact the Building Department at (208) 372-2166 to confirm any owner-design exceptions.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rexburg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.