Fruitland building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Fruitland, Idaho.
Verified 2026-07-07 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 200 S. Whitley Drive, Fruitland, ID 83619
- Phone
- (208) 452-4946
- Office hours
- Inspections requested by phone; calls received before 3:00 PM are scheduled for the next business day, calls after 3:00 PM scheduled for the second business day. Building Official: Danny Little (dlittle@fruitland.org); Building Inspector: Brandon Tarvin (btarvin@fruitland.org); Building Clerk: Beth Earles (bearles@fruitland.org).
- Website
- Official site
Inspection sequence
Applies to: Building Permit (New Construction, Additions, Remodels)
- 1
Footing
Before concrete pour
- 2
Foundation/Stem Wall
Foundation or stem wall inspection
- 3
Under Floor
Under-floor framing/systems inspection prior to floor cover
- 4
Shear Wall
Shear wall nailing/hardware inspection
- 5
Framing
Performed together with the mechanical rough-in inspection
- 6
Air Seal
Air sealing inspection prior to insulation
- 7
Insulation
Insulation inspection
- 8
Final
Performed together with the mechanical final inspection
Applies to: Commercial Building Permit (New Construction)
- 1
Footing
Before concrete pour
- 2
Foundation/Stem Wall
Foundation or stem wall inspection
- 3
Framing
Performed together with the mechanical rough-in inspection
- 4
Insulation
Insulation inspection
- 5
Final
Performed together with the mechanical final inspection; verifies compliance with approved commercial plans, including any required fire protection system
Applies to: Mechanical Permit
- 1
Pressure Test
Gas line/system pressure test
- 2
Rough-In/Piping
Performed together with the framing inspection
- 3
Final
Performed together with the final building inspection
Applies to: Commercial Tenant Improvement Permit (Remodel of Existing Commercial Space)
- 1
Framing
If the scope includes framing/wall changes; performed together with the mechanical rough-in inspection where applicable
- 2
Final
Verifies the completed tenant improvement matches approved plans, including any required fire protection system
Applies to: Residential Solar Photovoltaic (PV) Permit
- 1
State Electrical Inspection
Performed by DOPL, covering interconnection wiring, disconnects, and equipment grounding per the adopted NEC edition
- 2
City Building Final
Racking/mounting attachment and roof penetration sealing verified against approved City building permit plans
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fruitland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Fruitland building permits