Department contacts, adopted codes, permit types, fees, and gotchas for Fruitland, Idaho.

Last verified 2026-07-07 · Source · Embed this page’s badge · Version history

Building department

Address
200 S. Whitley Drive, Fruitland, ID 83619
Phone
(208) 452-4946
Office hours
Inspections requested by phone; calls received before 3:00 PM are scheduled for the next business day, calls after 3:00 PM scheduled for the second business day. Building Official: Danny Little (dlittle@fruitland.org); Building Inspector: Brandon Tarvin (btarvin@fruitland.org); Building Clerk: Beth Earles (bearles@fruitland.org).

Inspection guide

See how inspections work in Fruitland — sequence, scheduling & re-inspection fees.

Codes adopted

Idaho adopts a statewide baseline building code set under the Idaho Building Code Act (Idaho Code Title 39, Chapter 41) and IDAPA rules administered by the Idaho Division of Occupational and Professional Licenses (DOPL). Effective January 1, 2021, the statewide baseline includes the 2018 International Building Code (IBC), 2020 Idaho Residential Code (based on the 2018 IRC Parts I–III and IX with Idaho amendments), 2020 Idaho Energy Conservation Code (based on the 2018 IECC with Idaho amendments), 2018 International Existing Building Code (IEBC), 2018 International Mechanical Code (IMC), 2018 International Fuel Gas Code (IFGC), and 2018 International Fire Code (IFC). The National Electrical Code is adopted separately by the Idaho Electrical Board (IDAPA 24.39.10), not bundled with the building code: Idaho enforces the 2023 NEC, effective July 1, 2024 (the state used the 2017 NEC with amendments before that and skipped the 2020 edition). Local jurisdictions must enforce the state baseline and may adopt amendments only where those amendments are at least as stringent as the state-adopted editions; local amendments may not be less restrictive. Enforcement is local — each city or county issues permits and performs inspections. Always confirm the current adopted edition and any local amendments with your specific jurisdiction before submitting plans.

  • 2018 International Building Code (IBC)
  • 2018 International Residential Code (IRC)
  • 2018 International Energy Conservation Code (IECC)
  • 2018 International Mechanical Code (IMC)
  • 2012 International Fuel Gas Code (IFGC)
  • 2015 International Fire Code (IFC)
  • Current version of the Uniform Code for the Abatement of Dangerous Buildings
  • Current version of the Uniform Sign Code
  • Plumbing and electrical permits/inspections are administered directly by the State of Idaho, not the City of Fruitland

Permit types & fees

New residential construction activity

New privately-owned residential construction only

Housing units authorized by building permits for new privately-owned residential construction — this is not total permit volume (no commercial permits or remodels).

Latest month (2026-05)
3units

3 buildings · $1M valuation

Trailing 12 months
40units

12 of 12 months reported · #38 in Idaho coverage by units

Year to date (2026 YTD through 2026-05)
16units

16 buildings · $5.6M valuation

5 month(s) reported to Census

Full year 2025
43units

43 buildings · $13.5M valuation

Source: U.S. Census Bureau, Building Permits Survey (BPS), 2026-05 vintage. Census survey data — separate from the permit-requirements verification above. All Idaho building activity

Tips & gotchas

  • Fruitland does NOT issue its own electrical or plumbing trade permits — those are handled directly by the State of Idaho. The City's own Fee Schedule has no electrical/plumbing line items, and the Building Department page explicitly states 'All required plumbing and electrical permits must be obtained from the State of Idaho.'
  • There is no separate 'Fence Permit' or 'Demolition Permit' issued by the City of Fruitland. Fence construction is governed as a zoning matter (height limits: 36 inches in front yards, 7 feet elsewhere without a conditional use permit; electric fences prohibited; barbed wire restricted — City Code § 10-9-7) without its own building permit category, and demolition work is not tracked as a distinct permit type in the City's own 2025 Annual Building Report — it falls under the general Building Permit process and the adopted Uniform Code for the Abatement of Dangerous Buildings where applicable.
  • Re-roofing is likewise not a standalone tracked permit category; it is filed and fee-calculated as a general Building Permit (Type of Work: Remodel or Other) using the standard valuation table.
  • Idaho Code § 39-4117 (effective 2025, statewide) sets a 10-business-day (residential) / 20-business-day (commercial) statutory clock for the City to determine whether a submitted application is complete — this is NOT a guarantee of full plan approval within that window, and Fruitland has not published its own longer full-review SLA.
  • A building permit issued in Fruitland is valid for only 180 days — noticeably shorter than many other Idaho cities' 1-year-plus terms. Track your extension eligibility (first extension free if any work is done; second extension requires 25%+ completion) to avoid the project being deemed abandoned.
  • Design criteria (Seismic Category C, 115 mph wind load, 25 psf ground snow load, 24-inch frost depth, no required ice barrier underlayment) are lower-severity than many higher-elevation/higher-latitude Idaho jurisdictions (e.g., Blaine County's Hailey at 120 psf snow load and IECC Climate Zone 16) — reflecting Fruitland's low-elevation Snake/Payette River valley location in the Treasure Valley.
  • There is no fee for commercial/industrial plan review of any kind in Fruitland (construction review or fire/life-safety review), which is unusual compared to many peer cities that charge a percentage-of-permit plan-check fee.
  • Construction commenced without first obtaining a required permit triggers a civil penalty equal to twice the normal permit fee, payable before the permit can be issued (City Code § 9-1-2(G)).

Related guides

Comparable nearby cities

Payette
Both in Payette County4 shared permit types~4 mi away
Compare fees →
Cascade
5 shared permit typesBoth on the 2018 International Building Code (IBC)~55 mi away
Compare fees →
Emmett
4 shared permit typesBoth on the 2018 International Residential Code (IRC)~24 mi away
Compare fees →