Building Permit (New Construction, Additions, Remodels) in Fruitland, Idaho

Required for new dwellings (single-family, townhouse, duplex), commercial construction, additions, remodels, and detached shop/storage buildings in Fruitland. Confirmed in the City's own 2025 Annual Building Report as the most frequently issued permit category (New Construction, Remodel, and Addition types tracked separately from Commercial).

Verified 2026-07-07 · Source

When you need this permit

  • New dwellings: two (2) sets of plans/specifications on a minimum 24 in. x 36 in. sheet, drawn to scale (minimum 1/20 for site plan), no markups — site plan, footing/foundation plan, floor plan, wall section, elevations (front/back/both sides), and a Manual J, Manual D, and Manual S compliance report
  • Additions/remodels/repairs: two (2) sets of plans/specifications — site plan showing existing and new structures with setbacks and dimensions, detailed materials list, detailed construction drawing, foundation elevations at top of foundation, north arrow
  • Idaho Code Chapter 22 of Title 55 requires excavators to call 811 or 1-800-342-1585 not less than 2 business days nor more than 10 business days before excavation begins
  • A separate City of Fruitland Mechanical Permit is required for HVAC installation; plumbing and electrical permits are obtained directly from the State of Idaho, not the City

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — total valuation $1.00–$500.00City of Fruitland Fee Schedule, adopted September 8, 2025 by Resolution No. 2025-08; valuation calculated using the February 2025 ICC Building Valuation Data
$23.50
Building Permit — total valuation $501.00–$2,000.00
$23.50 for the first $500.00, plus $3.05 for each additional $100.00 or fraction thereof, to and including $2,000.00
Building Permit — total valuation $2,001.00–$25,000.00
$69.25 for the first $2,000.00, plus $14.00 for each additional $1,000.00 or fraction thereof, to and including $25,000.00
Building Permit — total valuation $25,001.00–$50,000.00
$391.75 for the first $25,000.00, plus $10.10 for each additional $1,000.00 or fraction thereof, to and including $50,000.00
Building Permit — total valuation $50,001.00–$100,000.00
$643.75 for the first $50,000.00, plus $7.00 for each additional $1,000.00 or fraction thereof, to and including $100,000.00
Building Permit — total valuation $100,001.00–$500,000.00
$993.75 for the first $100,000.00, plus $5.60 for each additional $1,000.00 or fraction thereof, to and including $500,000.00
Building Permit — total valuation $500,001.00–$1,000,000.00
$3,233.75 for the first $500,000.00, plus $4.75 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00
Building Permit — total valuation $1,000,001.00 and up
$5,608.75 for the first $1,000,000.00, plus $3.65 for each additional $1,000.00 or fraction thereof
Plan ReviewCity of Fruitland Fee Schedule effective September 8, 2025 — no plan review fee is charged
$0.00
Fire and Life Safety Plan ReviewCity of Fruitland Fee Schedule effective September 8, 2025; confirmed in City Code § 9-1-2(F) that no fee is charged for either type of commercial/industrial plan review
$0.00
Re-InspectionCity of Fruitland Fee Schedule effective September 8, 2025
$65.00
Construction without a PermitCity of Fruitland Fee Schedule effective September 8, 2025; codified as a civil penalty at City Code § 9-1-2(G), payable before a permit is issued
Amount equal to twice the cost of the permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Building Permit (New Construction, Additions, Remodels) permit actually take in Fruitland?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing

    Before concrete pour

  2. 2

    Foundation/Stem Wall

    Foundation or stem wall inspection

  3. 3

    Under Floor

    Under-floor framing/systems inspection prior to floor cover

  4. 4

    Shear Wall

    Shear wall nailing/hardware inspection

  5. 5

    Framing

    Performed together with the mechanical rough-in inspection

  6. 6

    Air Seal

    Air sealing inspection prior to insulation

  7. 7

    Insulation

    Insulation inspection

  8. 8

    Final

    Performed together with the mechanical final inspection

See the full Fruitland inspection guide — scheduling & re-inspection fees →

Tips

  • Fruitland's own 2025 Annual Building Report shows the Building Permit category tracked by Type of Work (New Construction, Remodel, Addition, Other) rather than by separate named permits for fences, demolition, or re-roofing — those scopes are filed and fee-calculated as a general Building Permit under the applicable valuation table, or as a $25 Siting Permit if they qualify as an accessory structure.
  • There is no fee for either commercial construction plan review or fire/life-safety plan review in Fruitland — both are published at $0.00 on the Fee Schedule and confirmed in City Code § 9-1-2(F).
  • A building permit is valid for only 180 days; a first 180-day extension is issued at no charge if any portion of the project is complete at expiration; a second 180-day extension requires that a 'substantial' (25%+) portion of the work be complete; beyond that, the project is deemed abandoned and the site must be restored unless the City Council approves continued work after a hearing.
  • Design criteria (Seismic Category C, 115 mph wind load, 25 psf basic ground snow load, 24-inch frost depth, no ice-barrier-underlayment requirement) are published directly by the City on both the Building Department webpage and the Residential Building Permit Submittal Checklist — confirmed identical on both official sources.
  • Framing inspections are combined with the mechanical rough-in inspection, and final building inspections are combined with the mechanical final inspection — schedule accordingly to avoid duplicate trips.

Frequently asked questions

Yes. Additions, remodels, and repairs require a Building Permit with two sets of plans/specifications showing the site plan, materials list, construction details, foundation elevations, and north arrow, submitted to the City of Fruitland Building Department.

In Fruitland, the published Building Permit — total valuation $1.00–$500.00 is: $23.50. Additional published fees: Building Permit — total valuation $501.00–$2,000.00 — $23.50 for the first $500.00, plus $3.05 for each additional $100.00 or fraction thereof, to and including $2,000.00; Building Permit — total valuation $2,001.00–$25,000.00 — $69.25 for the first $2,000.00, plus $14.00 for each additional $1,000.00 or fraction thereof, to and including $25,000.00; Building Permit — total valuation $25,001.00–$50,000.00 — $391.75 for the first $25,000.00, plus $10.10 for each additional $1,000.00 or fraction thereof, to and including $50,000.00; Building Permit — total valuation $50,001.00–$100,000.00 — $643.75 for the first $50,000.00, plus $7.00 for each additional $1,000.00 or fraction thereof, to and including $100,000.00; Building Permit — total valuation $100,001.00–$500,000.00 — $993.75 for the first $100,000.00, plus $5.60 for each additional $1,000.00 or fraction thereof, to and including $500,000.00; Building Permit — total valuation $500,001.00–$1,000,000.00 — $3,233.75 for the first $500,000.00, plus $4.75 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00; Building Permit — total valuation $1,000,001.00 and up — $5,608.75 for the first $1,000,000.00, plus $3.65 for each additional $1,000.00 or fraction thereof; Plan Review — $0.00; Fire and Life Safety Plan Review — $0.00; Re-Inspection — $65.00; Construction without a Permit — Amount equal to twice the cost of the permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

180 days from issuance. If the project is not finished in that time, a first 180-day extension issues at no charge if any work is complete; a second 180-day extension is available only if at least 25% of the project is complete. After that, the project is considered abandoned absent City Council approval.

You'll need: Building Permit Application; Residential Building Permit Submittal Checklist. Depending on your project, Fruitland may also ask for: Commercial Building Project Submittal Checklist; Plot Plan Example For Non-Habitable Structures. See the required-documents checklist on this page for details on each.

Fruitland requires 8 inspection(s) for a building permit (new construction, additions, remodels), in order: Footing, Foundation/Stem Wall, Under Floor, Shear Wall, Framing, Air Seal, Insulation, Final. Schedule each through City of Fruitland Building Department ((208) 452-4946).

Apply through City of Fruitland Building Department at 200 S. Whitley Drive, Fruitland, ID 83619. Phone: (208) 452-4946, email: bearles@fruitland.org. Office hours: Inspections requested by phone; calls received before 3:00 PM are scheduled for the next business day, calls after 3:00 PM scheduled for the second business day. Building Official: Danny Little (dlittle@fruitland.org); Building Inspector: Brandon Tarvin (btarvin@fruitland.org); Building Clerk: Beth Earles (bearles@fruitland.org).. Official information: https://www.fruitland.org/building.

Fruitland, Idaho has adopted: 2018 International Building Code (IBC); 2018 International Residential Code (IRC); 2018 International Energy Conservation Code (IECC); 2018 International Mechanical Code (IMC); 2012 International Fuel Gas Code (IFGC); 2015 International Fire Code (IFC); Current version of the Uniform Code for the Abatement of Dangerous Buildings; Current version of the Uniform Sign Code; Plumbing and electrical permits/inspections are administered directly by the State of Idaho, not the City of Fruitland. Local amendments apply — see the Fruitland overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fruitland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.