Agricultural Structure Permit (Zoning Permit + Ag Certification) in Unincorporated Power County, Idaho

Agricultural buildings in unincorporated Power County require a Zoning Permit and a notarized Agricultural Building Certification Statement, recorded with the Power County Recorder's Office. Qualifies only for structures used exclusively to house farm implements, hay, grain, poultry, or livestock — not for human habitation, employment where products are processed/treated/packaged, or public use.

Verified 2026-07-08 · Source

When you need this permit

  • Structure must be an 'agricultural building': designed and constructed to house farm implements, hay, grain, poultry, livestock, or other horticultural products
  • Structure must NOT be a place of human habitation, a place of employment for processing/treating/packaging agricultural products, or a place used by the public
  • Building must be in an agriculturally zoned district and located on an actual working farm
  • Setback of at least 60 feet from all habitable structures (additional setback requirements may vary by roadway classification)
  • Obtain the Building Permit/Zoning Permit from the Power County Building Administrator — property and structure are checked for compliance
  • Sign the Agricultural Building Certification Statement when picking up the permit; the notarized statement is recorded in the Power County Recorder's Office and will appear on subsequent title searches of the property

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Zoning/Building permit fee (valuation-based)Power County Building Code Ordinance, Appendix A (Building Valuation Data / Power County Permit Fees table)
Same Power County Permit Fees valuation table as the residential building permit (Appendix A) applies; no separate agricultural-specific fee schedule was found

Review timeline

Plan reviewUnincorporated Power County’s published plan-review target
10–14 business days

How long did your Agricultural Structure Permit (Zoning Permit + Ag Certification) permit actually take in Unincorporated Power County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Compliance / Site Inspection

    Property and structure are checked for compliance with agricultural-building placement and use requirements before the certification statement is signed

See the full Unincorporated Power County inspection guide — scheduling & re-inspection fees →

Tips

  • The Agricultural Building Certification Statement is a legal, notarized document that gets permanently recorded against your property title at the Power County Recorder's Office — it is not just a permit-file form.
  • This exemption path only works if the building is used exclusively for agricultural purposes. A shop, barn, or storage building used for anything else (personal storage, a home business, etc.) needs a standard building permit instead.
  • Confirm your minimum 60-foot setback from habitable structures before finalizing your site plan — this is specific to the agricultural exemption, not the standard residential setback table.

Frequently asked questions

Unincorporated Power County requires an agricultural structure permit (zoning permit + ag certification) for: Structure must be an 'agricultural building': designed and constructed to house farm implements, hay, grain, poultry, livestock, or other horticultural products; Structure must NOT be a place of human habitation, a place of employment for processing/treating/packaging agricultural products, or a place used by the public; Building must be in an agriculturally zoned district and located on an actual working farm; Setback of at least 60 feet from all habitable structures (additional setback requirements may vary by roadway classification); Obtain the Building Permit/Zoning Permit from the Power County Building Administrator — property and structure are checked for compliance; Sign the Agricultural Building Certification Statement when picking up the permit; the notarized statement is recorded in the Power County Recorder's Office and will appear on subsequent title searches of the property. If your project isn't listed, confirm with Power County Building Administrator / Planning and Zoning Department at 208-226-7625 before starting work.

In Unincorporated Power County, the published Zoning/Building permit fee (valuation-based) is: Same Power County Permit Fees valuation table as the residential building permit (Appendix A) applies; no separate agricultural-specific fee schedule was found. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Power County's published plan-review target for an agricultural structure permit (zoning permit + ag certification) is 10–14 business days.

You'll need: Agricultural Building Certification Statement (PDF); Consolidated Building-Development Permit Application (PDF). See the required-documents checklist on this page for details on each.

Unincorporated Power County requires 1 inspection(s) for an agricultural structure permit (zoning permit + ag certification), in order: Compliance / Site Inspection. Schedule each through Power County Building Administrator / Planning and Zoning Department (208-226-7625).

Apply through Power County Building Administrator / Planning and Zoning Department at 73 Fort Hall Ave., Ste. A, American Falls, ID 83211. Phone: 208-226-7625, email: ahiggins@co.power.id.us. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.powercounty.gov/195/Building-Administrator-Planning-and-Zoni.

Unincorporated Power County, Idaho has adopted: 2015 International Building Code (IBC) — adopted and amended per Power County Building Code Ordinance, Title 8, Chapter 1, Section 8-1-13-1; 2012 International Residential Code (IRC) — adopted and amended per Power County Building Code Ordinance, Title 8, Chapter 1, Section 8-1-13-2; 2015 International Energy Conservation Code (IECC); 2015 International Fire Code (IFC); 2015 International Existing Building Code (IEBC); Editions as codified in the Power County Building Code Ordinance (recorded 2018); Power County Code of Ordinances Title 8 (Building Regulations) is maintained on American Legal Publishing but the live section text is JavaScript-rendered and could not be independently re-verified for a possible later edition update beyond the archived 2018 ordinance PDF — treat edition years as sourced to that document. Local amendments apply — see the Unincorporated Power County overview page for the full list.

Yes. All buildings require a permit; however, for the farm-placement setback exemption, permits are issued only for buildings that conform to these placement requirements: the building must be in an agriculturally zoned district, must be 60 feet from all habitable structures, must be on an actual working farm, and must be used only for housing agricultural animals, livestock, or farm implements. Setback requirements may vary depending on the roadway. Source: Power County Building Administrator / Planning and Zoning FAQ, powercounty.gov.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Power County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare agricultural structure permit (zoning permit + ag certification) fees across Idaho

Look up this fee in a different city →