Residential Building Permit (New Construction / Addition) — Unincorporated Power County, Idaho · Requirements sheet
Verified 2026-07-08 · Source: https://www.powercounty.gov/195/Building-Administrator-Planning-and-Zoni
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction / Addition) in Unincorporated Power County, Idaho
Required for new single-family dwellings, additions, structural alterations, and outbuildings over 120 sq ft in unincorporated Power County. Applications are submitted on the shared Consolidated Building-Development Permit Application (used jointly by Power County, American Falls, and Rockland — applicant selects 'Power County' as the jurisdiction). Reviewed and inspected by the Power County Building Administrator.
Verified 2026-07-08 · Source
When you need this permit
- Building permit required for any new construction, structural addition, alteration, or outbuilding over 120 sq ft in unincorporated Power County
- Interior remodels require a permit except for painting and carpeting
- Re-roofing and re-siding projects require a permit (may be issued same-day if complete information is provided)
- Window/door replacement requires a permit if the new opening size is larger than the one removed
- Placing a manufactured home in or out of a park requires a permit
- Check subdivision or land-use restrictions before applying
- Obtain a Power County Highway Permit (208-226-2661) for any new/modified road approach
- Obtain a septic permit from the State Health District (208-226-5094 or 208-478-6320) where applicable
- Obtain Idaho State electrical, plumbing, and HVAC/mechanical permits where applicable — these are NOT issued by Power County (regulated under Idaho Code IC 54-1001 and IC 54-2601)
- Submit a complete set of blueprints to the Power County Building Administrator at least 10–14 days before construction begins
- Blueprints for larger commercial/residential projects must bear the original Engineer's or Architect's stamp
- Site plan drawn at a scale not less than 1 inch = 20 feet, showing property lines/dimensions, septic system and drain field, well location, natural features (rivers, springs, streams, rock outcroppings, slopes over 20% grade), driveway connection and public road name, north arrow, easements, and subdivision/lot info or Record of Survey
- Engineered stormwater retention plan required for properties on 10% or greater slope
- Property lines must be staked for setback verification prior to inspection
- Complete building plans required for the site-built house, addition, or outbuilding
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing
After excavation for footings is complete and any required reinforcing steel is in place
- 2
Foundation
Once forms, reinforcing steel, and materials are on-site; all components must be ready before inspection for concrete foundations
- 3
Concrete Slab / Under-Floor
After all in-slab or under-floor building service equipment, conduit, piping accessories, and other ancillary equipment items are in place, but before any concrete is placed
- 4
Frame
After the roof, all framing, fire-blocking, and bracing are in, and all pipes, electric, and ducts are approved
- 5
Lath / Gypsum Board
After all lathing and/or gypsum board joints and fasteners are in place, but before it is taped and finished
- 6
Final
After finish grade and building is completed and ready for occupancy
See the full Unincorporated Power County inspection guide — scheduling & re-inspection fees →
Tips
- This is the same Consolidated Building-Development Permit Application used by American Falls and Rockland — be sure to check 'Power County' as the location so it is routed correctly.
- Electrical, plumbing, and HVAC/mechanical permits are NOT issued by Power County. Contact the Idaho Division of Building Safety (DOPL/DBS) at dbs.idaho.gov/permits or 1-800-955-3044.
- Submit blueprints at least 10-14 days before you plan to start construction — same-day issuance is only available for re-roofing, re-siding, and sign permits with complete information.
- A Power County Highway Permit and, where applicable, a septic permit from the State Health District are prerequisites — get these BEFORE submitting the building permit application.
- Permits are valid 180 days from issuance. If your project runs long, request an extension before the permit lapses, provided verified work is in progress.
- If you start work before a permit is issued, you'll owe an investigative fee equal to the permit fee itself, on top of the normal permit fee.
- Properties on 10% grade or steeper need an engineered stormwater retention plan as part of the site plan submission.
- Stake your property lines before requesting a setback verification — inspectors will check actual staked distances against the approved site plan.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Power County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Power County
Residential Building Permit (New Construction / Addition) in other cities
Compare residential building permit (new construction / addition) fees across Idaho →
Look up this fee in a different city →