Required for solar photovoltaic panel installation in Osburn, valued per square foot per the City's fee resolution. Electrical interconnection work must be permitted separately through the State of Idaho (DOPL).

Verified 2026-07-08 · Source

When you need this permit

  • Solar panel installation requires a building permit through the City of Osburn for the structural/mounting portion
  • Electrical wiring and interconnection is regulated by the State of Idaho (DOPL), not the City of Osburn

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Solar PanelsResolution No. 2025-11, Exhibit A
$100.00 per sq. ft. (valuation input)
Plan Check FeeResolution No. 2025-11, Exhibit A
45% of the building permit fee, added to all permits issued

Review timeline

Plan review
Not published — contact the department

How long did your Solar Panel Installation Permit permit actually take in Osburn?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final — Building/Structural

    Panel mounting and roof/ground penetration sealing verified by City building official

See the full Osburn inspection guide — scheduling & re-inspection fees →

Tips

  • The City of Osburn's solar fee ($100/sq ft valuation) covers only the structural/mounting building permit; a separate electrical permit through Idaho DOPL is required for wiring and interconnection.
  • Confirm utility interconnection requirements with Avista (Osburn's electric utility) before energizing the system.

Frequently asked questions

Yes, a City building permit is required for the structural mounting, valued at $100/sq ft per Resolution No. 2025-11, Exhibit A. Electrical wiring and interconnection requires a separate permit through Idaho DOPL, not the City of Osburn.

In Osburn, the published Solar Panels is: $100.00 per sq. ft. (valuation input). Additional published fees: Plan Check Fee — 45% of the building permit fee, added to all permits issued. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Osburn does not publish a plan-review timeline for this permit. Contact City of Osburn Planning and Zoning / Building Department at (208) 752-0001 for current turnaround.

You'll need: Building/Development Permit Pre-Application. See the required-documents checklist on this page for details on each.

Osburn requires 1 inspection(s) for a solar panel installation permit, in order: Final — Building/Structural. Schedule each through City of Osburn Planning and Zoning / Building Department ((208) 752-0001).

Apply through City of Osburn Planning and Zoning / Building Department at 921 E Mullan Ave (PO Box 865), Osburn, ID 83849. Phone: (208) 752-0001, email: j.arthun@cityofosburn.org. Office hours: Mon–Thu 9:30 AM – 5:00 PM; Fri 9:30 AM – 12:30 PM. Official information: https://www.cityofosburn.org/planning-and-zoning.

Osburn, Idaho has adopted: 2018 International Building Code (IBC) — cited directly by permit number/section on the City of Osburn Building Permit Extension Request form (IBC 2018 §105.5, permit expiration/extension rule); International Residential Code (IRC) — Osburn Municipal Code §8-22 amends IBC §108.3 and IRC §R108.3 (building permit valuation set by the building official per the city's current fee resolution), per Resolution No. 2025-11; Osburn Municipal Code Chapter 8 — Buildings and Building Regulations, Article II (Building Codes); Osburn Municipal Code Chapter 14 — Floods (floodplain development permitting); Osburn Municipal Code Chapter 36 — Zoning; Note: Idaho Code §39-4116 requires all Idaho local governments that enforce building codes to adopt, by ordinance, the ICC codes designated by the Idaho Building Code Board on the state's standard adoption cycle. Osburn's local adoptions are codified in Osburn Municipal Code Chapter 8 (Buildings and Building Regulations), Article II (Building Codes), Secs. 8-19 through 8-27, hosted on Municode (library.municode.com/id/osburn, nodeId COOR_CH8BUBURE_ARTIIBUCO). The city's adoption of the 2018 IBC is confirmed there and in the city's own resolutions and permit-application PDFs; Sec. 8-19 also adopts the IECC and IMC, and Sec. 8-22 carries the valuation-schedule provision plus extensive local amendment text — including a complete codified design-criteria set (wind, snow, seismic, frost, soil bearing) — recorded in localAmendments below.; Codified adoption text, Osburn Municipal Code Sec. 8-19 ('Codes adopted'): 'The following nationally recognized codes are adopted as the official building codes of the city:' — (1) International Building Code, (2) International Residential Code, (3) International Energy Conservation Code, (4) International Mechanical Code, each 'prepared by the International Code Council, Inc., as adopted by the state or the state building code board, together with any amendments or revisions... made by the state building code board through the negotiated rulemaking process.' (Code 1975, Sec. 15.04.010; Ord. No. 265, Sec. 3(part), 2008; Ord. No. 276, Secs. 1, 2, 2-8-2011; Ord. No. 289, Sec. 1, 1-13-2015.) Note: Sec. 8-19 names NO edition year for any of the four codes — each floats to whatever the Idaho Building Code Board has designated. The IBC edition cited here is therefore sourced from the City's own permit forms rather than from the ordinance. The IECC is adopted under this same section. The full article is Osburn Municipal Code Chapter 8 (Buildings and Building Regulations), Article II (Building Codes), Secs. 8-19 through 8-27, published on library.municode.com (nodeId COOR_CH8BUBURE_ARTIIBUCO).; International Property Maintenance Code — adopted at Osburn Municipal Code Sec. 8-24. The ordinance carries a drafting defect: the SECTION HEADING reads '2012 International Property Maintenance Code adopted', but the section BODY adopts the IPMC 'as adopted by the state or the state building code board' with no edition year. Heading and body disagree. The same defect appears at Sec. 8-23. Do not rely on '2012' without confirming with the City (208-752-8551). Source: Osburn Municipal Code Chapter 8 (Buildings and Building Regulations), Article II (Building Codes), Secs. 8-19 through 8-27, on library.municode.com.; International Mechanical Code — separately re-adopted at Osburn Municipal Code Sec. 8-23 (as well as at Sec. 8-19(4)). The section as enacted contains two defects, reproduced here as written: (1) the heading reads '2012 International Mechanical Code adopted' while the body cites no edition, adopting the IMC 'as adopted by the state or the state building code board'; and (2) the body's scope clause describes the MECHANICAL code as providing 'a minimum standard for all electrical wiring, installation of electrical fixtures, apparatus or electrical appliances, for furnishing light, heat or power, or other electrical work' — that is electrical-code language left in a mechanical-code section. (Code 1975, Sec. 15.04.060; Ord. No. 265, Sec. 6, 2008; Ord. No. 289, Sec. 2, 1-13-2015.) See Osburn Municipal Code Chapter 8 (Buildings and Building Regulations), Article II (Building Codes), Secs. 8-19 through 8-27, on library.municode.com.. Local amendments apply — see the Osburn overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Osburn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Property Access

Osburn's permit history is searchable by address

1,496 permits on record for Osburn, 1959–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.

97% of Osburn's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.

Start your 7-day free trial7 days free for new customers, then $79/mo · the guide above stays free