Cascade building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Cascade, Idaho.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
105 South Main Street, Cascade, ID 83611
Phone
(208) 382-4279
Office hours
Mon–Fri 8:30 AM – 4:30 PM (per City of Cascade March 2023 newsletter; not independently republished elsewhere on the city site as of verification date)

Published scheduling rules

  • 24-hour advance notice is required to schedule any inspection. (Residential Building Permit)
  • 24-hour advance notice is required to schedule any inspection with the City Building Inspector. (General)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Excavation / Soils

    Site and soil inspection before placing forms for footings or column/post holes; property lines must be clearly marked

  2. 2

    Footing / Holes

    After forms are set, reinforcement accurately placed and adequately supported, before placing concrete; pole buildings require hole inspections

  3. 3

    Foundation / Wall

    After all forms and reinforcing materials are in place, before placing concrete

  4. 4

    Slab

    After bar or wire mesh is placed but before concrete placement

  5. 5

    Wall and Roof Sheathing

    Before house wrap or siding is placed; wall and roof nailing pattern checked

  6. 6

    Ice / Water Shield

    After roof sheathing inspection but before final roofing material is placed

  7. 7

    Frame

    After roof and wall sheathing (no siding installed); fire blocking, bracing, draft stops, and all plumbing/electrical/heating/gas rough-ins complete; done after electrical, plumbing, and HVAC rough-in inspections are signed off

  8. 8

    Insulation

    Done before the interior of the structure is covered

  9. 9

    Final

    Electrical, plumbing, and HVAC final inspections must be signed off by the State (DOPL) Inspectors before the City Building Inspector performs the final inspection; paint and flooring do not need to be complete

Applies to: Commercial Building Permit

  1. 1

    Excavation / Soils

    Site and soil inspection before placing forms for footings; property lines must be clearly marked. Same general inspection sequence the City publishes for all building-permit types -- no separate commercial-specific sequence exists.

  2. 2

    Footing / Holes

    After forms are set and reinforcement accurately placed, before placing concrete

  3. 3

    Foundation / Wall

    After all forms and reinforcing materials are in place, before placing concrete

  4. 4

    Slab

    After bar or wire mesh is placed but before concrete placement

  5. 5

    Wall and Roof Sheathing

    Before house wrap or siding is placed; wall and roof nailing pattern checked

  6. 6

    Frame

    After roof and wall sheathing (no siding installed); fire blocking, bracing, draft stops, and all plumbing/electrical/heating/gas rough-ins complete; done after electrical, plumbing, and HVAC rough-in inspections are signed off by State (DOPL) inspectors

  7. 7

    Insulation

    Done before the interior of the structure is covered

  8. 8

    Final

    Electrical, plumbing, and HVAC final inspections must be signed off by the State (DOPL) Inspectors before the City Building Inspector performs the final inspection

Applies to: Manufactured Home Permit

  1. 1

    Excavation

    Required for both permanent-set and block-set manufactured homes

  2. 2

    Footing

    Required for permanent-set manufactured homes only

  3. 3

    Foundation

    Required for permanent-set manufactured homes only

  4. 4

    Final

    Electrical, plumbing, and HVAC must be signed off by State Inspectors before the City's final inspection; required for both permanent-set and block-set homes

Applies to: Commercial Tenant Improvement (TI) / Remodel Permit

  1. 1

    Rough-In (Framing / Electrical / Plumbing / Mechanical, as applicable)

    Scoped to whichever trades the TI touches; not all TI projects require every rough-in inspection. Electrical, plumbing, and HVAC rough-in must be signed off by State (DOPL) inspectors before the City's framing/rough-in sign-off, consistent with the City's general inspection pattern for new construction.

  2. 2

    Insulation

    Required only if the TI scope opens up wall, ceiling, or floor assemblies that are later concealed

  3. 3

    Final

    Electrical, plumbing, and HVAC final inspections must be signed off by State (DOPL) Inspectors before the City Building Inspector performs the final inspection

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Structural/Racking (City)

    Roof penetrations, mounting-system attachment, and any ground-mount footing verified by the City Building Inspector

  2. 2

    Electrical Interconnection (State DOPL)

    Grid interconnection, grounding, and disconnects verified by a State of Idaho DOPL inspector before the system can be energized; the City's own final building inspection requires this state sign-off first, per Cascade's standard practice for electrical/plumbing/HVAC trades

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cascade building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Cascade building permits

Get alerts for Cascade

We'll email you when Cascade's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.