Inspection sequence, scheduling, and re-inspection fees for building permits in Red Lodge, Montana.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
1 South Platt Avenue, PO Box 9, Red Lodge, MT 59068
Phone
(406) 446-1606
Email
Office hours
City Hall: contact (406) 446-1606 x8 to reach Building Inspector Brian Hanna directly; applicants should call the building official to schedule an appointment for application submittal, per the City's Building Division page.

Inspection sequence

Applies to: Residential Building Permit (New Construction / Addition / Alteration)

  1. 1

    Foundation

    After excavation for footings is complete and any required reinforcing steel is in place; for concrete foundations, required forms must be in place prior to inspection

  2. 2

    Concrete Slab or Under-Floor

    After all in-slab or under-floor building service equipment, conduit, piping accessories, and other ancillary equipment items are in place, but before concrete is placed or floor sheathing/subfloor installed

  3. 3

    Frame

    After the roof, all framing, fire blocking and bracing are in place and all pipes, chimneys, and vents are complete, and rough electrical, plumbing, and heating wires/pipes/ducts are approved

  4. 4

    Lath or Gypsum Board

    After all lathing and gypsum board joints and fasteners are taped and finished

  5. 5

    Final

    After finish grading and the building is completed and ready for occupancy; a Certificate of Occupancy may be issued upon request

Applies to: Deck / Accessory Structure Permit

  1. 1

    Foundation/Footing

    Required before concrete pour for deck posts or accessory structure foundations

  2. 2

    Frame

    Structural framing and connections per plans

  3. 3

    Final

    Completed structure verified against approved plans and setbacks; for accessory structures built ahead of the principal use, final inspection is withheld until the principal use passes rough framing inspection

Applies to: EV Charging Station Permit (State-Issued Electrical Permit)

  1. 1

    Electrical Rough-In (if applicable)

    Required only if new circuit wiring is enclosed before final; conduit runs, wire sizing, and grounding verified; 48 hours' notice required

  2. 2

    Electrical Final

    EVSE breaker sizing, working clearances, and charger mounting verified against NEC Article 625

Applies to: Fire Protection Systems Permit (Sprinkler / Alarm) — Commercial Building Construction Permit

  1. 1

    Site Visit(s) During Construction

    Red Lodge Fire Rescue schedules site visits to confirm fire protection systems are being properly installed and that the Fire Department Connection is correctly placed (sprinklered buildings)

  2. 2

    Final / Occupancy Inspection

    Scheduled once construction is complete; all fire alarm and suppression systems are tested for compliance; a $35.00-$75.00 inspection fee is due at the time of inspection; the City of Red Lodge Planning Department is notified once all fire protection features pass

Applies to: Solar PV / Alternative Energy Permit (State-Issued Electrical + City-Issued Structural)

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing; 48 hours' notice required

  2. 2

    Final

    Panel connections, interconnection point, and system operation verified

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Red Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Red Lodge building permits

Get alerts for Red Lodge

We'll email you when Red Lodge's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.