Fire Protection Systems Permit (Sprinkler / Alarm) — Commercial Building Construction Permit in Red Lodge, Montana
Required from Red Lodge Fire Rescue for a commercial building's automatic fire-extinguishing (sprinkler) system and/or fire alarm and detection system, among other enumerated fire-protection categories, as part of the department's 'Commercial Building Construction Permit.' Red Lodge Fire Rescue issues and reviews this permit under an agreement with the City of Red Lodge and under Municipal Code Title 7, Chapter 1 (2021 International Fire Code as locally adopted and amended, Ord. 970, 4/8/2025). It is required IN ADDITION to, not instead of, the City of Red Lodge Building Division's own Building Permit and the Planning Department's review.
Verified 2026-07-22 · Source
When you need this permit
- Commercial Building Construction Permit Application filed with Red Lodge Fire Rescue, checking each fire-protection category that applies: Automatic Fire Extinguishing Systems and/or Fire Alarm and Detection Systems (the two categories relevant here), plus Compressed Gasses, Fire Pumps and Related Equipment, Flammable and Combustible Liquids, Hazardous Materials, LP-Gas Systems, Private Fire Hydrants, Spraying or Dipping Operations, and Standpipe Systems where applicable
- A written description of the building's fire protection features (proposed alarm systems, suppression systems, kitchen hood systems, hazardous materials storage areas) and the building's occupancy classification
- For buildings with automatic sprinklers only: the location of the proposed or closest existing fire hydrant and fire department connection; Red Lodge Fire Rescue conducts a flow test after the permit is received, for fire suppression system design purposes
- A complete scale site plan showing total building square footage, intended use, and all access to the building from public streets and private driveways
- Two complete sets of plans (one printed, one electronic)
- If the project site has no City of Red Lodge-issued physical address, a City of Red Lodge Addressing Application must be submitted alongside the fire permit application
- Each checked permit category is billed as a separate $75.00 Construction Permit — a project needing both a sprinkler permit and a fire alarm permit pays for two permits
- This Fire Department permit must be completed in addition to any application process required by the City of Red Lodge Planning and Building Departments
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Site Visit(s) During Construction
Red Lodge Fire Rescue schedules site visits to confirm fire protection systems are being properly installed and that the Fire Department Connection is correctly placed (sprinklered buildings)
- 2
Final / Occupancy Inspection
Scheduled once construction is complete; all fire alarm and suppression systems are tested for compliance; a $35.00-$75.00 inspection fee is due at the time of inspection; the City of Red Lodge Planning Department is notified once all fire protection features pass
See the full Red Lodge inspection guide — scheduling & re-inspection fees →
Tips
- A project needing both a sprinkler system and a fire alarm system pulls two separate $75.00 Construction Permits from Red Lodge Fire Rescue (one per system category), payable together on a single check made out to Red Lodge Fire Rescue.
- This Fire Department permit is separate from, and required in addition to, the City of Red Lodge Building Permit — budget for both application processes and both sets of fees, and expect the City Planning Department to be notified once the Fire Department permit and final inspection are complete.
- Because Red Lodge is DLI-certified for Building (B) only, fire-protection/life-safety permitting runs on an entirely separate track from the electrical/plumbing/mechanical trades documented elsewhere in this file: it is handled locally by Red Lodge Fire Rescue under a City-Fire District service agreement, not by the Montana DLI Building Codes Bureau and not by the City Building Division.
- The Commercial Building Construction Permit Application form itself still cites '2012 International Fire Code 105.7' even though Municipal Code Title 7, Chapter 1 was updated to adopt the 2021 IFC by Ord. 970 (4/8/2025) — the enumerated permit categories (sprinkler, alarm, etc.) are unchanged between those IFC editions, but confirm current code edition directly with Red Lodge Fire Rescue, (406) 446-2320, if it affects your specific project.
- IFC §903.6 (retrofit fire-sprinkler requirement for existing buildings) was explicitly NOT adopted by Red Lodge per Municipal Code §7-1-1(E)(4) — existing buildings are not required to retrofit sprinklers under the local fire code absent this provision.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Red Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Red Lodge
Fire Protection Systems Permit (Sprinkler / Alarm) — Commercial Building Construction Permit in other cities
Look up this fee in a different city →
Now live
Build your Red Lodge project checklist
Describe your project once and get every permit, document, and fee it triggers in Red Lodge — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →