Demolition Permit — Red Lodge, Montana · Requirements sheet
Verified 2026-07-03 · Source: https://www.cityofredlodge.net/media/13336
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Red Lodge, Montana
Required for demolition of a structure within Red Lodge city limits, processed through the same Building Permit Application used for new construction, additions, and alterations. Demolition work must be completed within 30 days of permit issuance unless otherwise noted.
Verified 2026-07-03 · Source
When you need this permit
- Building Permit Application completed with the scope of work identified as demolition (the form's class-of-work checkboxes are New/Addition/Alteration/Repair; demolition scope is described in the 'DESCRIBE WORK' field and remarks section per the form's own demolition completion clause)
- Demolition work must be completed within 30 days of permit issuance, unless otherwise noted under remarks on the permit
- A City Business Registration is required for contractors before the permit is issued
- Owner/contractor contact information, valuation of work, and building dimensions/legal description required as with any other permit type on this form
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No fixed, published fee table or standalone demolition bond requirement was found for Red Lodge — unlike Billings' distinct $10,000 demolition bond ordinance (City Code Chapter 6, Article 6-1000),… Show full citationHide
No fixed, published fee table or standalone demolition bond requirement was found for Red Lodge — unlike Billings' distinct $10,000 demolition bond ordinance (City Code Chapter 6, Article 6-1000), Red Lodge's Municipal Code Title 9, Chapter 3 (which would parallel a demolition-specific chapter) is marked '(RESERVED)', meaning no separate demolition ordinance exists; demolition fees are filled in on the same Building Permit Application's blank fee lines. Confirmed via direct review of Title 9 chapter listing (eCode360) and the Building Permit Application form. Left null rather than estimated.Review timeline
Inspection process
See the full Red Lodge inspection guide — scheduling & re-inspection fees →
Tips
- Demolition work must be completed within 30 days of permit issuance unless the permit's remarks section states otherwise.
- Unlike Billings, Red Lodge does not have a separate demolition bond ordinance on the books (Municipal Code Title 9, Chapter 3 is reserved/empty) — confirm current bonding/insurance expectations directly with the Building Division, (406) 446-1606, since this is a much smaller jurisdiction without Billings-scale published demolition procedures.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Applications & forms
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Red Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Red Lodge's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Red Lodge yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Red Lodge lands. Privacy.
Other permits in Red Lodge
Demolition Permit in other cities
Compare demolition permit fees across Montana →
Look up this fee in a different city →
Now live
Build your Red Lodge project checklist
Describe your project once and get every permit, document, and fee it triggers in Red Lodge — in one checklist. Free, for any city and any number of projects.