Solar PV / Alternative Energy Permit (State-Issued Electrical + City-Issued Structural) — Red Lodge, Montana · Requirements sheet
Verified 2026-07-19 · Source: https://bsd.dli.mt.gov/building-codes-permits/permit-applications/electrical-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV / Alternative Energy Permit (State-Issued Electrical + City-Issued Structural) in Red Lodge, Montana
Required for installation of rooftop or ground-mounted solar photovoltaic (and wind/hydro) alternative-energy systems within Red Lodge city limits. Because Red Lodge is DLI-certified for Building ONLY (not Electrical), the electrical-connection scope of a solar install is permitted directly by the Montana DLI Building Codes Bureau via its statewide Alternative Energy Permit application; the structural/roof-mounting scope falls under the City's own certified Building Permit program (Building Inspector Brian Hanna).
Verified 2026-07-19 · Source
When you need this permit
- Application for Alternative Energy Permit filed with the Montana DLI Building Codes Bureau covers the electrical connection scope of a solar, wind, or hydro system, since Red Lodge holds no Electrical certification
- If the project produces 90 or more volts of electricity, a licensed electrical contractor must do the work, UNLESS the homeowner is doing the work on their own private house
- If the project involves a grid-tied alternative energy generator, a licensed electrical contractor must obtain an additional permit for the final interconnection, even where a homeowner performed the rest of the installation
- Applicant selects one of: PV String System, Generator, or Microinverter/AC Module System
- The structural/roof-mounting scope of the installation requires a City of Red Lodge Building Permit (same Building Permit Application used for other construction), reviewed by Building Inspector Brian Hanna against the 2021 IRC/IBC and City Design Criteria (70 psf minimum roof snow load, wind load by risk category)
- A City Business Registration is required for contractors before the City Building Permit is issued
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No fixed, published valuation-based fee table was found on the City of Red Lodge website (same publication gap already documented for the residential-building-permit entry in this record) — the… Show full citationHide
No fixed, published valuation-based fee table was found on the City of Red Lodge website (same publication gap already documented for the residential-building-permit entry in this record) — the Building Permit Application's PLAN CHECK FEE / PERMIT FEE lines are filled in by staff after review. Contact the Building Division, (406) 446-1606, for a current quote.Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing; 48 hours' notice required
- 2
Final
Panel connections, interconnection point, and system operation verified
See the full Red Lodge inspection guide — scheduling & re-inspection fees →
Tips
- Because Red Lodge is not certified for Electrical, the electrical portion of any solar install is a STATE Alternative Energy Permit, applied for directly with the Montana DLI Building Codes Bureau, not the City.
- The structural/roof-mounting scope IS handled locally — confirm with Building Inspector Brian Hanna, (406) 446-1606 x8, whether your specific project needs a City Building Permit alongside the state Alternative Energy Permit.
- Grid-tied systems always require a licensed electrical contractor to pull a separate permit for the final interconnection, even for otherwise homeowner-installed systems.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Red Lodge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Red Lodge's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Red Lodge yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Red Lodge lands. Privacy.
Other permits in Red Lodge
Solar PV / Alternative Energy Permit (State-Issued Electrical + City-Issued Structural) in other cities
Look up this fee in a different city →
Now live
Build your Red Lodge project checklist
Describe your project once and get every permit, document, and fee it triggers in Red Lodge — in one checklist. Free, for any city and any number of projects.
Get started →