Addition / Alteration Permit in Miles City, Montana

Required for additions and alterations to existing one- and two-family dwellings in Miles City, using the same Building Permit Application as new construction. Reviewed under the 2021 IRC as adopted via City Code § 5-46.

Verified 2026-07-03 · Source

When you need this permit

  • Building permit required for 'Addition' or 'Alteration' classes of work per the Building Permit Application's Type of Improvement checklist
  • Application must show building setbacks (front, rear, side x2), total building square feet, building dimensions, and zoning district
  • Construction plans (site plan, floor plan, wall section drawings, stamped truss, floor joist info) submitted as applicable to the scope of work
  • Same 180-day application-abandonment provision (IBC Section 105.3.2) and inspection-request duty (IBC Section 110) apply as for new construction

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee (valuation-based, same schedule as new construction)City of Miles City Code § 5-4 (Ord. No. 1378, 5-28-24) — see GENUINELY UNPUBLISHED note under the Building Permit type for the full avenues-exhausted list
Set by City of Miles City fee schedule adopted by council resolution under City Code § 5-4; specific dollar-valuation table not independently locatable as a standalone published document as of this review
Building Plan Review Fee (projects valued $50,000 or more)City of Miles City Code § 5-4 (Ord. No. 1378, 5-28-24)
30% of the Building Permit Fee

Review timeline

Plan reviewMiles City’s published plan-review target
1–10 business days

How long did your Addition / Alteration Permit permit actually take in Miles City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • Review timeline governed by statute: an addition/alteration to a one- or two-family dwelling is filed on the same single-family-dwelling Building Permit Application, so MCA 50-60-106(2)(c) applies — Miles City (certified under 50-60-302 for Building) must issue 'the relevant building permit or notice of plan disapproval within 10 working days of the contractor's submission' when the department's single-family-dwelling checklist is attached to the plans. The 1-working-day floor reflects that a complete, clean submittal can issue sooner. The city publishes no separate SLA (independently reconfirmed 2026-07-03).
    • Accessory Dwelling Units (attached apartments or detached units including apartments over garages) are permitted through this same Building Permit Application, plus compliance with the ADU zoning standards in City Code § 24-65 (one ADU per lot, ≤2 bedrooms, ground floor area ≤50% of the principal dwelling's, matching roof pitch/siding/trim, 1 off-street parking space).

    Frequently asked questions

    Miles City requires an addition / alteration permit for: Building permit required for 'Addition' or 'Alteration' classes of work per the Building Permit Application's Type of Improvement checklist; Application must show building setbacks (front, rear, side x2), total building square feet, building dimensions, and zoning district; Construction plans (site plan, floor plan, wall section drawings, stamped truss, floor joist info) submitted as applicable to the scope of work; Same 180-day application-abandonment provision (IBC Section 105.3.2) and inspection-request duty (IBC Section 110) apply as for new construction. If your project isn't listed, confirm with City of Miles City Building Department at (406) 874-8611 before starting work.

    In Miles City, the published Building Permit Fee (valuation-based, same schedule as new construction) is: Set by City of Miles City fee schedule adopted by council resolution under City Code § 5-4; specific dollar-valuation table not independently locatable as a standalone published document as of this review. Additional published fees: Building Plan Review Fee (projects valued $50,000 or more) — 30% of the Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Miles City's published plan-review target for an addition / alteration permit is 1–10 business days.

    You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

    Apply through City of Miles City Building Department at 17 S. 8th St., Miles City, MT 59301. Phone: (406) 874-8611, email: gmartinsen@milescity-mt.org. Office hours: Monday-Friday 7:00 AM - 4:00 PM (Building Inspector); City Hall general hours Mon-Fri 8:00 AM - 5:00 PM. Official information: https://www.milescitymt.gov/building-department.

    Miles City, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; a certified local program's adopted code 'may include only codes adopted by the Building Codes Bureau' (ARM 24.301.202). Non-certified trades within a jurisdiction fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs and Current Codes pages (bsd.dli.mt.gov/building-codes-permits).; Miles City is a Montana DLI-certified jurisdiction for Building (B), Swimming Pool (SP), and Electrical — residential only — within Miles City city limits; certified program contact on file with DLI: Gabe Martinsen, (406) 874-8611. Miles City is NOT certified for Plumbing or Mechanical, or for commercial Electrical — those permits/inspections are issued directly by the Montana DLI Building Codes Bureau (Helena) even within Miles City city limits. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list (List of certified jurisdictions table), bsd.dli.mt.gov/building-codes-permits/certified-government; Miles City City Code § 5-2(a): the city adopts by ordinance 'the current editions of the building codes and all accompanying appendices, amendments and modifications' adopted by the DLI Building Codes Bureau, as authorized by MCA 50-60-301(1)(b) — the city does not maintain independently amended code text; it tracks whatever edition the state Building Codes Bureau currently has in force for local-government jurisdictions. Source: Miles City Code of Ordinances § 5-2, Municode (Ord. No. 1132, 5-28-02; most recently amended by Ord. No. 1375, 1-23-24); International Residential Code (IRC), 2021 Edition, as amended by ARM 24.301.154 — adopted by City of Miles City Code § 5-46 (Ord. No. 1375, 1-23-24); 2021 Existing Building Code, as amended by ARM 24.301.171 — adopted by City of Miles City Code § 5-61(a) (Ord. No. 1375, 1-23-24); 2021 International Swimming Pool and Spa Code, as amended by ARM 24.301.175 — adopted by City of Miles City Code § 5-61(b); Miles City is DLI-certified for Swimming Pool (SP) permitting (Ord. No. 1375, 1-23-24); 2021 International Energy Conservation Code, as amended by ARM 24.301.161 — adopted by City of Miles City Code § 5-61(c) (Ord. No. 1375, 1-23-24); National Electrical Code (NEC), 2020 Edition, as amended by ARM 24.301.401 — adopted by City of Miles City Code § 5-76 (Ord. No. 1392, 3-11-25); Miles City is DLI-certified for residential Electrical permitting only — commercial electrical work in Miles City is permitted and inspected directly by the state DLI Building Codes Bureau; International Building Code (IBC) — applicable via § 5-2(a)'s blanket adoption of the DLI Building Codes Bureau's current edition (2021 IBC statewide, effective June 11, 2022); the City of Miles City Building Permit Application form itself references IBC Section 105.3.2 (180-day application-abandonment provision) and IBC Section 110 (duty to request inspection); 2021 Uniform Plumbing Code (UPC) and 2021 International Mechanical Code (IMC)/International Fuel Gas Code (IFGC) — statewide editions; state-administered in Miles City since the city holds no Plumbing or Mechanical DLI certification; Miles City Code § 24-65 (Zoning, Article III): locally adopted Accessory Dwelling Unit (ADU) performance standards, including a Tiny Home provision referencing International Residential Code Appendix Q. Local amendments apply — see the Miles City overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-03.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Miles City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.