Change of Use / Certificate of Occupancy — Miles City, Montana · Requirements sheet
Reviewed 2026-07-22 · Source: https://www.milescitymt.gov/building-department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Certificate of Occupancy in Miles City, Montana
Miles City does not publish a standalone Change of Use or Certificate of Occupancy application, fee, or process distinct from its general Building Permit. A change in use or occupancy of an existing building, and certificate-of-occupancy issuance for new construction, are governed by the same 2021 International Building Code and 2021 Existing Building Code already adopted by City Code § 5-2(a) and § 5-61(a) (see this file's codesAdopted) that the city's DLI-certified Building Department administers — filed on the standard Building Permit Application (Class of Work 'Alteration' or 'Other') rather than through a separate CO/change-of-use product.
Reviewed 2026-07-22 · Source
When you need this permit
- A change in use or occupancy of an existing building, or certificate-of-occupancy issuance for new construction, in Miles City is addressed through the standard City Building Permit Application (Class of Work 'Alteration' or 'Other'), not a separate Change of Use or Certificate of Occupancy form — no such standalone form was found published by the City of Miles City
- Substantively governed by the 2021 International Building Code (adopted via City Code § 5-2(a)'s blanket adoption of the state's currently-in-force edition) and the 2021 Existing Building Code (adopted by City Code § 5-61(a)) — both already documented in this file's codesAdopted list — which set the technical standards for occupancy classification, change-of-occupancy compliance, and certificate-of-occupancy issuance that the Building Inspector applies when reviewing a Building Permit Application for a use or occupancy change
- The Montana DLI Building Codes Bureau's own published description of its statewide Building Codes Program (bsd.dli.mt.gov, independently re-fetched 2026-07-22) states its purpose includes safeguarding against hazards arising from 'the enlargement, relocation, repair, alteration, or change in use or occupancy of existing buildings' — the same certified-program framework under which Miles City administers Building permits (see codesAdopted)
- No Miles City-specific published guidance, fee line, or processing timeline distinct from the general Building Permit process was located for a change-of-use or certificate-of-occupancy review as of this review
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
Tips
- A change of occupancy in Miles City is not a separate permit product — it is handled as an Alteration or 'Other' Building Permit Application, evaluated against the 2021 IBC and 2021 Existing Building Code (already adopted by City Code §§ 5-2(a) and 5-61(a)) that this file's codesAdopted section documents.
- Because a change-of-use/CO submission is not necessarily a single-family-dwelling application, do not assume the 10-working-day SFD statute governing this file's Building/Addition/Roofing entries applies — confirm turnaround directly with the Building Inspector.
- Fire-code compliance for an occupancy change (e.g., increased occupant load or a change in hazard classification) may also require coordination with Miles City Fire & Rescue, which performs fire-related plan review and inspection for the city (see this file's Fire Sprinkler & Fire Alarm Permit entry).
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Miles City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Miles City
Change of Use / Certificate of Occupancy in other cities
Compare change of use / certificate of occupancy fees across Montana →
Look up this fee in a different city →