Electric Vehicle (EV) Charger Permit in Miles City, Montana

Miles City publishes no distinct EV-charger permit type or fee. The City is DLI-certified for residential Electrical only (City Code § 5-76, adopting the 2020 NEC), so a new circuit, outlet, or panel/service upgrade installed to serve an EV charger at a residence would be permitted through the City Building Department's standard Residential Electrical Permit process, on the same Cloud Permit application used for Building, Residential Electrical, and Roofing permits. No EV-specific city guidance, and no standalone electrical fee table separate from the general § 5-4 valuation-based schedule, was found published.

Reviewed 2026-07-20 · Source

When you need this permit

  • A Residential Electrical Permit is required for any new circuit, outlet, or panel/service upgrade installed to serve an EV charger, per City Code § 5-76 (2020 NEC)
  • Applied for via the same Cloud Permit application (us.cloudpermit.com) or paper Building Permit Application used for general Building/Residential Electrical/Roofing permits
  • Commercial EV charging installations fall outside Miles City's residential-only DLI Electrical certification and must be permitted directly through the Montana DLI Building Codes Bureau (Helena)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Department permit fee (same § 5-4 valuation-based schedule as other Residential Electrical work)Same gap already documented on this file's general electrical-permit entry — Miles City has not published a standalone dollar-valuation electrical fee table
Set by City of Miles City fee schedule adopted by council resolution under City Code § 5-4; no distinct EV-charger fee line, and no standalone electrical fee table separate from the general schedule, was found published as of this review

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger Permit permit actually take in Miles City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • There is no Miles City-specific 'EV charger permit' — a new circuit or outlet for EV charging would fall under the standard Residential Electrical Permit process (City Code § 5-76, 2020 NEC).
    • No EV-specific city page or fee line was located during this research pass; this entry documents the applicable general mechanism rather than an EV-confirmed fee.
    • Confirm scope and fee with the Building Inspector at (406) 874-8611 before applying, especially for any commercial EV charging installation, which routes to the state DLI Building Codes Bureau instead.

    Frequently asked questions

    Miles City has not published EV-specific guidance, but a new electrical circuit or outlet to serve an EV charger would fall under the City's standard Residential Electrical Permit process (City Code § 5-76, 2020 NEC), administered by the Building Department.

    In Miles City, the published Building Department permit fee (same § 5-4 valuation-based schedule as other Residential Electrical work) is: Set by City of Miles City fee schedule adopted by council resolution under City Code § 5-4; no distinct EV-charger fee line, and no standalone electrical fee table separate from the general schedule, was found published as of this review. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Miles City does not publish a plan-review timeline for this permit. Contact City of Miles City Building Department at (406) 874-8611 for current turnaround.

    You'll need: Building Permit Application (Residential Electrical). See the required-documents checklist on this page for details on each.

    Apply through City of Miles City Building Department at 17 S. 8th St., Miles City, MT 59301. Phone: (406) 874-8611, email: gmartinsen@milescity-mt.org. Office hours: Monday-Friday 7:00 AM - 4:00 PM (Building Inspector); City Hall general hours Mon-Fri 8:00 AM - 5:00 PM. Official information: https://www.milescitymt.gov/building-department.

    Miles City, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; a certified local program's adopted code 'may include only codes adopted by the Building Codes Bureau' (ARM 24.301.202). Non-certified trades within a jurisdiction fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs and Current Codes pages (bsd.dli.mt.gov/building-codes-permits).; Miles City is a Montana DLI-certified jurisdiction for Building (B), Swimming Pool (SP), and Electrical — residential only — within Miles City city limits; certified program contact on file with DLI: Gabe Martinsen, (406) 874-8611. Miles City is NOT certified for Plumbing or Mechanical, or for commercial Electrical — those permits/inspections are issued directly by the Montana DLI Building Codes Bureau (Helena) even within Miles City city limits. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list (List of certified jurisdictions table), bsd.dli.mt.gov/building-codes-permits/certified-government; Miles City City Code § 5-2(a): the city adopts by ordinance 'the current editions of the building codes and all accompanying appendices, amendments and modifications' adopted by the DLI Building Codes Bureau, as authorized by MCA 50-60-301(1)(b) — the city does not maintain independently amended code text; it tracks whatever edition the state Building Codes Bureau currently has in force for local-government jurisdictions. Source: Miles City Code of Ordinances § 5-2, Municode (Ord. No. 1132, 5-28-02; most recently amended by Ord. No. 1375, 1-23-24); International Residential Code (IRC), 2021 Edition, as amended by ARM 24.301.154 — adopted by City of Miles City Code § 5-46 (Ord. No. 1375, 1-23-24); 2021 Existing Building Code, as amended by ARM 24.301.171 — adopted by City of Miles City Code § 5-61(a) (Ord. No. 1375, 1-23-24); 2021 International Swimming Pool and Spa Code, as amended by ARM 24.301.175 — adopted by City of Miles City Code § 5-61(b); Miles City is DLI-certified for Swimming Pool (SP) permitting (Ord. No. 1375, 1-23-24); 2021 International Energy Conservation Code, as amended by ARM 24.301.161 — adopted by City of Miles City Code § 5-61(c) (Ord. No. 1375, 1-23-24); National Electrical Code (NEC), 2020 Edition, as amended by ARM 24.301.401 — adopted by City of Miles City Code § 5-76 (Ord. No. 1392, 3-11-25); Miles City is DLI-certified for residential Electrical permitting only — commercial electrical work in Miles City is permitted and inspected directly by the state DLI Building Codes Bureau; International Building Code (IBC) — applicable via § 5-2(a)'s blanket adoption of the DLI Building Codes Bureau's current edition (2021 IBC statewide, effective June 11, 2022); the City of Miles City Building Permit Application form itself references IBC Section 105.3.2 (180-day application-abandonment provision) and IBC Section 110 (duty to request inspection); 2021 Uniform Plumbing Code (UPC) and 2021 International Mechanical Code (IMC)/International Fuel Gas Code (IFGC) — statewide editions; state-administered in Miles City since the city holds no Plumbing or Mechanical DLI certification; Miles City Code § 24-65 (Zoning, Article III): locally adopted Accessory Dwelling Unit (ADU) performance standards, including a Tiny Home provision referencing International Residential Code Appendix Q. Local amendments apply — see the Miles City overview page for the full list.

    Sources & verification

    Key facts verified against official sources. Last reviewed 2026-07-20.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Miles City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.