Cut Bank building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Cut Bank, Montana.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 221 West Main Street, Cut Bank, MT 59427
- Phone
- (406) 873-5526
- Office hours
- City Hall (Winter Hours): Monday - Friday, 8:00 AM - 5:00 PM. Building Official Kory Sandon can be reached directly at (406) 873-5526 or ksandon@cityofcutbank.org.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction / Addition / Alteration)
- 1
Foundation/Footing
Verify footing width, depth, material, and 48-inch minimum frost depth before concrete pour
- 2
Framing
Framing, sheathing, and structural connections per approved plans before walls are closed
- 3
Final
Completed work verified against approved plans, including smoke/CO alarm placement per IRC R314/R315 where applicable
Applies to: Deck / Accessory Structure Permit (Garage, Pole Barn, Patio Cover)
- 1
Footing/Foundation
Required before concrete pour for deck posts, garage foundations, or pole barn footings, verifying the 48-inch frost depth
- 2
Final
Completed structure verified against approved plans and setbacks
Applies to: Electric Vehicle Charging Station Permit (State-Issued Electrical Permit)
- 1
Rough-In (if new circuit run before concealment)
Conduit/wiring for the new charger circuit before covering
- 2
Final
Charger installed, circuit verified, system energized
Applies to: Fire Alarm System Permit (State-Issued, via Electrical Permit — No Dedicated Fee Line)
- 1
Rough-In (if new wiring run before concealment)
Conduit/wiring for fire alarm initiating and notification circuits inspected before covering, consistent with standard practice for state-issued electrical permits documented elsewhere in this file
- 2
Final
Fire alarm panel and devices installed, circuits verified, system tested and energized
Applies to: Solar PV / Alternative Energy Permit (State-Issued)
- 1
Rough-In (Electrical)
Conduit runs, wire sizing, disconnect placement before covering/energizing; must be requested with 48 hours' notice
- 2
Final Interconnection
Per the state application form, a licensed electrical contractor must obtain and complete an additional permit/inspection for the final grid-tied utility connection before Permission to Operate
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cut Bank building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Cut Bank building permits
Get alerts for Cut Bank
We'll email you when Cut Bank's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.