Solar PV / Alternative Energy Permit (State-Issued) in Cut Bank, Montana

Required for installation of grid-tied residential or commercial rooftop/ground-mounted solar photovoltaic systems in Cut Bank. Because Cut Bank is DLI-certified for Building only (no Electrical certification), the electrical/interconnection portion of any solar PV installation is issued directly by the Montana DLI Building Codes Bureau in Helena as an Application for Alternative Energy Permit — the same statewide form used for solar, wind, and hydro systems — not by the City of Cut Bank. The City's own Permitting FAQ confirms electrical permits generally are obtained 'online from the Montana Department of Labor and Industry.' Roof-mounted racking/structural attachment may separately require the City of Cut Bank's own Building Permit, since Cut Bank holds its own DLI Building certification.

Verified 2026-07-20 · Source

When you need this permit

  • Complete the state's Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25): identify the alternative energy type as Solar and the system type (PV String System, Generator, or Micro Inverter/AC Module System)
  • If the system will produce 90 or more volts, the electrical work must be performed by a Montana-licensed electrical contractor unless the homeowner is doing the work on their own private house
  • If the project involves a grid-tied alternative energy generator (virtually all net-metered residential/commercial solar), a licensed electrical contractor must obtain an ADDITIONAL permit for the final utility interconnection — stated directly on the state application form
  • Mail the completed application and fee to Department of Labor & Industry, Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or apply online at https://aca-prod.accela.com/bcb/
  • Because Cut Bank holds its own DLI Building certification, a separate City of Cut Bank Building Permit application is likely required for the roof-mount racking/structural attachment portion of the installation — confirm with the City

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Change of Service (applies to residential grid-tied solar PV)Montana DLI Building Codes Bureau, Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25), Type of Work item F, 'Residential Change of Service'; the flat fee line item on the same form used for solar/wind/hydro alternative energy applications statewide, directly fetched and text-extracted from the state's own PDF form
$45
Commercial Alternative Energy/Solar — valuation $0 to $1,000Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25), Commercial fee chart
$45 for the first $500 plus 6% of the balance of the project cost
Commercial Alternative Energy/Solar — valuation $1,001 to $10,000Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25)
$75 for the first $1,000 plus 2% of the balance of the project cost
Commercial Alternative Energy/Solar — valuation $10,001 to $50,000Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25)
$255 for the first $10,000 plus 0.5% of the balance of the project cost
Commercial Alternative Energy/Solar — valuation $50,001 or moreApplication for Alternative Energy Permit (BCP-1 series, Rev. 11/25)
$455 for the first $50,000 plus 0.3% of the balance of the project cost

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV / Alternative Energy Permit (State-Issued) permit actually take in Cut Bank?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In (Electrical)

    Conduit runs, wire sizing, disconnect placement before covering/energizing; must be requested with 48 hours' notice

  2. 2

    Final Interconnection

    Per the state application form, a licensed electrical contractor must obtain and complete an additional permit/inspection for the final grid-tied utility connection before Permission to Operate

See the full Cut Bank inspection guide — scheduling & re-inspection fees →

Tips

  • Solar PV in Cut Bank is NOT processed by the City for the electrical portion — the City's own Permitting FAQ confirms electrical permits are obtained online from the Montana Department of Labor and Industry, and this extends to the Alternative Energy Permit used for solar/wind/hydro systems.
  • A grid-tied system (virtually all residential net-metered solar) requires a licensed electrical contractor to obtain a SEPARATE additional permit for the final utility connection, per the state form's own certification language.
  • The residential flat fee of $45 applies under the 'Residential Change of Service' line item on the same Alternative Energy Permit form; commercial projects are billed on the same tiered valuation schedule as standard commercial electrical work.
  • Because Cut Bank holds its own local Building certification, the structural/racking attachment likely needs a City of Cut Bank Building Permit in addition to the state electrical permit — confirm before starting work.

Frequently asked questions

Cut Bank requires a solar pv / alternative energy permit (state-issued) for: Complete the state's Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25): identify the alternative energy type as Solar and the system type (PV String System, Generator, or Micro Inverter/AC Module System); If the system will produce 90 or more volts, the electrical work must be performed by a Montana-licensed electrical contractor unless the homeowner is doing the work on their own private house; If the project involves a grid-tied alternative energy generator (virtually all net-metered residential/commercial solar), a licensed electrical contractor must obtain an ADDITIONAL permit for the final utility interconnection — stated directly on the state application form; Mail the completed application and fee to Department of Labor & Industry, Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or apply online at https://aca-prod.accela.com/bcb/; Because Cut Bank holds its own DLI Building certification, a separate City of Cut Bank Building Permit application is likely required for the roof-mount racking/structural attachment portion of the installation — confirm with the City. If your project isn't listed, confirm with City of Cut Bank Building Department — Building Official Kory Sandon, Certified Residential & Commercial Building Inspector; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Cut Bank city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 873-5526 before starting work.

The state's Application for Alternative Energy Permit lists a flat $45 fee under 'Residential Change of Service,' which applies to residential grid-tied solar. Commercial solar is billed on the state's tiered valuation-based fee schedule (e.g., $45 for the first $500 plus 6% of the balance for projects up to $1,000).

Cut Bank does not publish a plan-review timeline for this permit. Contact City of Cut Bank Building Department — Building Official Kory Sandon, Certified Residential & Commercial Building Inspector; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Cut Bank city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 873-5526 for current turnaround.

You'll need: Application for Alternative Energy Permit. Depending on your project, Cut Bank may also ask for: City of Cut Bank Building Permit Application. See the required-documents checklist on this page for details on each.

Cut Bank requires 2 inspection(s) for a solar pv / alternative energy permit (state-issued), in order: Rough-In (Electrical), Final Interconnection. Schedule each through City of Cut Bank Building Department — Building Official Kory Sandon, Certified Residential & Commercial Building Inspector; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Cut Bank city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. ((406) 873-5526).

Apply through City of Cut Bank Building Department — Building Official Kory Sandon, Certified Residential & Commercial Building Inspector; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Cut Bank city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at 221 West Main Street, Cut Bank, MT 59427. Phone: (406) 873-5526, email: ksandon@cityofcutbank.org. Office hours: City Hall (Winter Hours): Monday - Friday, 8:00 AM - 5:00 PM. Building Official Kory Sandon can be reached directly at (406) 873-5526 or ksandon@cityofcutbank.org.. Official information: https://www.cityofcutbank.org/building-department.

Cut Bank, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code (building, plumbing, electrical, mechanical, swimming pool, etc.); non-certified trades in a partially-certified jurisdiction fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list (bsd.dli.mt.gov/building-codes-permits).; Cut Bank is a Montana DLI-certified jurisdiction for Building (B) ONLY within city limits; certified building official on file with DLI: Kory Sandon, (406) 873-5526. Source: Montana DLI Building Codes Bureau, 'Montana Certified Local Government Program' roster, updated 04/22/2026, https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf — roster row: 'Cutbank | B | Kory Sandon | 873-5526 | City Limits' (verified directly via pdftotext extraction of the primary-source PDF, not a third-party mirror).; The City of Cut Bank's own Building Permit Fee Schedule and Permitting FAQ (published on cityofcutbank.org) confirm the City issues Building permits only, while explicitly directing applicants to the Montana DLI for mechanical, electrical, and plumbing permits: 'Where do I get my mechanical, electrical, or plumbing permit? Online from the Montana Department of Labor and Industry.' Source: City of Cut Bank Permitting FAQ's (PDF), cityofcutbank.org/media/2616; Per the Montana DLI Building Codes Bureau's Current Codes page (statewide effective date June 11, 2022, applicable to all certified and state-enforced jurisdictions alike): 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 ISPSC, 2021 UPC, 2020 NEC, 2017 ICC A117.1 Accessibility. Cut Bank's own Building Permit Application checklist references the adopted Uniform/International Residential Code framework (IRC Section R105.2 exemptions, R301.1.3 engineered design, R314/R315 smoke and CO alarms, R311.4 egress) consistent with enforcement of the state-adopted IRC edition rather than a locally-amended one. Source: bsd.dli.mt.gov/building-codes-permits/current-codes; City of Cut Bank Building Permit Application Checklist (PDF), cityofcutbank.org/media/2766. Local amendments apply — see the Cut Bank overview page for the full list.

The Montana Department of Labor & Industry Building Codes Bureau issues the electrical/interconnection permit for solar PV in Cut Bank, using its statewide Application for Alternative Energy Permit — the City's own Permitting FAQ confirms electrical permits are obtained from the state, not the city. The roof-mount/racking structural portion is likely handled by the City of Cut Bank's own Building Permit.