Solar PV / Alternative Energy Permit (State-Issued) — Cut Bank, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/ApplicationAlternativeEnergyPermit.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV / Alternative Energy Permit (State-Issued) in Cut Bank, Montana
Required for installation of grid-tied residential or commercial rooftop/ground-mounted solar photovoltaic systems in Cut Bank. Because Cut Bank is DLI-certified for Building only (no Electrical certification), the electrical/interconnection portion of any solar PV installation is issued directly by the Montana DLI Building Codes Bureau in Helena as an Application for Alternative Energy Permit — the same statewide form used for solar, wind, and hydro systems — not by the City of Cut Bank. The City's own Permitting FAQ confirms electrical permits generally are obtained 'online from the Montana Department of Labor and Industry.' Roof-mounted racking/structural attachment may separately require the City of Cut Bank's own Building Permit, since Cut Bank holds its own DLI Building certification.
Verified 2026-07-20 · Source
When you need this permit
- Complete the state's Application for Alternative Energy Permit (BCP-1 series, Rev. 11/25): identify the alternative energy type as Solar and the system type (PV String System, Generator, or Micro Inverter/AC Module System)
- If the system will produce 90 or more volts, the electrical work must be performed by a Montana-licensed electrical contractor unless the homeowner is doing the work on their own private house
- If the project involves a grid-tied alternative energy generator (virtually all net-metered residential/commercial solar), a licensed electrical contractor must obtain an ADDITIONAL permit for the final utility interconnection — stated directly on the state application form
- Mail the completed application and fee to Department of Labor & Industry, Building Codes Bureau, PO Box 200517, Helena, MT 59620-0517, or apply online at https://aca-prod.accela.com/bcb/
- Because Cut Bank holds its own DLI Building certification, a separate City of Cut Bank Building Permit application is likely required for the roof-mount racking/structural attachment portion of the installation — confirm with the City
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In (Electrical)
Conduit runs, wire sizing, disconnect placement before covering/energizing; must be requested with 48 hours' notice
- 2
Final Interconnection
Per the state application form, a licensed electrical contractor must obtain and complete an additional permit/inspection for the final grid-tied utility connection before Permission to Operate
See the full Cut Bank inspection guide — scheduling & re-inspection fees →
Tips
- Solar PV in Cut Bank is NOT processed by the City for the electrical portion — the City's own Permitting FAQ confirms electrical permits are obtained online from the Montana Department of Labor and Industry, and this extends to the Alternative Energy Permit used for solar/wind/hydro systems.
- A grid-tied system (virtually all residential net-metered solar) requires a licensed electrical contractor to obtain a SEPARATE additional permit for the final utility connection, per the state form's own certification language.
- The residential flat fee of $45 applies under the 'Residential Change of Service' line item on the same Alternative Energy Permit form; commercial projects are billed on the same tiered valuation schedule as standard commercial electrical work.
- Because Cut Bank holds its own local Building certification, the structural/racking attachment likely needs a City of Cut Bank Building Permit in addition to the state electrical permit — confirm before starting work.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cut Bank building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Cut Bank
Solar PV / Alternative Energy Permit (State-Issued) in other cities
Compare solar pv / alternative energy permit (state-issued) fees across Montana →
Look up this fee in a different city →