Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Beaver County, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
105 East Center Street, Beaver, UT 84713 (mailing: P.O. Box 1013, Beaver, UT 84713)
Phone
(435) 438-6484
Office hours
Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 12:00 PM. Field inspections conducted 7:00 AM – 4:00 PM Monday–Thursday. Closed federal and local holidays.

Published scheduling rules

  • A certificate of occupancy will not be issued until all required inspections for the permit have been completed — plan inspection scheduling (minimum 24 hours' notice) accordingly. (Change Of Use / Certificate Of Occupancy)
  • Beaver City is NOT a pure hand-off to the county. As of the county's own current guidance (How-to-Apply document, effective 5/1/2026), Beaver City operates its own independent City Inspect portal for zoning, permit application, and inspection scheduling, and payment is made in person at Beaver City offices — Beaver County's role there is limited to performing the physical inspections under contract. This is the same contracted-inspection pattern documented elsewhere in this corpus (e.g., West Bountiful), not a case where the county effectively administers the city's permitting. Confirms this corpus's 'ambiguous, lean-exclude' flag as correct: Beaver City should remain excluded/covered by its own file, not folded into this county file. (General)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Footings

    Interior/exterior and/or spot footings, with steel in place, prior to pouring concrete (IRC 109.5, per Beaver County Inspection Information page)

  2. 2

    Foundation

    With steel in place and prior to pouring concrete

  3. 3

    Underground Electrical and Plumbing

    Before backfill

  4. 4

    Framing

    Structural framing complete before insulation/wall cover

  5. 5

    Rough Plumbing / Rough Electrical / Rough Mechanical

    MEP systems roughed in, before wall closure

  6. 6

    Weather Resistive Barrier and Flashing

    Per IBC Section 1403.2-1405.3, before exterior finish

  7. 7

    Insulation and Vapor Barrier

    Before drywall

  8. 8

    Drywall / Firewall

    Before finish work

  9. 9

    Exterior: Siding, Brick, or Stucco

    Exterior finish inspection

  10. 10

    Gas Piping

    If applicable

  11. 11

    Electrical Service Panel

    Panel and service verification

  12. 12

    Final

    All safety aspects complete: electrical, handrails, smoke detectors, kitchens, bathrooms, and basic living facilities, per the county's FAQ on final inspection requirements

Applies to: Commercial Building Permit

  1. 1

    Footings

    Interior/exterior and/or spot footings, with steel in place, prior to pouring concrete (IRC 109.5 / IBC equivalent, per Beaver County Inspection Information page)

  2. 2

    Foundation

    With steel in place and prior to pouring concrete

  3. 3

    Underground Electrical and Plumbing

    Before backfill

  4. 4

    Framing

    Structural framing complete before insulation/wall cover

  5. 5

    Rough Plumbing / Rough Electrical / Rough Mechanical

    MEP systems roughed in, before wall closure

  6. 6

    Final

    All work complete, including electrical, before occupancy

Applies to: Solar / Solar-PV Installation Permit

  1. 1

    Structural/Roof-Mount Inspection

    Racking attachment, roof penetrations/flashing, and any ground-mount footings, administered by the Beaver County Building Department under the general Building permit

  2. 2

    Electrical Inspection

    Inverter, disconnects, new circuit/panel work, and interconnection point, administered under the Electrical/Plumbing/Mechanical/Roof permit

  3. 3

    Final

    Completed installation verified before the system is energized/put into service

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough-In

    Rough electrical, plumbing, or mechanical inspection before wall closure, as applicable to the scope of work

  2. 2

    Final

    Completed work verified before occupancy/reoccupancy

Applies to: Electrical / Mechanical / Plumbing / Roofing Permit

  1. 1

    Rough-In

    Rough electrical, rough plumbing, or rough mechanical inspection before wall closure, as applicable to the scope of work

  2. 2

    Final

    Completed work verified — electrical service panel, gas piping, or roofing final as applicable

Re-inspection fees

Residential Building PermitRe-Inspection Fee · Beaver County Fee Schedule 2026
$150
Electrical / Mechanical / Plumbing / Roofing PermitRe-Inspection Fee · Beaver County Fee Schedule 2026
$150
Commercial Building PermitRe-Inspection Fee · Beaver County Fee Schedule 2026
$150
Commercial Tenant Improvement / Tenant Finish PermitRe-Inspection Fee · Beaver County Fee Schedule 2026
$150
Solar / Solar-PV Installation PermitRe-Inspection Fee · Beaver County Fee Schedule 2026
$150
Change Of Use / Certificate Of OccupancyRe-Inspection Fee · Beaver County Fee Schedule 2026
$150

Unincorporated Beaver County building permits

Get alerts for Unincorporated Beaver County

We'll email you when Unincorporated Beaver County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.