Unincorporated Beaver County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Beaver County, Utah.
Verified 2026-07-08 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 105 East Center Street, Beaver, UT 84713 (mailing: P.O. Box 1013, Beaver, UT 84713)
- Phone
- (435) 438-6484
- Office hours
- Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 12:00 PM. Field inspections conducted 7:00 AM – 4:00 PM Monday–Thursday. Closed federal and local holidays.
- Website
- Official site
Published scheduling rules
- A certificate of occupancy will not be issued until all required inspections for the permit have been completed — plan inspection scheduling (minimum 24 hours' notice) accordingly. (Change Of Use / Certificate Of Occupancy)
- Beaver City is NOT a pure hand-off to the county. As of the county's own current guidance (How-to-Apply document, effective 5/1/2026), Beaver City operates its own independent City Inspect portal for zoning, permit application, and inspection scheduling, and payment is made in person at Beaver City offices — Beaver County's role there is limited to performing the physical inspections under contract. This is the same contracted-inspection pattern documented elsewhere in this corpus (e.g., West Bountiful), not a case where the county effectively administers the city's permitting. Confirms this corpus's 'ambiguous, lean-exclude' flag as correct: Beaver City should remain excluded/covered by its own file, not folded into this county file. (General)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footings
Interior/exterior and/or spot footings, with steel in place, prior to pouring concrete (IRC 109.5, per Beaver County Inspection Information page)
- 2
Foundation
With steel in place and prior to pouring concrete
- 3
Underground Electrical and Plumbing
Before backfill
- 4
Framing
Structural framing complete before insulation/wall cover
- 5
Rough Plumbing / Rough Electrical / Rough Mechanical
MEP systems roughed in, before wall closure
- 6
Weather Resistive Barrier and Flashing
Per IBC Section 1403.2-1405.3, before exterior finish
- 7
Insulation and Vapor Barrier
Before drywall
- 8
Drywall / Firewall
Before finish work
- 9
Exterior: Siding, Brick, or Stucco
Exterior finish inspection
- 10
Gas Piping
If applicable
- 11
Electrical Service Panel
Panel and service verification
- 12
Final
All safety aspects complete: electrical, handrails, smoke detectors, kitchens, bathrooms, and basic living facilities, per the county's FAQ on final inspection requirements
Applies to: Commercial Building Permit
- 1
Footings
Interior/exterior and/or spot footings, with steel in place, prior to pouring concrete (IRC 109.5 / IBC equivalent, per Beaver County Inspection Information page)
- 2
Foundation
With steel in place and prior to pouring concrete
- 3
Underground Electrical and Plumbing
Before backfill
- 4
Framing
Structural framing complete before insulation/wall cover
- 5
Rough Plumbing / Rough Electrical / Rough Mechanical
MEP systems roughed in, before wall closure
- 6
Final
All work complete, including electrical, before occupancy
Applies to: Solar / Solar-PV Installation Permit
- 1
Structural/Roof-Mount Inspection
Racking attachment, roof penetrations/flashing, and any ground-mount footings, administered by the Beaver County Building Department under the general Building permit
- 2
Electrical Inspection
Inverter, disconnects, new circuit/panel work, and interconnection point, administered under the Electrical/Plumbing/Mechanical/Roof permit
- 3
Final
Completed installation verified before the system is energized/put into service
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Rough-In
Rough electrical, plumbing, or mechanical inspection before wall closure, as applicable to the scope of work
- 2
Final
Completed work verified before occupancy/reoccupancy
Applies to: Electrical / Mechanical / Plumbing / Roofing Permit
- 1
Rough-In
Rough electrical, rough plumbing, or rough mechanical inspection before wall closure, as applicable to the scope of work
- 2
Final
Completed work verified — electrical service panel, gas piping, or roofing final as applicable
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Beaver County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Beaver County building permits
Get alerts for Unincorporated Beaver County
We'll email you when Unincorporated Beaver County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.