Solar / Solar-PV Installation Permit — Unincorporated Beaver County, Utah · Requirements sheet
Verified 2026-07-21 · Source: https://beaver.utah.gov/DocumentCenter/View/2403/2025-FEE-SCHEDULE
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar / Solar-PV Installation Permit in Unincorporated Beaver County, Utah
Beaver County does not publish a distinct solar or solar-PV permit type, application, checklist, or fee line item. A residential or commercial solar-PV installation in unincorporated Beaver County is processed under the same two general BUILDING-section fee lines that cover all other construction: the structural and roof-mounting scope (racking, roof penetrations, any new or altered structural support) falls under the general valuation-based Building permit ('Determined by the Current IBC/IRC'), and the electrical interconnection scope (inverter, disconnects, new circuits or panel work) falls under the flat $75.75 Electrical/Plumbing/Mechanical/Roof permit — the same combined trade-permit fee that covers EV chargers elsewhere in this record. No solar, photovoltaic, PV, or renewable-energy fee, form, or checklist appears anywhere in the 8 pages of the county's 2026 Fee Schedule PDF, the county's Permits page form list, the Building Permit Requirements page's 'Work Requiring/Not Requiring a Permit' lists, or the Fees & Payments page.
Verified 2026-07-21 · Source
When you need this permit
- Installation of a roof-mounted or ground-mounted solar photovoltaic (PV) system at a residential or commercial property in unincorporated Beaver County
- New or altered structural support (racking, roof penetrations, ground-mount footings) inspected under the state-adopted 2024 IBC/2021 IRC
- New electrical interconnection work (inverter, disconnects, branch circuits, panel/service modifications) inspected under the adopted 2023 National Electrical Code
- Licensed contractor, or owner-performed work on the owner's own residence with an Owner/Builder Certification Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Beaver County Fee Schedule 2026, BUILDING > Permits > 'Electrical/Plumbing/Mechanical/Roof' — the county's only published flat fee covering standalone electrical scopes, including a solar system's… Show full citationHide
Beaver County Fee Schedule 2026, BUILDING > Permits > 'Electrical/Plumbing/Mechanical/Roof' — the county's only published flat fee covering standalone electrical scopes, including a solar system's inverter/interconnection work. Independently confirmed on the Fees & Payments page ('Electrical, mechanical, plumbing, and roofing permits are $75.75') and the Building Department FAQ.Review timeline
Inspection process
- 1
Structural/Roof-Mount Inspection
Racking attachment, roof penetrations/flashing, and any ground-mount footings, administered by the Beaver County Building Department under the general Building permit
- 2
Electrical Inspection
Inverter, disconnects, new circuit/panel work, and interconnection point, administered under the Electrical/Plumbing/Mechanical/Roof permit
- 3
Final
Completed installation verified before the system is energized/put into service
See the full Unincorporated Beaver County inspection guide — scheduling & re-inspection fees →
Tips
- Beaver County has no distinct solar/PV permit type, application form, or fee line — plan on filing under both the general Building permit (structural/roof-mount scope) and the flat $75.75 Electrical/Plumbing/Mechanical/Roof permit (electrical interconnection scope), and confirm the exact split with the Building Department, (435) 438-6484, before applying.
- This is the same fee-folding pattern documented elsewhere in this record for EV charger installations — the county prices standalone electrical scope under one combined $75.75 flat fee rather than itemizing by equipment type.
- Ground-mount systems should also confirm the additional 23-foot road-improvement setback reservation (Beaver County Code § 9-1-7(C)) doesn't affect siting.
- Beaver County's frost depth (30 inches) and roof snow load (generally 30 lbs/sq ft in valley areas, engineering-determined above 6,200 ft elevation) apply to any new structural racking or ground-mount footings.
- All inspections require a minimum 24 hours' advance notice — call (435) 438-6484 or request online via beavercounty.cityinspect.com.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fee schedules
Applications & forms
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Beaver County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Unincorporated Beaver County's permit history is searchable by address
1,751 permits on record for Unincorporated Beaver County, 2014–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Unincorporated Beaver County
Solar / Solar-PV Installation Permit in other cities
Compare solar / solar-pv installation permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Beaver County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Beaver County — in one checklist. Free, for any city and any number of projects.
Get started →