Unincorporated Box Elder County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Box Elder County, Utah.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 1 S Main Street, Room 19, Brigham City, UT 84302
- Phone
- (435) 734-2634
- Office hours
- Monday through Friday, 8:00 AM to 5:00 PM (per Box Elder County Building Permits/Inspection page)
- Website
- Official site
Published scheduling rules
- The Chief Building Official is Codey Illum (cillum@boxeldercountyut.gov, 435-734-3303); day-to-day permit/inspection scheduling contacts are Diane Fuhriman and Jessie Fernelius at (435) 734-2634. (General)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footing
After trenches/holes excavated and forms/reinforcement in place, before concrete pour. UFER ground must be in place. Soil reports may be required.
- 2
Foundation
When reinforcement, forms, and all hold-downs/bolts are placed and ready, prior to pouring concrete.
- 3
Foundation Insulation
When required interior or exterior insulation is placed for slab-on-grade portions; energy compliance documents must be on site.
- 4
Sub-Rough Plumbing / Sub-Rough Mechanical / Sub-Rough Electrical
Under-slab plumbing, ductwork/radiant tubing, and raceway/conduit installed and placed under required test before slab pour.
- 5
Rough 4-Way
After electrical, mechanical, and plumbing roughs, roof and framing (including fire blocking/bracing), and windows/doors installed. All piping systems under required test.
- 6
Insulation
After Rough inspections approved and required wall/floor insulation completed per energy compliance documents.
- 7
Temporary Power
After pedestal or pole placed per Rocky Mountain Power requirements.
- 8
Power to Panel (Meter Set)
Rough completed, receptacles/outlets and covers installed, panel complete with feeders/breakers for circuits to be energized.
- 9
Final 4-Way
All permanent roofing, siding, veneers, exterior doors/windows, decks/guardrails, interior finishes, stairs (with guardrails/handrails), smoke/CO detectors, mechanical/electrical/plumbing fixtures, and finish grade/drainage complete.
Applies to: Commercial Building Permit
- 1
Footing
After trenches/holes excavated and forms/reinforcement in place, before concrete pour.
- 2
Foundation
When reinforcement, forms, and hold-downs/bolts are placed and ready, prior to pouring concrete.
- 3
Rough 4-Way
After electrical, mechanical, and plumbing roughs, roof and framing, windows/doors installed.
- 4
Fire Flow / Fire Marshal Review
If required by the Fire Marshal's recommendation prior to permit issuance, per the Commercial Building Permit Submittal Required Documents checklist.
- 5
Insulation
After Rough inspections approved and required insulation completed per energy compliance documents.
- 6
Final 4-Way
All permanent roofing, siding, exterior doors/windows, interior finishes, ADA accessible route/parking/restrooms (if applicable), and finish grade/drainage complete.
Applies to: Fire Sprinkler System Permit
- 1
Flow Test
One of the 3 included inspections for the Fire Sprinkler System Permit.
- 2
Hydrostatic Test
One of the 3 included inspections for the Fire Sprinkler System Permit.
- 3
Final Inspection
Final inspection of the installed fire sprinkler system.
Applies to: Accessory Dwelling Unit (ADU) / Internal ADU (IADU)
- 1
Conditional Use Permit Compliance Inspection
Following issuance of the conditional use permit, the Building Official may approve a building permit application once construction plans meet the conditions/requirements established by the Planning Commission.
- 2
Final / Certificate of Occupancy Inspection
Building department representatives inspect the completed project to ensure all required improvements meet the conditional use permit conditions and Chapter 5-6 before a certificate of occupancy is issued.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Rough 4-Way
Rough electrical, mechanical, and plumbing as applicable to the tenant-improvement scope, before wall closure.
- 2
Final
Completed work verified, including any ADA accessibility items affected by the scope, before reoccupancy.
Applies to: Residential Solar Photovoltaic (PV) System Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing, per NEC requirements.
- 2
Solar Inspection / Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and grounding/bonding verified.
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Box Elder County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Box Elder County building permits
Get alerts for Unincorporated Box Elder County
We'll email you when Unincorporated Box Elder County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.