Residential Building Permit in Unincorporated Box Elder County, Utah
Required for new single-family home construction and additions in unincorporated Box Elder County. The county uses the State ICC valuation-based fee structure rather than a published flat fee table.
Verified 2026-07-03 · Source
When you need this permit
- New single-family dwelling construction
- Additions and structural alterations
- Site plan with zoning approval — orientation of site plan must match orientation of building plans
- Engineering package and stamped structural pages where applicable
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing
After trenches/holes excavated and forms/reinforcement in place, before concrete pour. UFER ground must be in place. Soil reports may be required.
- 2
Foundation
When reinforcement, forms, and all hold-downs/bolts are placed and ready, prior to pouring concrete.
- 3
Foundation Insulation
When required interior or exterior insulation is placed for slab-on-grade portions; energy compliance documents must be on site.
- 4
Sub-Rough Plumbing / Sub-Rough Mechanical / Sub-Rough Electrical
Under-slab plumbing, ductwork/radiant tubing, and raceway/conduit installed and placed under required test before slab pour.
- 5
Rough 4-Way
After electrical, mechanical, and plumbing roughs, roof and framing (including fire blocking/bracing), and windows/doors installed. All piping systems under required test.
- 6
Insulation
After Rough inspections approved and required wall/floor insulation completed per energy compliance documents.
- 7
Temporary Power
After pedestal or pole placed per Rocky Mountain Power requirements.
- 8
Power to Panel (Meter Set)
Rough completed, receptacles/outlets and covers installed, panel complete with feeders/breakers for circuits to be energized.
- 9
Final 4-Way
All permanent roofing, siding, veneers, exterior doors/windows, decks/guardrails, interior finishes, stairs (with guardrails/handrails), smoke/CO detectors, mechanical/electrical/plumbing fixtures, and finish grade/drainage complete.
See the full Unincorporated Box Elder County inspection guide — scheduling & re-inspection fees →
Tips
- Box Elder County adopts the 'State ICC Fee Structure' for building permit fees rather than publishing a flat valuation table — the exact dollar fee is not published online; confirm with the Building Official (435-734-3303 / cillum@boxeldercountyut.gov) for a specific project valuation.
- Standard processing time for all permits is 7 to 10 business days once the office receives all required documents, per the county's own Building Permits/Inspection page.
- 24-hour advance notice is required for all inspections — schedule with Diane or Jessie at (435) 734-2634, dfuhriman@boxeldercountyut.gov, or jfernelius@boxeldercountyut.gov.
- Design Criteria handout lists 43 PSF ground snow load, 90 mph 3-second gust wind speed, Seismic Design Category D (typical), and 30-inch frost depth — use these for prescriptive design in the absence of a site-specific report.
- A Fire Flow (water availability) report may be required by the Fire Marshal before a permit is issued.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Box Elder County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Box Elder County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Box Elder County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Box Elder County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →