Box Elder County's 2026 Fee Schedule for County Fire lists a Fire Sprinkler System permit as its own line item under Fire Protection Systems, tiered by square footage. Plan review is handled by a required third party at no county fee, while the installation permit itself (flow, hydro, final inspections) carries a flat $300.00 county fee across all size tiers.

Verified 2026-07-20 · Source

When you need this permit

  • Fire Sprinkler System plans require third-party plan review for submission, tiered by square footage (0-3,000 / 3,001-10,000 / 10,001+ sq ft) — the county charges no fee for this plan review step
  • Permit (flow, hydro, final) includes 3 inspections and costs $300.00 regardless of size tier, per Box Elder County's 2026 Fee Schedule for County Fire
  • Plan Re-inspection (each additional inspection beyond the 3 included) is $100.00

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review — 0-3,000 sq ft (includes 1 plan review)Box Elder County 2026 Fee Schedule for County Fire, Fire Protection Systems — Fire Sprinkler System, directly fetched 2026-07-20 (boxeldercountyut.gov/583/2026-Fee-Schedule-for-County-Fire).
No County fee, but Third party review required for submission
Plan Review — 3,001-10,000 sq ft (includes 1 plan review)Same source as above.
No County fee, but Third party review required for submission
Plan Review — 10,001+ sq ftSame source as above.
No County fee, but Third party review required for submission
Permit (flow, hydro, final) — 0-3,000 sq ft (includes 3 inspections)Same source as above.
$300.00
Permit (flow, hydro, final) — 3,001-10,000 sq ft (includes 3 inspections)Same source as above.
$300.00
Permit (flow, hydro, final) — 10,001+ sq ft (includes 3 inspections)Same source as above.
$300.00
Plan Re-inspection (each additional inspection)Same source as above.
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler System Permit permit actually take in Unincorporated Box Elder County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Flow Test

    One of the 3 included inspections for the Fire Sprinkler System Permit.

  2. 2

    Hydrostatic Test

    One of the 3 included inspections for the Fire Sprinkler System Permit.

  3. 3

    Final Inspection

    Final inspection of the installed fire sprinkler system.

See the full Unincorporated Box Elder County inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike Roy City's and Santaquin's tiered sprinkler permit fees, Box Elder County's Fire Sprinkler System Permit is a flat $300.00 regardless of square footage tier — only the plan review step is tiered by size, and that step carries no county fee (just a required third-party review cost).
  • Budget separately for the third-party plan reviewer's own fee, which is not set by the county and not published in this fee schedule.

Frequently asked questions

Unincorporated Box Elder County requires a fire sprinkler system permit for: Fire Sprinkler System plans require third-party plan review for submission, tiered by square footage (0-3,000 / 3,001-10,000 / 10,001+ sq ft) — the county charges no fee for this plan review step; Permit (flow, hydro, final) includes 3 inspections and costs $300.00 regardless of size tier, per Box Elder County's 2026 Fee Schedule for County Fire; Plan Re-inspection (each additional inspection beyond the 3 included) is $100.00. If your project isn't listed, confirm with Box Elder County Building Permits / Inspection at (435) 734-2634 before starting work.

Per Box Elder County's 2026 Fee Schedule for County Fire, the Fire Sprinkler System Permit (flow, hydro, final — includes 3 inspections) is a flat $300.00 regardless of size tier. Plan review carries no county fee but requires a required third-party reviewer, whose fee is separate and not set by the county. Additional inspections beyond the 3 included are $100.00 each.

Unincorporated Box Elder County does not publish a plan-review timeline for this permit. Contact Box Elder County Building Permits / Inspection at (435) 734-2634 for current turnaround.

You'll need: Fire Sprinkler System plans (third-party reviewed). See the required-documents checklist on this page for details on each.

Unincorporated Box Elder County requires 3 inspection(s) for a fire sprinkler system permit, in order: Flow Test, Hydrostatic Test, Final Inspection. Schedule each through Box Elder County Building Permits / Inspection ((435) 734-2634).

Apply through Box Elder County Building Permits / Inspection at 1 S Main Street, Room 19, Brigham City, UT 84302. Phone: (435) 734-2634, email: cillum@boxeldercountyut.gov. Office hours: Monday through Friday, 8:00 AM to 5:00 PM (per Box Elder County Building Permits/Inspection page). Official information: https://www.boxeldercountyut.gov/195/Building-Permits-Inspection.

Unincorporated Box Elder County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — governs per Utah Code §15A-2-103(1)(a) (https://le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), in force statewide since 7/1/2026 and binding on counties under §15A-1-204. Box Elder County's own '2021 Adopted Code' document (DocumentCenter/View/173) still lists the 2021 IBC with Appendix J only (no Appendix C) — live-checked 2026-07-16, the county's own document has not been updated to the current statewide edition.; 2021 International Residential Code (IRC), including Appendix AQ — governs per Utah Code §15A-2-103(1)(b)/(c); this edition is UNCHANGED from the prior code cycle. Box Elder County's own document lists the 2021 IRC (without a distinct Appendix AQ citation) — live-checked 2026-07-16, consistent with the current statute on the base edition.; 2024 International Plumbing Code (IPC) — governs per Utah Code §15A-2-103(1)(d). Box Elder County's own document still lists the 2021 IPC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Mechanical Code (IMC) — governs per Utah Code §15A-2-103(1)(e). Box Elder County's own document still lists the 2021 IMC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Fuel Gas Code (IFGC) — governs per Utah Code §15A-2-103(1)(f). Box Elder County's own document still lists the 2021 IFGC — live-checked 2026-07-16, lags the current statewide edition.; 2023 National Electrical Code (NEC) — governs per Utah Code §15A-2-103(1)(g); this edition is UNCHANGED from the prior code cycle. Box Elder County's own '2021 Adopted Code' document lists the 2017 NEC — live-checked 2026-07-16, a genuine and long-standing discrepancy in the county's own published document (not a transcription error); confirm the currently enforced edition directly with the Chief Building Official, Codey Illum, at (435) 734-3303 before relying on this for a live electrical project.; 2024 International Energy Conservation Code (IECC) — one code, no residential/commercial split, per Utah Code §15A-2-103(1)(h). Box Elder County's own document lists the 2021 IECC (also undifferentiated by residential/commercial) — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Existing Building Code (IEBC), subject to Utah Code §15A-2-104(2) (the HUD Code) — governs per Utah Code §15A-2-103(1)(i)/(j). Box Elder County's own document lists the 2021 IEBC — live-checked 2026-07-16, lags the current statewide edition.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — governs statewide per Utah Code §15A-2-103(1)(n). Box Elder County's own '2021 Adopted Code' document does not list any ISPSC edition — live-checked 2026-07-16; added here per the statute, not omitted.; Modular Building Institute (MBI) Standards 1200 and 1205 — governs statewide per Utah Code §15A-2-103(1)(o). Not separately listed in Box Elder County's own '2021 Adopted Code' document — live-checked 2026-07-16.. Local amendments apply — see the Unincorporated Box Elder County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Box Elder County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.