Electrical Permit (Meter Upgrade / Generator / Battery) — Unincorporated Box Elder County, Utah · Requirements sheet
Verified 2026-07-03 · Source: https://www.boxeldercountyut.gov/587/2026-Fee-Schedule-for-Buildings-Grounds
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical Permit (Meter Upgrade / Generator / Battery) in Unincorporated Box Elder County, Utah
Required for gas & electric meter upgrades, generator, and battery installations in unincorporated Box Elder County. These are listed as their own flat-fee line items in the county fee schedule, distinct from the general valuation-based building permit fee.
Verified 2026-07-03 · Source
When you need this permit
- Meter upgrade (gas or electric)
- Generator or battery storage installation
- Compliance with the 2023 NEC, which governs per Utah Code §15A-2-103(1)(g); Box Elder County's own published adopted-code document still lists the 2017 NEC (live-checked 2026-07-16) — confirm the currently enforced edition with the Building Official before starting work
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Power to Panel (Meter Set)
Rough completed, receptacles/outlets and covers installed, panel complete with feeders/breakers for circuits to be energized.
See the full Unincorporated Box Elder County inspection guide — scheduling & re-inspection fees →
Tips
- Meter upgrades, generators, batteries, and pumps have their own flat fees separate from the valuation-based building permit fee — see the 2026 Fee Schedule for Buildings & Grounds.
- A Gas Clearance Form is listed among the county's Forms & Applications for gas-related work.
- 24-hour advance notice is required for all inspections.
- Installing a home EV charger (new branch circuit) falls under this general Electrical Permit — the county does not publish a separate EV-charger fee like it does for meter upgrades, generators, or batteries.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Box Elder County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Box Elder County
Electrical Permit (Meter Upgrade / Generator / Battery) in other cities
Compare electrical permit (meter upgrade / generator / battery) fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Box Elder County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Box Elder County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →