New Commercial Building Permit in Woods Cross, Utah

Required for new commercial construction in Woods Cross. Requires prior Development Review Committee (DRC) and Planning Commission approval before a building permit application may be submitted; fees follow the same Table 3-A valuation schedule as residential.

Verified 2026-07-08 · Source

When you need this permit

  • Planning Commission final approval of the project (via Development Review Committee review) required before a building permit application may be submitted
  • Site plan including ADA compliance requirements and parking with signage/striping details
  • Construction plans electronically stamped by the architect, structural engineer, electrical engineer, and mechanical engineer
  • Supporting documentation: structural calculations, project manual, energy analysis documents, soils report, as applicable
  • Project valuation (labor and materials, excluding land/equipment/site improvements)
  • Contractor Construction Bond Agreement ($10 per linear foot of public street frontage) Contractor
  • SWPPP (Storm Water Pollution Prevention Plan) copy, with a second copy and the UPDES permit posted onsite at all times
  • Project approval letter from the South Davis Metro Fire Marshal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, Table 3-A, 1997 Uniform Administrative Code as locally adjusted)Woods Cross City Consolidated Fee Schedule, Exhibit 1 / Table 3-A (Resolution 2026-967, Version #75, adopted 2/17/26); the fee schedule does not use a separate commercial table.
Same Table 3-A schedule as the Residential Building Permit: e.g., $100,001–$500,000 valuation = $1,045.80 + $5.90 per additional $1,000.
Plan Review DepositWoods Cross New Commercial Buildings permit handout: 'A Plan Review Deposit Fee of $250 must be paid when the permit application is submitted.'
$250.00
Plan Review FeeConsolidated Fee Schedule, 'BUILDING' section.
65% of the Permit Fee
Investigation FeeConsolidated Fee Schedule, 'BUILDING' section.
100% of the Permit Fee
State FeeConsolidated Fee Schedule, 'BUILDING' section.
1% of the Permit Fee
Construction Bond (commercial/other)Consolidated Fee Schedule 'BUILDING BONDS' section: 'All other* $10.00 per linear feet of public street frontage.' Not required if building valuation is under $60,000.
$10.00 per linear foot of public street frontage

Review timeline

Plan reviewWoods Cross’s published plan-review target
21–21 business days

How long did your New Commercial Building Permit permit actually take in Woods Cross?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building, Electrical, Mechanical, Plumbing (staged per 1997 UAC/adopted codes)

    Scheduled through Beacon Code Consultants (801-564-0897 or 801-726-1606) per Woods Cross's inspection scheduling process.

  2. 2

    Final / Certificate of Occupancy

    Final inspection required before occupancy.

See the full Woods Cross inspection guide — scheduling & re-inspection fees →

Tips

  • New commercial construction cannot go straight to a building permit application — it must first clear Development Review Committee review and receive final Planning Commission approval.
  • A South Davis Metro Fire Marshal approval letter is a hard gate: the New Commercial Buildings handout states the fire marshal's project approval letter is required as part of the application package.
  • Sewer approvals and fees are handled separately by South Davis Sewer District (801-292-3469 per this handout; the Sewer District's own materials list 801-295-3469) and are not part of the city building permit.

Frequently asked questions

Woods Cross requires a new commercial building permit for: Planning Commission final approval of the project (via Development Review Committee review) required before a building permit application may be submitted; Site plan including ADA compliance requirements and parking with signage/striping details; Construction plans electronically stamped by the architect, structural engineer, electrical engineer, and mechanical engineer; Supporting documentation: structural calculations, project manual, energy analysis documents, soils report, as applicable; Project valuation (labor and materials, excluding land/equipment/site improvements); Contractor Construction Bond Agreement ($10 per linear foot of public street frontage); SWPPP (Storm Water Pollution Prevention Plan) copy, with a second copy and the UPDES permit posted onsite at all times; Project approval letter from the South Davis Metro Fire Marshal. If your project isn't listed, confirm with Woods Cross City Building Division (Community Development Department) at (801) 292-4421 Ext. 2002 before starting work.

In Woods Cross, the published Building Permit Fee (valuation-based, Table 3-A, 1997 Uniform Administrative Code as locally adjusted) is: Same Table 3-A schedule as the Residential Building Permit: e.g., $100,001–$500,000 valuation = $1,045.80 + $5.90 per additional $1,000.. Additional published fees: Plan Review Deposit — $250.00; Plan Review Fee — 65% of the Permit Fee; Investigation Fee — 100% of the Permit Fee; State Fee — 1% of the Permit Fee; Construction Bond (commercial/other) — $10.00 per linear foot of public street frontage. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the city's official New Commercial Buildings permit handout, plan review takes approximately 21 working days from the date a complete application is submitted, following required Development Review Committee and Planning Commission approval.

You'll need: Site Plan Approval Application; Building Permit Application (City Inspect Portal); South Davis Metro Fire Marshal Approval Letter; SWPPP / UPDES Permit. See the required-documents checklist on this page for details on each.

Woods Cross requires 2 inspection(s) for a new commercial building permit, in order: Building, Electrical, Mechanical, Plumbing (staged per 1997 UAC/adopted codes), Final / Certificate of Occupancy. Schedule each through Woods Cross City Building Division (Community Development Department) ((801) 292-4421 Ext. 2002).

Apply through Woods Cross City Building Division (Community Development Department) at 1555 South 800 West, Woods Cross, UT 84087. Phone: (801) 292-4421 Ext. 2002, email: permits@woodscross.com. Office hours: Mon–Thu 7:30 AM – 5:00 PM (some permit handouts list 7:30 AM–5:30 PM Mon–Thu and 7:30–11:30 AM Fri); closed Fri afternoon–Sun and holidays per the Building Services contact page. Official information: https://www.woodscross.gov/194/Building-Services.

Woods Cross, Utah has adopted: 2021 International Residential Code (IRC) with Appendix AE and AQ — REMAINS CURRENT per Utah Code § 15A-2-103(1)(b)/(c), UNCHANGED by the 7/1/2026 statewide amendment. Consistent with Woods Cross City's official Building Codes and Design Criteria handout (re-fetched live 2026-07-16, unchanged).; 2015 International Residential Code Chapter 11 (residential energy provisions) — CORRECTED/SUPERSEDED: Utah Code § 15A-2-103(1)(h) adopts a single unsplit 2024 IECC statewide as of 7/1/2026 (see the consolidated IECC entry below); this pre-existing residential-energy carve-out to the 2015 edition no longer reflects the current statute. Woods Cross's own Building Codes and Design Criteria handout (re-fetched live 2026-07-16) still lists '2015 International residential Code Chapter 11' under 'RESIDENTIAL BUILDING CODES' and has not been updated — preserved here as recorded history, not deleted.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(n); supersedes the 2021 edition. Woods Cross's Building Codes and Design Criteria handout (re-fetched live 2026-07-16) still lists '2021 International Swimming Pool and Spa Code' and has not been updated.; 2024 International Building Code (IBC) with Appendix C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition. Woods Cross's handout labels this 'COMMERCIAL CONSTRUCTION BUILDING CODES' but § 15A-2-103 does not itself carry a residential/commercial IBC split — the IBC applies per the statute regardless of the handout's section heading. Woods Cross's handout (re-fetched live 2026-07-16) still lists '2021 International Building Code with Appendix C and J' and has not been updated.; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); supersedes the 2021 edition. Woods Cross's handout (re-fetched live 2026-07-16) still lists '2021 International Mechanical Code' and has not been updated.; 2021 International Fire Code (IFC) — per Woods Cross City Building Codes and Design Criteria handout; NOTE: the IFC is adopted under Utah Code Title 15A Chapter 5, not § 15A-2-103 (which governs the IBC/IRC/IPC/IMC/IFGC/IECC/IEBC/NEC/residential-ISPSC/MBI editions in this array) — § 15A-2-103 does not itself adopt or list an IFC edition, so this entry is unaffected by the 7/1/2026 § 15A-2-103 amendment.; 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); supersedes the 2021 edition. Woods Cross's handout (re-fetched live 2026-07-16) still lists '2021 International Plumbing Code' and has not been updated.; 2024 International Fuel Gas Code (IFGC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f); supersedes the 2021 edition. Woods Cross's handout (re-fetched live 2026-07-16) still lists '2021 International Fuel Gas Code' and has not been updated.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); supersedes both the 2021 edition Woods Cross's handout lists under 'COMMERCIAL CONSTRUCTION BUILDING CODES' and the 2015 IRC Chapter 11 residential-energy carve-out listed separately under 'RESIDENTIAL BUILDING CODES' (see history entry above) — § 15A-2-103 does not carry a residential/commercial IECC split. Woods Cross's handout (re-fetched live 2026-07-16) has not been updated for either.; 2023 National Electrical Code (NEC) — CURRENT statewide per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment (2023 has been the statewide NEC edition since before this cycle). CORRECTED: Woods Cross City's Building Codes and Design Criteria handout (re-fetched live 2026-07-16, unchanged) lists '2020 National Electrical Code,' which is NOT a valid statewide-adopted edition — this file previously flagged the discrepancy but had not yet cited the statute directly or resolved which edition is correct; the statute controls and 2023 is confirmed correct. Confirm the currently enforced NEC edition directly with the Building Department before relying on the City's own document for a live project.; 2024 International Existing Building Code (IEBC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(i); supersedes the 2021 edition. Woods Cross's handout (re-fetched live 2026-07-16) still lists '2021 International Existing Building Code' and has not been updated.; 2009 ICC/ANSI A117.1 Accessible and Usable Buildings and Facilities — per Woods Cross City Building Codes and Design Criteria handout; not governed by § 15A-2-103, which does not itself adopt an ICC/ANSI A117.1 edition.; MBI 1200 and MBI 1205 (manufactured/modular construction standards) — statewide per Utah Code § 15A-2-103(1)(o); not itemized in Woods Cross's own Building Codes and Design Criteria handout, added here per statute.; All codes above are noted on the city's official handout as 'As adopted by the State of Utah. See Utah Code Title 15A for a complete list of adopted codes and amendments.'; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Woods Cross's own Building Codes and Design Criteria handout was re-fetched live 2026-07-16 and is unchanged: it still lists 2021 IBC/IMC/IPC/IFGC/IECC/IEBC/ISPSC, a 2015 IRC Chapter 11 residential-energy carve-out, and an outright incorrect '2020 National Electrical Code' — none of these have been updated by the City to reflect the statewide 7/1/2026 transition or the pre-existing 2023 NEC requirement. The statute is cited directly as governing throughout; the City's lagging handout is preserved above as recorded history, not deleted.. Local amendments apply — see the Woods Cross overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Woods Cross building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter