New Commercial Building Permit in Woods Cross, Utah
Required for new commercial construction in Woods Cross. Requires prior Development Review Committee (DRC) and Planning Commission approval before a building permit application may be submitted; fees follow the same Table 3-A valuation schedule as residential.
Verified 2026-07-08 · Source
When you need this permit
- Planning Commission final approval of the project (via Development Review Committee review) required before a building permit application may be submitted
- Site plan including ADA compliance requirements and parking with signage/striping details
- Construction plans electronically stamped by the architect, structural engineer, electrical engineer, and mechanical engineer
- Supporting documentation: structural calculations, project manual, energy analysis documents, soils report, as applicable
- Project valuation (labor and materials, excluding land/equipment/site improvements)
- Contractor Construction Bond Agreement ($10 per linear foot of public street frontage) Contractor
- SWPPP (Storm Water Pollution Prevention Plan) copy, with a second copy and the UPDES permit posted onsite at all times
- Project approval letter from the South Davis Metro Fire Marshal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building, Electrical, Mechanical, Plumbing (staged per 1997 UAC/adopted codes)
Scheduled through Beacon Code Consultants (801-564-0897 or 801-726-1606) per Woods Cross's inspection scheduling process.
- 2
Final / Certificate of Occupancy
Final inspection required before occupancy.
See the full Woods Cross inspection guide — scheduling & re-inspection fees →
Tips
- New commercial construction cannot go straight to a building permit application — it must first clear Development Review Committee review and receive final Planning Commission approval.
- A South Davis Metro Fire Marshal approval letter is a hard gate: the New Commercial Buildings handout states the fire marshal's project approval letter is required as part of the application package.
- Sewer approvals and fees are handled separately by South Davis Sewer District (801-292-3469 per this handout; the Sewer District's own materials list 801-295-3469) and are not part of the city building permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Woods Cross building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Woods Cross.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Woods Cross
New Commercial Building Permit in other cities
Compare new commercial building permit fees across Utah →
Look up this fee in a different city →