Change of Use / Certificate of Occupancy Review — Woods Cross, Utah · Requirements sheet
Reviewed 2026-07-22 · Source: https://www.woodscross.gov/193/Business-Licensing
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Certificate of Occupancy Review in Woods Cross, Utah
Woods Cross does not publish a standalone 'Change of Use Permit' or 'Certificate of Occupancy application' distinct from the processes already documented in this file. A direct search of the Building Services document index (woodscross.gov/194/Building-Services), the Zoning Ordinances index (woodscross.gov/186/Zoning-Ordinances), and the Business Licensing page (woodscross.gov/193/Business-Licensing) found no dedicated change-of-use handout. Instead, a change in use of an existing commercial space in Woods Cross is gated through two existing, official mechanisms: (1) the City's online Business License application, whose plan-review stage routes every new license through Planning, Fire Marshal, and Business Licensing department review — including a 'Land Use Classification / Use Permitted in the Zone (Permitted / Conditional Use / Conditional Use w/ Limitations / Not Permitted)' checklist item, per the City's official 'How to Apply' business-license guide — before a business may occupy the space; and (2) Woods Cross Zoning Ordinance Chapter 12-4 (Zoning Administration), § 12-4-105 'Zoning Enforcement,' which directs the Community Development Director to 'oversee the inspection of all buildings in course of construction, alteration or repair, and any change in the use of land,' confirming that a change in land use is itself a zoning-enforcement event the City tracks, even though no separate permit application or fee line item is published for it. If the new use requires physical modifications to the space, that work is filed under this file's existing 'commercial-tenant-improvement-permit' entry, which itself notes Woods Cross has no dedicated TI handout either — both entries point to the same underlying gap in the City's published permit-type catalog. A final Certificate of Occupancy for new construction is issued as part of the final inspection already documented under the New Residential Buildings and New Commercial Buildings permit types in this file; Woods Cross's own Landscape Standards ordinance (Chapter 12-25) and Building Bond provisions (City Code § 10-3-110) both separately condition CO issuance on landscape completion and bond compliance, respectively.
Reviewed 2026-07-22 · Source
When you need this permit
- A new business occupying an existing commercial space, or an existing business changing its use/tenant classification, must obtain a City of Woods Cross Business License before beginning operations, per the City's online licensing portal (accessed via the Business Licensing page)
- The Business License plan-review stage includes a Planning Department checklist item verifying 'Land Use Classification / Use Permitted in the Zone (Permitted / Conditional Use / Conditional Use w/ Limitations / Not Permitted)' for the proposed use at the specific address, per the City's official 'How to Apply' business-license guide
- Fire Marshal review is a required department on the Business License plan-review workflow, alongside Planning and Business Licensing, per the same official guide
- Per Woods Cross Zoning Ordinance § 12-4-105, 'any change in the use of land' falls within the Community Development Director's zoning-inspection and enforcement authority, distinct from (but related to) the Business License review
- If the new use requires structural, electrical, mechanical, or plumbing modifications to the space, a separate building permit is required — see this file's 'commercial-tenant-improvement-permit' entry
- A Certificate of Occupancy for new construction is issued only after all required building final inspections are complete and, per the City's Landscape Standards ordinance (Chapter 12-25), after all landscape improvements shown on the approved site/landscape plan are completed (or bonded, for up to 120 days, in cases of seasonal/weather delay)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Fire Marshal Business License Inspection
Fire Marshal is a standing reviewing department on every Business License plan review, per the City's official 'How to Apply' guide; may include an on-site life-safety inspection depending on occupancy classification.
- 2
Final Building Inspection / Certificate of Occupancy (if the space was newly constructed or altered)
Only applicable when the change of use is paired with new construction or a tenant-improvement building permit; see the New Commercial Buildings and Commercial Tenant Improvement entries in this file for the underlying inspection sequence.
See the full Woods Cross inspection guide — scheduling & re-inspection fees →
Tips
- Woods Cross does not have a form or process literally named 'Change of Use Permit' or 'Certificate of Occupancy Application' — a new business or a use change in an existing commercial space is instead screened through the City's online Business License plan review, which checks land use classification/zoning permissibility for the address before a license (and therefore occupancy) is granted.
- Apply for the Business License well before the planned opening date — plan review routes through multiple departments (Planning, Fire Marshal, Business Licensing) and no published turnaround SLA exists for this workflow.
- If the new use requires any construction, electrical, plumbing, or mechanical work, that work needs its own building permit (see 'commercial-tenant-improvement-permit') in addition to, not instead of, the Business License application.
- A Certificate of Occupancy issued for new construction is contingent on completed landscaping per Chapter 12-25 and, where applicable, satisfaction of the Building Bond requirements under City Code § 10-3-110 — incomplete landscaping can delay CO issuance by up to 120 days under a completion bond.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Woods Cross building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Woods Cross
Change of Use / Certificate of Occupancy Review in other cities
Compare change of use / certificate of occupancy review fees across Utah →
Look up this fee in a different city →