Unincorporated Juab County building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Juab County, Utah.
Verified 2026-07-08 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 160 N Main Street, Office #117, Nephi, UT 84648
- Phone
- (435) 623-3400
- Office hours
- Monday–Thursday 7:00 AM – 6:00 PM
- Website
- Official site
Published scheduling rules
- Utah Code § 17-36-55(3)(a) sets a 14-business-day statutory ceiling for county plan review of one-to-two-family dwellings and townhomes, measured from a complete application; a separate 3-business-day maximum applies to inspection scheduling response under § 17-36-55(2)(b). (General)
Inspection sequence
Applies to: Commercial Building Permit
- 1
Footing / Foundation
Before concrete pour — verify excavation, forms, rebar placement, and foundation type matches the permit application, per the same inspection sequence documented for residential permits in this county.
- 2
Framing
After framing and rough-in MEP, before insulation or wall cover.
- 3
Final
All work complete. Occupancy of the structure is prohibited until after final inspection and a Certificate of Occupancy is issued.
Applies to: Residential Building Permit
- 1
Footing / Foundation
Before concrete pour — verify excavation, forms, rebar placement, and foundation type matches the permit application
- 2
Framing
After framing and rough-in MEP, before insulation or wall cover
- 3
Final
All work complete. Occupancy of the structure is prohibited until after final inspection and a Certificate of Occupancy is issued, per the Juab County Building Permit Application's applicant certification language.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural (if applicable)
Verified before close-in where the tenant improvement scope includes framing or structural changes.
- 2
Final
All work complete; occupancy of the tenant space is prohibited until after final inspection and Certificate of Occupancy issuance.
Applies to: Solar PV Installation Permit
- 1
Electrical Inspection
Verification of PV system wiring, inverter/disconnect installation, and interconnection per NEC Article 690, performed under the general Building Permit inspection process. Specific solar inspection checklist not separately published online.
- 2
Final
Final inspection and sign-off before the system may be energized/interconnected; occupancy/use restrictions from the general Building Permit Application apply to any structural work performed alongside the installation.
Final inspection only: Change of Use / Change of Occupancy Permit, EV Charger / EVSE Permit, Fire Sprinkler & Fire Alarm Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Juab County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Juab County building permits
Get alerts for Unincorporated Juab County
We'll email you when Unincorporated Juab County's fees, documents, or codes change — not often.