Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Juab County, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
160 N Main Street, Office #117, Nephi, UT 84648
Phone
(435) 623-3400
Email
Office hours
Monday–Thursday 7:00 AM – 6:00 PM

Published scheduling rules

  • Utah Code § 17-36-55(3)(a) sets a 14-business-day statutory ceiling for county plan review of one-to-two-family dwellings and townhomes, measured from a complete application; a separate 3-business-day maximum applies to inspection scheduling response under § 17-36-55(2)(b). (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour — verify excavation, forms, rebar placement, and foundation type matches the permit application, per the same inspection sequence documented for residential permits in this county.

  2. 2

    Framing

    After framing and rough-in MEP, before insulation or wall cover.

  3. 3

    Final

    All work complete. Occupancy of the structure is prohibited until after final inspection and a Certificate of Occupancy is issued.

Applies to: Residential Building Permit

  1. 1

    Footing / Foundation

    Before concrete pour — verify excavation, forms, rebar placement, and foundation type matches the permit application

  2. 2

    Framing

    After framing and rough-in MEP, before insulation or wall cover

  3. 3

    Final

    All work complete. Occupancy of the structure is prohibited until after final inspection and a Certificate of Occupancy is issued, per the Juab County Building Permit Application's applicant certification language.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Verified before close-in where the tenant improvement scope includes framing or structural changes.

  2. 2

    Final

    All work complete; occupancy of the tenant space is prohibited until after final inspection and Certificate of Occupancy issuance.

Applies to: Solar PV Installation Permit

  1. 1

    Electrical Inspection

    Verification of PV system wiring, inverter/disconnect installation, and interconnection per NEC Article 690, performed under the general Building Permit inspection process. Specific solar inspection checklist not separately published online.

  2. 2

    Final

    Final inspection and sign-off before the system may be energized/interconnected; occupancy/use restrictions from the general Building Permit Application apply to any structural work performed alongside the installation.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Juab County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Juab County building permits

Get alerts for Unincorporated Juab County

We'll email you when Unincorporated Juab County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.