Skip to main content
PermitBase

Accessory Structure Permit (Garage, Pool, Storage, Detached Structures) in Morgan County, Utah

Required for detached garages, storage buildings, swimming pools, and other residential accessory structures in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department.

Verified 2026-07-08 · Source

When you need this permit

  • Detached garage, storage building, swimming pool, or other accessory structure
  • Non-refundable $50 preplan review deposit due at application
  • Submission through Civic Review portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Garage/Swimming Pool/Accessory Structure — Preplan Review DepositMorgan County Building Permit Fees and Worksheet (Rev 9-2021). Non-refundable, applied toward actual plan review fees; remaining fee calculated per project valuation plus 1% State fee and possible impact fees.
$50.00
Performance Bond (pools and accessory buildings, if public infrastructure affected)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
$2,500 or $15 per linear foot of frontage, whichever is greater

Review timeline

Plan review
Not published — contact the department

How long did your Accessory Structure Permit (Garage, Pool, Storage, Detached Structures) permit actually take in Morgan County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structure framing complete

  3. 3

    Final

    All work complete

See the full Morgan County inspection guide — scheduling & re-inspection fees →

Tips

  • Morgan County Planning and Development Services issues accessory structure permits for the entire county, including Morgan City.
  • A Performance Bond may apply for pools and accessory buildings if curb, gutter, sidewalk, or storm drainage facilities exist on the frontage.

Frequently asked questions

Morgan County requires an accessory structure permit (garage, pool, storage, detached structures) for: Detached garage, storage building, swimming pool, or other accessory structure; Non-refundable $50 preplan review deposit due at application; Submission through Civic Review portal. If your project isn't listed, confirm with Morgan County Planning and Development Services at 801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director) before starting work.

A non-refundable $50 preplan review deposit is due at application per the Morgan County Building Permit Fees and Worksheet (Rev 9-2021). The remaining fee is calculated per project valuation plus 1% State fee and possible impact fees.

Morgan County does not publish a plan-review timeline for this permit. Contact Morgan County Planning and Development Services at 801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director) for current turnaround.

You'll need: Civic Review Application; Site Plan. See the required-documents checklist on this page for details on each.

Morgan County requires 3 inspection(s) for an accessory structure permit (garage, pool, storage, detached structures), in order: Foundation/Footing, Framing, Final. Schedule each through Morgan County Planning and Development Services (801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director)).

Apply through Morgan County Planning and Development Services at 48 West Young Street, P.O. Box 886, Morgan, UT 84050. Phone: 801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director), email: submit@morgancountyutah.gov (form submissions); jdrage@morgancountyutah.gov (Office Manager/Permit Tech). Office hours: Mon–Fri 8:00 AM – 5:00 PM (county offices; confirmed via Recorder, Treasurer, DMV, and Business License pages, all consistent county-wide hours). Official information: https://www.morgancountyutah.gov/planning-and-development.

Morgan County, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective since July 1, 2026, superseding the 2021 IBC; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update, remains in force; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective since July 1, 2026, superseding the 2021 IPC; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective since July 1, 2026, superseding the 2021 IMC; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective since July 1, 2026, superseding the 2021 IFGC; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective since July 1, 2026, superseding the 2021 IECC. The statute adopts a single IECC edition with no residential/commercial split.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective since July 1, 2026, superseding the 2021 IEBC; 2024 residential provisions of the International Swimming Pool and Spa Code (ISPSC) — Utah Code § 15A-2-103(1)(n); effective since July 1, 2026, superseding the 2021 ISPSC; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force, unchanged by the July 1, 2026 update; NOTE (updated 2026-07-16): The July 1, 2026 statewide code-edition transition (2024 IBC/IPC/IMC/IFGC/IECC/IEBC/ISPSC replacing 2021 editions) took effect 15 days ago per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; next version's editions confirmed identical). 2021 IRC and 2023 NEC are unchanged. Live-checked the Morgan County buildingpermits page today (2026-07-16) — it does not cite specific code edition years at all (references 'Chapter 11 of the IRC' and 'the IECC' generically), so no page-lag discrepancy to flag there. The International Fire Code is NOT adopted by § 15A-2-103 (it lives in Title 15A Chapter 5) and is not referenced elsewhere in this file.. Local amendments apply — see the Morgan County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morgan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.