EV Charger / EVSE Permit in Morgan County, Utah

Morgan County does not publish a distinct EV charger, EVSE, or electric vehicle charging station permit or fee. EV charger/EVSE installation is electrical work and falls under the county's general Electrical Permit, administered by Morgan County Planning and Development Services (covering both unincorporated county land and Morgan City). The Morgan County Building Permit Fees and Worksheet (Rev 9-2021) does not publish a separate EV-specific fee line item; the flat $100.00 Electrical Permit fee applies.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New dedicated electrical circuit and/or panel capacity to serve the charger, covered under the general Electrical Permit
  • Submission through Civic Review portal
  • Compliance with the 2023 National Electrical Code (NEC) per Utah Code § 15A-2-103(1)(g)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical PermitMorgan County Building Permit Fees and Worksheet (Rev 9-2021), flat fee line item under 'Building Permit Fees'. Same line item covers EV charger circuit installation; no distinct EV-specific fee is published.
$100.00
Re-inspection Fee (not ready)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
$70.00 (+1% State Fee)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Morgan County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    After wiring installed, before walls closed

  2. 2

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified

See the full Morgan County inspection guide — scheduling & re-inspection fees →

Tips

  • Morgan County has no separate EV-charger permit — EV charger (EVSE) installations are treated as standard electrical work under the flat $100 Electrical Permit.
  • Morgan County Planning and Development Services issues electrical permits for the entire county, including Morgan City — there is no separate city electrical inspector.
  • Call 801-845-4015 to confirm whether a specific EV charger installation qualifies for a reduced-scope Utility Permit ($100 + 1% State Fee) instead of a full building/electrical permit.

Frequently asked questions

Morgan County requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property; New dedicated electrical circuit and/or panel capacity to serve the charger, covered under the general Electrical Permit; Submission through Civic Review portal; Compliance with the 2023 National Electrical Code (NEC) per Utah Code § 15A-2-103(1)(g). If your project isn't listed, confirm with Morgan County Planning and Development Services at 801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director) before starting work.

In Morgan County, the published Electrical Permit is: $100.00. Additional published fees: Re-inspection Fee (not ready) — $70.00 (+1% State Fee). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Morgan County does not publish a plan-review timeline for this permit. Contact Morgan County Planning and Development Services at 801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director) for current turnaround.

You'll need: Civic Review Application. Depending on your project, Morgan County may also ask for: Electrical Plan / Single-Line Diagram. See the required-documents checklist on this page for details on each.

Morgan County requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Morgan County Planning and Development Services (801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director)).

Apply through Morgan County Planning and Development Services at 48 West Young Street, P.O. Box 886, Morgan, UT 84050. Phone: 801-845-4015 (general office/inspections); 801-845-4030 (Treasurer — deposit/fee payment); 801-845-4059 (Planning Director), email: submit@morgancountyutah.gov (form submissions); jdrage@morgancountyutah.gov (Office Manager/Permit Tech). Office hours: Mon–Fri 8:00 AM – 5:00 PM (county offices; confirmed via Recorder, Treasurer, DMV, and Business License pages, all consistent county-wide hours). Official information: https://www.morgancountyutah.gov/planning-and-development.

Morgan County, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective since July 1, 2026, superseding the 2021 IBC; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update, remains in force; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective since July 1, 2026, superseding the 2021 IPC; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective since July 1, 2026, superseding the 2021 IMC; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective since July 1, 2026, superseding the 2021 IFGC; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective since July 1, 2026, superseding the 2021 IECC. The statute adopts a single IECC edition with no residential/commercial split.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective since July 1, 2026, superseding the 2021 IEBC; 2024 residential provisions of the International Swimming Pool and Spa Code (ISPSC) — Utah Code § 15A-2-103(1)(n); effective since July 1, 2026, superseding the 2021 ISPSC; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force, unchanged by the July 1, 2026 update; NOTE (updated 2026-07-16): The July 1, 2026 statewide code-edition transition (2024 IBC/IPC/IMC/IFGC/IECC/IEBC/ISPSC replacing 2021 editions) took effect 15 days ago per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; next version's editions confirmed identical). 2021 IRC and 2023 NEC are unchanged. Live-checked the Morgan County buildingpermits page today (2026-07-16) — it does not cite specific code edition years at all (references 'Chapter 11 of the IRC' and 'the IECC' generically), so no page-lag discrepancy to flag there. The International Fire Code is NOT adopted by § 15A-2-103 (it lives in Title 15A Chapter 5) and is not referenced elsewhere in this file.. Local amendments apply — see the Morgan County overview page for the full list.

No. Morgan County does not publish a distinct EV-charger or EVSE permit or fee. EV charger installation is billed under the flat $100.00 Electrical Permit fee per the Morgan County Building Permit Fees and Worksheet (Rev 9-2021).

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morgan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.