How to schedule

Inspections are requested through the building department below.

Address
4580 South 2300 East, Holladay, UT 84117 (permanent address per the city's official Building Permit application form; the city's main website separately lists a temporary City Hall location at 3330 S 1300 E, Millcreek, UT 84106 during a facilities transition — verify current in-person location before visiting)
Phone
801-527-3890 (Building Division permit/fee inquiries); 801-272-9450 (City Hall main line)
Office hours
Weekdays 8:00 am - 5:00 pm; in-person counter consultation with the Building Official and a planner is by appointment only, Monday & Wednesday 3:30 pm - 5 pm, per the city's official Building Division page.
Website
Official site

Inspection sequence

Applies to: Residential Building Permit (New Dwelling / Remodel)

  1. 1

    Footing / Set Backs

    First inspection in Holladay's official Inspection Checklist, per the city's Building Permit application form.

  2. 2

    Foundation

    Per the official Inspection Checklist.

  3. 3

    Foundation Water Proofing

    Per the official Inspection Checklist.

  4. 4

    Subrough Plumbing / Electrical / Mechanical / Radiant

    Combined subrough trade inspection, per the official Inspection Checklist.

  5. 5

    Suspended Slabs (Garages / Porch Caps)

    Per the official Inspection Checklist.

  6. 6

    Shear Wall

    Requested separately from the 4-Way inspection, and before windows are installed, per the official Inspection Checklist.

  7. 7

    Exterior Weather Barrier

    Per the official Inspection Checklist.

  8. 8

    Roof Dry-In (Ice & Water Shield)

    Per the official Inspection Checklist.

  9. 9

    Mechanical Manual J & D

    Requested separately from the 4-Way inspection, per the official Inspection Checklist.

  10. 10

    4-Way

    Combined structural/trade inspection milestone, per the official Inspection Checklist.

  11. 11

    Power to Panel (Clearance)

    Per the official Inspection Checklist.

  12. 12

    Gas Line (Clearance)

    Per the official Inspection Checklist.

  13. 13

    Insulation

    Per the official Inspection Checklist.

  14. 14

    Final

    Final inspection, per the official Inspection Checklist. Inspection requests are made online at holladay.portal.iworq.net/HOLLADAY/permits/600 and must be submitted 24 hours in advance, prior to 4:00 pm; a contractor access code (assigned at permit issuance) is required to request inspections.

Applies to: Commercial Building Permit (New Commercial or Multi-Family Building)

  1. 1

    Footing / Set Backs

    Per the city's official Inspection Checklist (published for residential permits; the same Building Division administers commercial inspections, but no separate commercial-specific inspection sequence is published).

  2. 2

    Foundation

    Per the official Inspection Checklist.

  3. 3

    Subrough Plumbing / Electrical / Mechanical

    Combined subrough trade inspection, per the official Inspection Checklist.

  4. 4

    Final

    Final inspection. Inspection requests are made online at holladay.portal.iworq.net/HOLLADAY/permits/600 and must be submitted 24 hours in advance, prior to 4:00 pm; a contractor access code is required.

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Subrough Plumbing / Electrical / Mechanical

    Combined subrough trade inspection, per the city's official Inspection Checklist (published for residential permits; no separate commercial/TI-specific inspection sequence is published).

  2. 2

    Final

    Final inspection, requested online at holladay.portal.iworq.net/HOLLADAY/permits/600, 24 hours in advance prior to 4:00 pm; a contractor access code is required.

Applies to: Electrical, Mechanical & Plumbing Permit

  1. 1

    Subrough Plumbing / Electrical / Mechanical / Radiant

    Combined subrough trade inspection line, per the city's official Inspection Checklist. Requested online at holladay.portal.iworq.net/HOLLADAY/permits/600, 24 hours in advance prior to 4:00 pm.

  2. 2

    Final

    Final inspection, per the official Inspection Checklist.

Applies to: EV Charger / EVSE Permit

  1. 1

    Subrough Electrical

    Combined subrough trade inspection line, per the city's official Inspection Checklist. Requested online at holladay.portal.iworq.net/HOLLADAY/permits/600, 24 hours in advance prior to 4:00 pm.

  2. 2

    Final

    Final inspection, per the official Inspection Checklist.

Applies to: Solar PV / Solar Panel Installation Permit

  1. 1

    Power to Panel (Clearance)

    Electrical service/interconnection clearance inspection, per the city's official Inspection Checklist (published for residential permits; no separate solar-specific inspection sequence is published).

  2. 2

    Final

    Final inspection, requested online at holladay.portal.iworq.net/HOLLADAY/permits/600, 24 hours in advance prior to 4:00 pm; a contractor access code is required.

Final inspection only: Sign Permit

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holladay building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Holladay building permits

Get alerts for Holladay

We'll email you when Holladay's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.