Unincorporated San Juan County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated San Juan County, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
117 South Main Street, P.O. Box 9, Monticello, UT 84535
Phone
(435) 587-3829
Office hours
Monday–Friday 8:00 AM – 5:00 PM (San Juan County Administration Building, 117 South Main Street, Monticello — per San Juan County's official Contact Us / Administrative Office pages; the Building Department's own page does not separately publish office hours)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Foundation Inspection

    Made after trenches are excavated, forms erected, and required reinforcement steel is in place. Frost depth is checked for all exterior footings (monolithic slab/footings also need to reach frost depth). Also checks building location relative to setbacks while footers/foundation are formed but not poured.

  2. 2

    4-Way Inspection

    Framing (before building wrap or roofing underlayment), rough electrical, rough plumbing, rough mechanical — made after roof, framing, fire-blocking, and bracing are in place, and pipe chimneys/vents are complete, before any work is concealed.

  3. 3

    Septic System Inspection

    Final on-site inspection of house sewer, septic tank, and absorption field lines after completion but before the system is covered — usually performed by the San Juan County Health District Sanitarian, sometimes the Building Official. A separate Septic Permit is required.

  4. 4

    Final Inspection

    Made after finished grade and building is complete and ready for occupancy, but before occupied — includes porches, steps, decks, railings, sidewalks, and driveways. The completed building should not be occupied until a written Certificate of Occupancy is issued.

Applies to: Commercial Building Permit

  1. 1

    Foundation Inspection

    Made after trenches are excavated, forms erected, and required reinforcement steel is in place; frost depth checked for all exterior footings.

  2. 2

    4-Way Inspection

    Framing, rough electrical, rough plumbing, rough mechanical — made after roof, framing, fire-blocking, and bracing are in place, before any work is concealed.

  3. 3

    Final Inspection

    Made after finished grade and building is complete and ready for occupancy; the completed building should not be occupied until a written Certificate of Occupancy is issued.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough-In (Framing/Electrical/Plumbing/Mechanical)

    Scope-dependent rough-in inspection before any work is concealed.

  2. 2

    Final Inspection

    Made after the improved space is complete and ready for occupancy; a written Certificate of Occupancy is required before use.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated San Juan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated San Juan County building permits

Get alerts for Unincorporated San Juan County

We'll email you when Unincorporated San Juan County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.