Required for new residential construction, moving a trailer or pre-built home onto a lot, and any addition or remodeling in unincorporated San Juan County (which also covers the Town of Bluff, whose Planning & Zoning Commission issues a prerequisite Land Use Clearance before the county issues the actual building permit). Plan review for one- and two-family dwellings and townhomes must be completed within the 14-business-day statutory window required by Utah Code § 17-36-55(3)(a).

Verified 2026-07-08 · Source

When you need this permit

  • New residential construction, moving a trailer/pre-built home onto a lot, or any addition or remodeling
  • Complete set of plans drawn to scale submitted to the Building Department for review (per the county's Plan Requirements sheet)
  • Per Utah Code §§ 58-22-305 & 58-3a-304, only one- or two-family dwellings not exceeding two stories are exempt from requiring a licensed Professional Engineer or Architect to prepare the plans; the Building Official may require stamped plans when project scope/design warrants it
  • All commercial buildings must be designed, drawn, and stamped by a Utah Licensed Architect or Engineer
  • Structural Steel, Straw Bale, Adobe, or Rammed Earth construction methods require plans drawn by a Utah Licensed Architect or Engineer regardless of building type
  • Legal description and San Juan County property tax parcel number
  • Sewage system approved by the San Juan County Health Department (located at 735 S 200 W Suite 2, Blanding, or in the basement of the County Administration Building in Monticello)
  • Road Encroachment Permit from the San Juan County Road Department, if applicable
  • Property must be deeded in the applicant's name and recorded in the San Juan County Recorder's Office before permit issuance (or a notarized statement from the legal owner granting permission to build)
  • For property within the Town of Bluff: a Land Use Clearance (LUC) approved by the Bluff Planning & Zoning Commission must be obtained before the county building permit application

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review & Building Permit (combined)San Juan County Planning & Building Department official webpage (sanjuancountyut.gov/building), 'Fee Structure' section, retrieved live 2026-07-08.
1.75 × square footage of the structure (example given by the county: 2,000 sq ft = $3,500)
Inspection FeeSan Juan County Planning & Building Department official webpage (sanjuancountyut.gov/building), retrieved live 2026-07-08.
$65.00 per inspection + State mileage rate
Appeal for Time ExtensionSan Juan County Planning & Building Department official webpage (sanjuancountyut.gov/building).
$150.00
Work Done Without Permit (Investigation Fee)San Juan County Planning & Building Department official webpage (sanjuancountyut.gov/building); also referenced in the county's Building Permit Checklist as an investigation fee equal to the permit fee.
2× permit price, plus $150/week if continued beyond a 30-day notice

Review timeline

Plan reviewUnincorporated San Juan County’s published plan-review target
14–14 business days

How long did your Residential Building Permit permit actually take in Unincorporated San Juan County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation Inspection

    Made after trenches are excavated, forms erected, and required reinforcement steel is in place. Frost depth is checked for all exterior footings (monolithic slab/footings also need to reach frost depth). Also checks building location relative to setbacks while footers/foundation are formed but not poured.

  2. 2

    4-Way Inspection

    Framing (before building wrap or roofing underlayment), rough electrical, rough plumbing, rough mechanical — made after roof, framing, fire-blocking, and bracing are in place, and pipe chimneys/vents are complete, before any work is concealed.

  3. 3

    Septic System Inspection

    Final on-site inspection of house sewer, septic tank, and absorption field lines after completion but before the system is covered — usually performed by the San Juan County Health District Sanitarian, sometimes the Building Official. A separate Septic Permit is required.

  4. 4

    Final Inspection

    Made after finished grade and building is complete and ready for occupancy, but before occupied — includes porches, steps, decks, railings, sidewalks, and driveways. The completed building should not be occupied until a written Certificate of Occupancy is issued.

See the full Unincorporated San Juan County inspection guide — scheduling & re-inspection fees →

Tips

  • Every request for inspection must be filed at least 48 hours in advance, by phone (435-587-3221) or email (building@sanjuancountymail.org per the county's Building Permit Checklist; the department's general contact email is permits@sanjuancountyut.gov).
  • San Juan County requires the building lot to be deeded in the applicant's name and recorded with the San Juan County Recorder's Office (or a notarized owner-permission statement) before the county will issue a building permit.
  • If your property is within the Town of Bluff, you must first obtain a Land Use Clearance from the Bluff Planning & Zoning Commission — the LUC is valid for one year, and if a building permit is not acquired within that year, a new LUC is required.
  • Investigation fees equal to the permit fee are charged if construction work begins before a permit is obtained, plus $150/week if the violation continues beyond a 30-day notice, per the county's official Building Department webpage.
  • Owner-builders acting as their own contractor on a personal, non-commercial single-family residence are permitted under the Utah Construction Trades Licensing Act, but unlicensed-contractor violations can be a class A misdemeanor plus an administrative fine up to $2,000/day; all commercial project work must be performed by licensed contractors. Owner-builderContractor
  • Rooftop or ground-mounted solar PV installations require this same Residential Building Permit — San Juan County's Building Department webpage (sanjuancountyut.gov/building), live-checked 2026-07-19, publishes no distinct solar-specific fee tier or permit type, so solar installs are billed under the same combined Plan Review & Building Permit formula (1.75× square footage); confirm with the department at (435) 587-3829 how valuation is calculated for a non-structure PV system.
  • EV charger / EVSE installation would fall under this same Residential Building Permit — San Juan County's Building Department webpage (re-checked 2026-07-20) publishes no distinct EV/EVSE fee tier or permit type (consistent with its treatment of solar, above); a standalone EV charging circuit would be expected to be billed under the county's $65.00-per-inspection Inspection Fee rather than the combined Plan Review & Building Permit valuation formula used for new structures.

Frequently asked questions

Unincorporated San Juan County requires a residential building permit for: New residential construction, moving a trailer/pre-built home onto a lot, or any addition or remodeling; Complete set of plans drawn to scale submitted to the Building Department for review (per the county's Plan Requirements sheet); Per Utah Code §§ 58-22-305 & 58-3a-304, only one- or two-family dwellings not exceeding two stories are exempt from requiring a licensed Professional Engineer or Architect to prepare the plans; the Building Official may require stamped plans when project scope/design warrants it; All commercial buildings must be designed, drawn, and stamped by a Utah Licensed Architect or Engineer; Structural Steel, Straw Bale, Adobe, or Rammed Earth construction methods require plans drawn by a Utah Licensed Architect or Engineer regardless of building type; Legal description and San Juan County property tax parcel number; Sewage system approved by the San Juan County Health Department (located at 735 S 200 W Suite 2, Blanding, or in the basement of the County Administration Building in Monticello); Road Encroachment Permit from the San Juan County Road Department, if applicable; Property must be deeded in the applicant's name and recorded in the San Juan County Recorder's Office before permit issuance (or a notarized statement from the legal owner granting permission to build); For property within the Town of Bluff: a Land Use Clearance (LUC) approved by the Bluff Planning & Zoning Commission must be obtained before the county building permit application. If your project isn't listed, confirm with San Juan County Planning & Building Department at (435) 587-3829 before starting work.

San Juan County's combined Plan Review & Building Permit fee is 1.75 times the structure's square footage (the county's own example: 2,000 sq ft = $3,500), plus a $65.00 inspection fee per inspection plus the state mileage rate, per the county's official Building Department webpage.

San Juan County's Building Department does not publish its own distinct SLA figure. Utah Code § 17-36-55(3)(a) requires a county to complete plan review of a one- or two-family dwelling or townhome construction project within 14 business days after the applicant submits a complete building permit application.

You'll need: Building Permit Application; Complete Set of Plans (per Plan Requirements sheet); Legal Description and County Property Tax Parcel Number; Septic/Sewage System Approval; Proof of Property Ownership / Notarized Owner Permission. Depending on your project, Unincorporated San Juan County may also ask for: Road Encroachment Permit; Town of Bluff Land Use Clearance (LUC). See the required-documents checklist on this page for details on each.

Unincorporated San Juan County requires 4 inspection(s) for a residential building permit, in order: Foundation Inspection, 4-Way Inspection, Septic System Inspection, Final Inspection. Schedule each through San Juan County Planning & Building Department ((435) 587-3829).

Apply through San Juan County Planning & Building Department at 117 South Main Street, P.O. Box 9, Monticello, UT 84535. Phone: (435) 587-3829, email: permits@sanjuancountyut.gov. Office hours: Monday–Friday 8:00 AM – 5:00 PM (San Juan County Administration Building, 117 South Main Street, Monticello — per San Juan County's official Contact Us / Administrative Office pages; the Building Department's own page does not separately publish office hours). Official information: https://sanjuancountyut.gov/building.

Unincorporated San Juan County, Utah has adopted: State of Utah construction codes adopted by reference — San Juan County's official Building Code Information page states verbatim: 'San Juan County has adopted the State of Utah codes as established in Title 15A, Chapters 1-5 of the Utah Code Annotated, as amended.' The county page does not enumerate individual code editions (IBC/IRC/IPC/IMC/IFGC/NEC/IECC) by year, so the current statutory statewide editions are cited directly below.; 2024 International Building Code (IBC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; 2021 International Residential Code (IRC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026 (edition unchanged from prior cycle); 2024 International Plumbing Code (IPC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; 2024 International Mechanical Code (IMC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; 2024 International Energy Conservation Code (IECC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; 2023 National Electrical Code (NEC) — statewide per Utah Code § 15A-2-103, effective 07/01/2026; Residential provisions of the 2024 International Swimming Pool and Spa Code — statewide per Utah Code § 15A-2-103(1)(n), effective 07/01/2026. Local amendments apply — see the Unincorporated San Juan County overview page for the full list.

Blanding operates its own independent building department (its own Building Official, Taylor Francom, using the CityInspect online permitting platform) — Blanding is NOT covered by this county file. The Town of Bluff, however, requires applicants to first obtain a Land Use Clearance from the Bluff Planning & Zoning Commission, after which San Juan County's Planning & Building Department issues the actual building permit — so Bluff IS effectively covered by this county file for the building-permit-issuance step, even though Bluff retains its own local land-use/zoning sign-off.

Compare residential building permit fees across Utah

Look up this fee in a different city →

Embed this data card →

Now live

Build your Unincorporated San Juan County project checklist

Describe your project once and get every permit, document, and fee it triggers in Unincorporated San Juan County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →