Solar PV (Photovoltaic) Permit — Unincorporated San Juan County, Utah · Requirements sheet
Verified 2026-07-21 · Source: https://sanjuancountyut.gov/building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV (Photovoltaic) Permit in Unincorporated San Juan County, Utah
San Juan County does not publish a distinct solar, solar PV, or photovoltaic installation permit or fee. The county's official Building Department webpage (sanjuancountyut.gov/building, live-checked 2026-07-21) and its Building Permit Checklist / Plan Requirements PDF do not mention solar, PV, or photovoltaic anywhere; the county's separate Planning & Zoning Fee Schedule (sjcpcfeesched16.pdf, which covers only planning/zoning services, not building-trade permits) likewise contains no solar line item. A rooftop or ground-mounted solar PV installation is therefore processed under the same general Residential or Commercial Building Permit administered by the San Juan County Planning & Building Department, with its Rough Electrical inspection (part of the required 4-Way Inspection) covering the PV system's electrical work under the 2023 National Electrical Code (NEC Article 690, Solar Photovoltaic Systems, adopted statewide by Utah Code § 15A-2-103(1)(g)).
Verified 2026-07-21 · Source
When you need this permit
- Installation of a rooftop-mounted or ground-mounted solar photovoltaic (PV) system at a residential or commercial property
- Electrical Layout plan showing the new PV circuit, inverter/disconnect location, service size, and panel size/location — part of the standard Plan Requirements for a San Juan County Building Permit
- Structural sign-off for roof-mounted arrays where the Building Official determines added roof loading warrants review (per the general plan-review authority described in the county's Building Permit Checklist; no PV-specific structural threshold is published)
- Rough Electrical inspection as part of the county's required 4-Way Inspection (Framing, Rough Electrical, Rough Plumbing, Rough Mechanical)
- Compliance with the 2023 National Electrical Code (NEC), including Article 690 (Solar Photovoltaic Systems), as adopted statewide by Utah Code § 15A-2-103(1)(g)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Part of the county's required 4-Way Inspection (Framing, Rough Electrical, Rough Plumbing, Rough Mechanical), performed after PV wiring/conduit is in place but before it is concealed.
See the full Unincorporated San Juan County inspection guide — scheduling & re-inspection fees →
Tips
- San Juan County has no separate solar, solar PV, or photovoltaic permit type — a solar installation is covered under the general Residential or Commercial Building Permit and its Rough Electrical inspection, the same treatment the county gives EV charger installations.
- The county's published 1.75-per-square-foot fee formula is designed for new construction; for a standalone rooftop or ground-mounted PV retrofit with no added square footage, confirm the applicable fee directly with the Building Department at (435) 587-3829 or permits@sanjuancountyut.gov.
- PV system electrical work must comply with NEC Article 690 (Solar Photovoltaic Systems) under the 2023 National Electrical Code, adopted statewide effective 07/01/2026 per Utah Code § 15A-2-103(1)(g).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated San Juan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated San Juan County
Solar PV (Photovoltaic) Permit in other cities
Compare solar pv (photovoltaic) permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated San Juan County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated San Juan County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →