American Fork building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in American Fork, Utah.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
275 East 200 North, American Fork, UT 84003
Phone
801-763-3060
Email
Office hours
Mon–Thu 7:00 AM – 6:00 PM (Building Division checklists list a separate plan-submittal contact line 801-763-3065); closed Fridays, per American Fork City Building Inspection Policies and Procedures (rev. 7/22/2024).

Published scheduling rules

  • Inspections must be requested online through the City Inspect portal at least one working day in advance — there are no same-day inspections. (Residential Building Permit)
  • A $125 cancellation fee applies if a scheduled inspection is cancelled within 3 days of the appointment; a $175 re-inspection fee applies if the job is not ready at the scheduled time. (Residential Building Permit)
  • Solar inspections are scheduled in narrower windows (10:00–11:30 AM or 3:00–4:30 PM) than standard building inspections. (Solar PV Permit)
  • Inspections must be requested online via the City Inspect portal at least one working day in advance; no same-day inspections, and inspections cannot be arranged in the field with inspectors on-site. (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing/Foundation

    Before concrete pour, per standard IBC inspection sequence enforced by American Fork Building Division. Concrete inspections are given a one-hour scheduling window per Building Inspection Policies and Procedures (rev. 7/22/2024); no inspections take place between 12:00-1:00 PM.

  2. 2

    Framing and MEP Rough-In

    Structural framing, wall sections, and electrical/mechanical/plumbing rough-in verified per the Commercial Plans Minimum Plan Requirements checklist (floor plan including electrical, mechanical, and plumbing; wall sections; roof or truss detail).

  3. 3

    Energy Compliance (ASHRAE 90.1 / ComCheck)

    ASHRAE 90.1 standards compliance verified via ComCheck (envelope, electrical, and mechanical) per American Fork's Commercial Plans checklist; lot, subdivision, and/or plan number must be on the submittal.

  4. 4

    Final / Certificate of Occupancy

    All work complete; Occupancy Fee ($150.00 commercial) applies per American Fork City Adopted Fee Schedule.

Applies to: Residential Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour, per standard IRC/IBC inspection sequence enforced by American Fork Building Division.

  2. 2

    Framing

    After framing, sheathing, and roof installed; includes MEP rough-in per American Fork inspection scheduling rules (City Inspect portal, 1 working day advance notice required).

  3. 3

    Insulation

    After insulation installed, before drywall.

  4. 4

    Final / Certificate of Occupancy

    All work complete; Occupancy Fee ($50 residential) applies per American Fork City Adopted Fee Schedule.

Applies to: Change of Use Permit (Zoning Confirmation Letter / Business License Change of Location)

  1. 1

    Zoning Clearance (Planning Department sign-off)

    Required signature on the Commercial Business License Application before the license is issued, confirming the new use/location complies with zoning, per the Commercial Business License Application (Rev. 9/15).

  2. 2

    Fire Inspection

    Required signature from the American Fork Fire Department (801-763-3045) on the Commercial Business License Application before the license is issued.

  3. 3

    Building Inspection

    Required signature from the American Fork Building Department (801-763-3060) on the Commercial Business License Application before the license is issued.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing/Structural

    Wall sections and any structural modifications verified per submitted plans before close-in, where the tenant improvement scope includes structural work.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against the floor plan submitted for the tenant space.

  3. 3

    Final / Certificate of Occupancy

    All work complete; Occupancy Fee ($150.00 commercial) applies if occupancy classification changes, per American Fork City Adopted Fee Schedule.

Applies to: Residential Addition / Remodel / Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window openings verified per American Fork checklist requirements.

  2. 2

    MEP Rough-In

    Electrical and plumbing rough-in per basement/remodel layout submitted.

  3. 3

    Final

    Smoke detectors and carbon monoxide detectors upgraded to current IRC requirements throughout the home, not just the finished area, per American Fork Basement Finish/Remodel checklist.

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and box placement verified before walls closed.

  2. 2

    Final

    Panel/meter verification and device testing; scheduled through the City Inspect portal at least one working day in advance.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed.

  2. 2

    Mechanical Final

    American Fork's Building Inspection Policies and Procedures (rev. 7/22/2024) specify mechanical finals are performed in dedicated windows: 10:00 AM–11:30 AM for AM inspections and 3:00 PM–4:30 PM for PM inspections (narrower than the general 7:30 AM–11:30 AM / 1 PM–4:30 PM windows).

Applies to: Plumbing Permit

  1. 1

    Underground/Rough-In

    Before walls closed or slab poured — pipe slope, materials, cleanouts verified.

  2. 2

    Final

    Fixtures connected, water heater venting/strapping verified as part of the building permit final inspection.

Applies to: Roofing Permit

  1. 1

    Deck/Substrate

    After tear-off, before underlayment — sheathing condition verified.

  2. 2

    Final

    Completed roof inspection scheduled through the City Inspect portal at least one working day in advance.

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing.

  2. 2

    Solar Final

    American Fork's Building Inspection Policies and Procedures (rev. 7/22/2024) specify solar inspections are performed in dedicated windows: 10:00 AM–11:30 AM for AM inspections and 3:00 PM–4:30 PM for PM inspections.

Re-inspection fees

Residential Building PermitReinspection Fee · American Fork City Adopted Fee Schedule (effective 7/1/2025), p.10: 'Reinspection Fee per unit — $175.00.' Confirmed consistent with Building Inspection Policies and Procedures (rev. 7/22/2024): 'A $175 re-inspection fee may be assessed for any inspection that was scheduled but not ready at the appointed time.'
$175.00 per unit
Commercial Building PermitReinspection Fee (Commercial) · American Fork City Adopted Fee Schedule, Effective July 1, 2025, p.11, Commercial Building Division Fees: 'Reinspection Fee per unit — $175.00.'
$175.00 per unit
Commercial Tenant Improvement / Tenant Finish PermitReinspection Fee (Commercial) · American Fork City Adopted Fee Schedule, Effective July 1, 2025, p.11, Commercial Building Division Fees: 'Reinspection Fee per unit — $175.00.'
$175.00 per unit

American Fork building permits

Get alerts for American Fork

We'll email you when American Fork's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.