American Fork building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in American Fork, Utah.
Verified 2026-07-04 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 275 East 200 North, American Fork, UT 84003
- Phone
- 801-763-3060
- Office hours
- Mon–Thu 7:00 AM – 6:00 PM (Building Division checklists list a separate plan-submittal contact line 801-763-3065); closed Fridays, per American Fork City Building Inspection Policies and Procedures (rev. 7/22/2024).
- Website
- Official site
Published scheduling rules
- Inspections must be requested online through the City Inspect portal at least one working day in advance — there are no same-day inspections. (Residential Building Permit)
- A $125 cancellation fee applies if a scheduled inspection is cancelled within 3 days of the appointment; a $175 re-inspection fee applies if the job is not ready at the scheduled time. (Residential Building Permit)
- Solar inspections are scheduled in narrower windows (10:00–11:30 AM or 3:00–4:30 PM) than standard building inspections. (Solar PV Permit)
- Inspections must be requested online via the City Inspect portal at least one working day in advance; no same-day inspections, and inspections cannot be arranged in the field with inspectors on-site. (General)
Inspection sequence
Applies to: Commercial Building Permit
- 1
Footing/Foundation
Before concrete pour, per standard IBC inspection sequence enforced by American Fork Building Division. Concrete inspections are given a one-hour scheduling window per Building Inspection Policies and Procedures (rev. 7/22/2024); no inspections take place between 12:00-1:00 PM.
- 2
Framing and MEP Rough-In
Structural framing, wall sections, and electrical/mechanical/plumbing rough-in verified per the Commercial Plans Minimum Plan Requirements checklist (floor plan including electrical, mechanical, and plumbing; wall sections; roof or truss detail).
- 3
Energy Compliance (ASHRAE 90.1 / ComCheck)
ASHRAE 90.1 standards compliance verified via ComCheck (envelope, electrical, and mechanical) per American Fork's Commercial Plans checklist; lot, subdivision, and/or plan number must be on the submittal.
- 4
Final / Certificate of Occupancy
All work complete; Occupancy Fee ($150.00 commercial) applies per American Fork City Adopted Fee Schedule.
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour, per standard IRC/IBC inspection sequence enforced by American Fork Building Division.
- 2
Framing
After framing, sheathing, and roof installed; includes MEP rough-in per American Fork inspection scheduling rules (City Inspect portal, 1 working day advance notice required).
- 3
Insulation
After insulation installed, before drywall.
- 4
Final / Certificate of Occupancy
All work complete; Occupancy Fee ($50 residential) applies per American Fork City Adopted Fee Schedule.
Applies to: Change of Use Permit (Zoning Confirmation Letter / Business License Change of Location)
- 1
Zoning Clearance (Planning Department sign-off)
Required signature on the Commercial Business License Application before the license is issued, confirming the new use/location complies with zoning, per the Commercial Business License Application (Rev. 9/15).
- 2
Fire Inspection
Required signature from the American Fork Fire Department (801-763-3045) on the Commercial Business License Application before the license is issued.
- 3
Building Inspection
Required signature from the American Fork Building Department (801-763-3060) on the Commercial Business License Application before the license is issued.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing/Structural
Wall sections and any structural modifications verified per submitted plans before close-in, where the tenant improvement scope includes structural work.
- 2
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against the floor plan submitted for the tenant space.
- 3
Final / Certificate of Occupancy
All work complete; Occupancy Fee ($150.00 commercial) applies if occupancy classification changes, per American Fork City Adopted Fee Schedule.
Applies to: Residential Addition / Remodel / Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window openings verified per American Fork checklist requirements.
- 2
MEP Rough-In
Electrical and plumbing rough-in per basement/remodel layout submitted.
- 3
Final
Smoke detectors and carbon monoxide detectors upgraded to current IRC requirements throughout the home, not just the finished area, per American Fork Basement Finish/Remodel checklist.
Applies to: Electrical Permit
- 1
Rough-In
Wiring and box placement verified before walls closed.
- 2
Final
Panel/meter verification and device testing; scheduled through the City Inspect portal at least one working day in advance.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed.
- 2
Mechanical Final
American Fork's Building Inspection Policies and Procedures (rev. 7/22/2024) specify mechanical finals are performed in dedicated windows: 10:00 AM–11:30 AM for AM inspections and 3:00 PM–4:30 PM for PM inspections (narrower than the general 7:30 AM–11:30 AM / 1 PM–4:30 PM windows).
Applies to: Plumbing Permit
- 1
Underground/Rough-In
Before walls closed or slab poured — pipe slope, materials, cleanouts verified.
- 2
Final
Fixtures connected, water heater venting/strapping verified as part of the building permit final inspection.
Applies to: Roofing Permit
- 1
Deck/Substrate
After tear-off, before underlayment — sheathing condition verified.
- 2
Final
Completed roof inspection scheduled through the City Inspect portal at least one working day in advance.
Applies to: Solar PV Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing.
- 2
Solar Final
American Fork's Building Inspection Policies and Procedures (rev. 7/22/2024) specify solar inspections are performed in dedicated windows: 10:00 AM–11:30 AM for AM inspections and 3:00 PM–4:30 PM for PM inspections.
Final inspection only: Automatic Fire Protection (Fire Sprinkler) System Permit, Fire Alarm System Permit, EV Charger / EVSE Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the American Fork building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
American Fork building permits
Get alerts for American Fork
We'll email you when American Fork's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.