Fire Alarm System Permit in American Fork, Utah

Required in American Fork City for installation of a new fire alarm system, remodel of an existing system, or extension of alarm coverage to additional floors, plan-reviewed by the Fire Prevention Division. American Fork's Fiscal Year 2025-2026 Fee Schedule prices fire alarm system plan review separately from sprinkler (Automatic Fire Protection System) plan review, with distinct fees for new systems, remodels, and additional floors; these fees are for in-house plan reviews only.

Verified 2026-07-20 · Source

When you need this permit

  • Fire alarm system plans submitted to the Fire Prevention Division for plan review before installation, remodel, or extension to additional floors
  • Compliance with NFPA standards, the Life Safety Code, and the State Adopted International Fire and Building Code with amendments, per American Fork's Fire Prevention Division page
  • Final construction inspection and fire system testing before a certificate of fire clearance is issued

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire Alarm Systems Plan Review — New System (in-house)American Fork City Fiscal Year 2025-2026 Fee Schedule (effective July 1, 2025), Fire Department Fees section, line item 146: 'New System — $100.00' (Fire Alarm Systems, fees are for in-house plan reviews only).
$100.00
Fire Alarm Systems Plan Review — Remodel (in-house)American Fork City Fiscal Year 2025-2026 Fee Schedule, line item 147: 'Remodel — $50.00.'
$50.00
Fire Alarm Systems Plan Review — Additional Floors (in-house)American Fork City Fiscal Year 2025-2026 Fee Schedule, line item 148: 'Additional Floors — $50.00.'
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Alarm System Permit permit actually take in American Fork?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Construction Inspection / Fire System Test

    Once plans are reviewed, the construction site is inspected and fire systems are tested and approved before a certificate of fire clearance is issued, per American Fork's Fire Prevention Division page.

See the full American Fork inspection guide — scheduling & re-inspection fees →

Tips

  • American Fork's fire alarm plan review fees ($100 new system / $50 remodel / $50 additional floors) apply to in-house plan reviews only — confirm with the Fire Marshal's office whether third-party review applies to your project and what that would cost.
  • A separate Fire Alarm Panel Inspection fee ($35.00, submitted to a 3rd party) applies to periodic/ongoing testing after initial installation, per the Fee Schedule's Fire Inspections/Enforcement section — this is a recurring inspection fee, not part of the initial installation permit.
  • False fire alarm response fees apply per calendar year for both commercial and residential occupancies once the first two free responses are exceeded, per the Fee Schedule's Fire Operations section.

Frequently asked questions

American Fork requires a fire alarm system permit for: Fire alarm system plans submitted to the Fire Prevention Division for plan review before installation, remodel, or extension to additional floors; Compliance with NFPA standards, the Life Safety Code, and the State Adopted International Fire and Building Code with amendments, per American Fork's Fire Prevention Division page; Final construction inspection and fire system testing before a certificate of fire clearance is issued. If your project isn't listed, confirm with American Fork City Building Department at 801-763-3060 before starting work.

Per American Fork City's Fiscal Year 2025-2026 Fee Schedule (effective July 1, 2025), in-house fire alarm system plan review costs $100.00 for a new system, $50.00 for a remodel, or $50.00 for extending an existing system to additional floors.

American Fork does not publish a plan-review timeline for this permit. Contact American Fork City Building Department at 801-763-3060 for current turnaround.

You'll need: Fire Alarm System Plans. See the required-documents checklist on this page for details on each.

American Fork requires 1 inspection(s) for a fire alarm system permit, in order: Final Construction Inspection / Fire System Test. Schedule each through American Fork City Building Department (801-763-3060).

Apply through American Fork City Building Department at 275 East 200 North, American Fork, UT 84003. Phone: 801-763-3060. Office hours: Mon–Thu 7:00 AM – 6:00 PM (Building Division checklists list a separate plan-submittal contact line 801-763-3065); closed Fridays, per American Fork City Building Inspection Policies and Procedures (rev. 7/22/2024).. Official information: https://www.americanfork.gov/173/Building-Department.

American Fork, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition American Fork's official Building Department page still stated as of live-check 2026-07-16: 'the American Fork Building Department uses the 2021 IBC and IRC Code as adopted by the State of Utah,' effective July 1, 2023, per americanfork.gov/173/Building-Department. The 2021 edition applied under the prior version of § 15A-2-103; American Fork's page has not been updated to reflect the 7/1/2026 transition.; 2021 International Residential Code (IRC) — REMAINS CURRENT, Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment; americanfork.gov/173/Building-Department's statement is correct on this point (no update needed for IRC).; 2020 National Electrical Code (NEC) as published by American Fork's own Solar Minimum Plan Requirements checklist — STALE even under the PRIOR version of the statute: the checklist (americanfork.gov/DocumentCenter/View/13852/Solar-Checklist) explicitly cites '2020 NEC 690.4(C)' and multiple other 2020 NEC section references (690.7, 690.12, 706.15(C), 230.71, 230.62(C)), fetched 2026-07-04 and unconfirmed changed since. The statewide-governing NEC edition is, and remains, the 2023 NEC per Utah Code § 15A-2-103(1)(g) — unchanged by the 7/1/2026 amendment, but American Fork's own document has not been updated to reference it, a pre-existing discrepancy independent of the 2026 code-cycle transition (the same kind of stale-document issue documented for Provo's Building FAQ in provo.json). Reported here as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); required per American Fork City Residential Plans Minimum Plan Requirements checklist (americanfork.gov/DocumentCenter/View/58/Residential-Plan-Checklist): 'Utah Energy Conservation Code requirements. Must have lot, subdivision, and plan number on the Res check submittal.' The checklist itself does not state a specific edition year — the 2024 edition is added here per statute.; Utah statewide baseline construction code editions per Utah Code § 15A-2-103, effective 7/1/2026 (superseded 1/1/2027): 2024 IPC (§(1)(d)), 2024 IMC (§(1)(e)), 2024 IFGC (§(1)(f)), 2024 IEBC (§(1)(i)), and the residential provisions of the 2024 ISPSC (§(1)(n)) — none separately itemized on americanfork.gov/173/Building-Department or in American Fork's own checklists; added here per statute since American Fork's own materials omit them.; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. American Fork's Building Department page (americanfork.gov/173/Building-Department) was live-checked 2026-07-16 and IS STILL LAGGING: it verbatim states 'Beginning July 1, 2023, The American Fork Building Department will be using the 2021 IBC and IRC Code as adopted by the State of Utah' with no update reflecting the 2024 IBC. The IRC portion of that statement remains accurate (2021 IRC is unchanged). No newer American Fork-specific code-adoption notice was found. The Utah Code § 15A-2-103 citation has been added to the sources array below, pointing to the current in-force version link.. Local amendments apply — see the American Fork overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the American Fork building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.