Skip to main content
PermitBase

Fence Permit in Spanish Fork, Utah

Required for fence installation in Spanish Fork. Fences are explicitly listed as permit-required on the city's permits page. Spanish Fork has a specific fence permit application in CitizenServe. Fence regulations are in Municipal Code § 15.4.16.150.

Verified 2026-07-01 · Source

When you need this permit

  • Any new fence construction
  • Replacement of existing fence (confirm with building department whether like-for-like replacement requires a permit)
  • Fences in any residential zone

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fence PermitGrounded, verbatim from Spanish Fork Municipal Code § 15.4.16.150 Fencing and Clear Vision Area: 'A Building Permit is required for all fences that are taller than three (3) feet. No fee is charged for Fence Permits unless the Permit is required by the Building Code.' Cited: spanishfork.municipalcodeonline.com § 15.4.16.150, retrieved 2026-07-01 (current through Ord. 02-2026, 4/7/2026).
No fee, unless the fence permit is required under the Building Code (in which case the standard valuation-based Building Permit fee applies)
Building Re-inspectionSpanish Fork Building Fees page, FY2026 (effective 07/01/2025–06/30/2026).
$132 flat fee per trip

Review timeline

Plan reviewTypical estimate — confirm current times with the Spanish Fork building department
~3–7 business days

How long did your Fence Permit permit actually take in Spanish Fork?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verify fence matches approved plan and meets height and setback requirements per Spanish Fork Municipal Code § 15.4.16.150.

See the full Spanish Fork inspection guide — scheduling & re-inspection fees →

Tips

  • Fences are explicitly listed as requiring a permit on Spanish Fork's permits page.
  • A Building Permit is required for all fences over 3 feet tall — but per Municipal Code § 15.4.16.150, NO FEE is charged for the fence permit unless the Building Code otherwise requires one.
  • Fence height and setback regulations are in Spanish Fork Municipal Code § 15.4.16.150 — see spanishfork.municipalcodeonline.com.
  • Additional fence/awning requirements are at Municipal Code § 15.3.24.090 F.
  • Call 811 before digging fence post holes.

Frequently asked questions

Yes, for fences taller than 3 feet. Spanish Fork's permits page lists fences as requiring a permit with its own CitizenServe application. Apply at citizenserve.com/spanishforkcity or call (801) 804-4540.

No fee is charged for a fence permit unless the permit is required by the Building Code, per Spanish Fork Municipal Code § 15.4.16.150. If the Building Code applies, the standard valuation-based building permit fee is charged instead.

Plan review for a fence permit in Spanish Fork typically runs 3–7 business days. This is an estimate, not a published figure — confirm current review times with Spanish Fork City Building Department at (801) 804-4540.

You'll need: Fence Permit Application (CitizenServe); Site Plan. See the required-documents checklist on this page for details on each.

Spanish Fork requires 1 inspection(s) for a fence permit, in order: Final. Schedule each through Spanish Fork City Building Department ((801) 804-4540).

Apply through Spanish Fork City Building Department at 40 S Main St, Room 120, Spanish Fork, UT 84660. Phone: (801) 804-4540, email: twilliams@spanishfork.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.spanishfork.gov/departments/community_development/building/index.php.

Spanish Fork, Utah has adopted: 2024 International Building Code (IBC) with Utah Amendments — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026 (confirmed by direct fetch of the live statute 2026-07-16). Supersedes the 2021 IBC, which governed through 6/30/2026. NOTE (2026-07-16 city-page lag): Spanish Fork's own Design Criteria page (spanishfork.gov/departments/community_development/building/design_criteria.php), live-checked via browser 2026-07-16, still lists 'IBC 2021 Int'l Bldg Code w/UT Amendments' verbatim — the city's page has NOT been updated to reflect the 7/1/2026 statewide flip. The statute controls regardless of the city page's lag.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle. Matches Spanish Fork's Design Criteria page (live-checked 2026-07-16: 'IRC 2021 Int'l Residential Code').; Appendix AQ of the 2021 International Residential Code — Utah Code § 15A-2-103(1)(c) (confirmed by direct fetch of the live statute 2026-07-16; not independently listed on Spanish Fork's Design Criteria page).; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026. NOTE (2026-07-16 city-page lag): Spanish Fork's Design Criteria page still lists 'IPC 2021 Plumbing' — the statute controls.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026. NOTE (2026-07-16 city-page lag): Spanish Fork's Design Criteria page still lists 'IMC 2021 Mechanical' — the statute controls.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026. NOTE (2026-07-16 city-page lag): Spanish Fork's Design Criteria page still lists 'IFGC 2021 Fuel Gas Code' — the statute controls.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle. Matches Spanish Fork's Design Criteria page (live-checked 2026-07-16: 'NEC 2023 Commercial Electrical').; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). ONE statewide edition — no residential/commercial split. Supersedes the 2021 IECC, which governed through 6/30/2026. NOTE (2026-07-16 city-page lag): Spanish Fork's Design Criteria page still lists 'IECC 2021 Energy' — the statute controls.; 2021 International Fire Code (IFC) — local citation only, per Spanish Fork's Design Criteria page (live-checked 2026-07-16: 'IFC 2021 National Fire'). CORRECTION (2026-07-16): a prior version of this file cited Utah Code § 15A-2-103(1)(c) for this entry — that is WRONG; §15A-2-103 does NOT adopt the IFC at all (its statute text has no IFC subsection; subsection (c) actually adopts Appendix AQ of the 2021 IRC, listed separately above). The IFC edition is left unchanged here since §15A-2-103 provides no statewide IFC edition to supersede it.; ICC/ANSI A117.1-2009 (ADA/Accessibility) — Spanish Fork Design Criteria page (live-checked 2026-07-16, unchanged).; NOTE (2026-07-16 corpus-staleness fix): This file previously stated the 2021 editions of IBC/IPC/IMC/IFGC/IECC as current with only a forward-looking mention of the 7/1/2026 flip; that effective date has now passed. A live browser fetch of Spanish Fork's Design Criteria page on 2026-07-16 confirms the city itself has NOT updated its page — it still displays 2021 for IBC/IECC/IFC/IMC/IPC/IFGC verbatim (NEC correctly remains 2023). Because Utah is a statewide-mandatory-code state under Utah Code § 15A-2-103 (per Utah Code § 15A-1-204, binding the state and every political subdivision), the statute controls regardless of the city page's lag, so the entries above state the 2024 editions as current for IBC/IPC/IMC/IFGC/IECC. IRC (2021) and NEC (2023) are correctly unchanged on both the statute and the (otherwise stale) city page.. Local amendments apply — see the Spanish Fork overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Spanish Fork building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.