Unincorporated Wayne County building inspections

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Wayne County, Utah.

Reviewed 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
18 South Main St, PO Box 189, Loa, UT 84747
Phone
(435) 836-1302
Email
Office hours
Monday–Friday 8:00 AM – 5:00 PM (closed 12:30–1:00 PM for lunch); Wayne County Courthouse hours per County Offices page

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Initial (before work begins)

    Required initial inspection before construction work begins, per the county's Inspection Record form

  2. 2

    Footings

    Before concrete pour — footing excavation, rebar

  3. 3

    Foundation

    After forms are in place, but before concrete is poured

  4. 4

    Underground Plumbing

    Underground/under-slab plumbing before it is covered

  5. 5

    Rough Framing

    When finished and before covering

  6. 6

    Rough Plumbing

    After concealed piping is in place, but before covering

  7. 7

    Rough Electrical

    After electrical is in place, but before covering

  8. 8

    Rough Mechanical

    Ductwork and mechanical rough-in before covering

  9. 9

    Insulation

    After insulation is installed, before drywall

  10. 10

    Drywall

    Drywall inspection before finishing

  11. 11

    Building Final

    Final building inspection — required before occupancy; occupancy of the structure is prohibited until after final inspection

  12. 12

    Plumbing Final

    Final plumbing inspection

  13. 13

    Electrical Final

    Final electrical inspection

Applies to: Commercial Building Permit

  1. 1

    Initial (before work begins)

    Required initial inspection before construction work begins, per the county's Inspection Record form.

  2. 2

    Footings

    Before concrete pour — footing excavation, rebar.

  3. 3

    Foundation

    After forms are in place, but before concrete is poured.

  4. 4

    Rough Framing

    When finished and before covering.

  5. 5

    Rough Plumbing / Electrical / Mechanical

    After concealed piping, wiring, and ductwork are in place, but before covering.

  6. 6

    Building Final

    Final building inspection — required before occupancy; occupancy of the structure is prohibited until after final inspection.

  7. 7

    Plumbing / Electrical Final

    Final plumbing and electrical inspections.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough Framing / Plumbing / Electrical / Mechanical

    Scope-dependent rough-in inspection before covering.

  2. 2

    Building Final

    Final building inspection — required before occupancy of the improved space.

Applies to: EV Charger / EVSE Permit, Solar PV / Solar Panel Installation Permit

  1. 1

    Rough Electrical

    After electrical is in place, but before covering — per the county's standard inspection sequence documented in this file's residential-building-permit entry.

  2. 2

    Electrical Final

    Final electrical inspection.

Applies to: Fire Sprinkler & Fire Alarm Permit

  1. 1

    Fire Sprinkler/Alarm Rough-In

    Inspection of sprinkler piping or alarm wiring before it is concealed; no published county or fire-district inspection checklist exists for this system specifically, so this entry follows the general rough-in sequence documented in this file's residential-building-permit and commercial-building-permit entries.

  2. 2

    Fire Sprinkler/Alarm Final

    Final acceptance test/inspection of the completed system, coordinated directly with the Fire Inspections contact (Eric Torgerson) since no published fire-district inspection process exists.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Wayne County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Wayne County building permits

Get alerts for Unincorporated Wayne County

We'll email you when Unincorporated Wayne County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.