Residential Building Permit in Unincorporated Wayne County, Utah
Required for new construction, additions, alterations, repairs, demolition, and moving of structures in unincorporated Wayne County. The Wayne County Building Department, via its single county-wide Building Inspector, issues and reviews all building permits under the standard 'Application for Building Permit and/or Certificate of Occupancy — Building Department - Wayne County' form. The same form and inspector serve incorporated towns within the county (confirmed via Loa Town's own building-permits page, which lists the identical inspector and directs residents to the county process) as well as unincorporated areas.
Reviewed 2026-07-19 · Source
When you need this permit
- New single-family dwelling construction, addition, alteration, repair, demolition, or moving of a structure (form covers all six categories: New, Alteration, Addition, Demolish, Repair, Move)
- Proof of ownership of property
- Waste water system permit (septic) must accompany the application per the county's own application instructions
- Plot plan showing lot dimensions, existing streets, building dimensions, and distances from the structure to all four property lines
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Initial (before work begins)
Required initial inspection before construction work begins, per the county's Inspection Record form
- 2
Footings
Before concrete pour — footing excavation, rebar
- 3
Foundation
After forms are in place, but before concrete is poured
- 4
Underground Plumbing
Underground/under-slab plumbing before it is covered
- 5
Rough Framing
When finished and before covering
- 6
Rough Plumbing
After concealed piping is in place, but before covering
- 7
Rough Electrical
After electrical is in place, but before covering
- 8
Rough Mechanical
Ductwork and mechanical rough-in before covering
- 9
Insulation
After insulation is installed, before drywall
- 10
Drywall
Drywall inspection before finishing
- 11
Building Final
Final building inspection — required before occupancy; occupancy of the structure is prohibited until after final inspection
- 12
Plumbing Final
Final plumbing inspection
- 13
Electrical Final
Final electrical inspection
See the full Unincorporated Wayne County inspection guide — scheduling & re-inspection fees →
Tips
- It is the General Contractor's responsibility to contact the Building Inspector for inspections and to give 24-hour notice, per the county's official Inspection Record instructions.
- Carports, small additions, and buildings on slabs may only need one or two inspections — conditions vary and the contractor should use good judgment in calling for inspections; the Building Inspector fills in which of the listed inspections are required (checked) for each permit.
- The permit becomes null and void if work is not commenced within 180 days, or if construction is suspended or abandoned for 180 days at any time after work has commenced, per the application's terms.
- Occupancy of the structure is prohibited until after the final inspection.
- No county-wide published dollar fee schedule for building permits exists on the Wayne County website or in the Wayne County Administrative Manual (Ch. 15, Application Fee and Review Fee Schedules) as of verification — the Administrative Manual's fee schedule forms show blank 'Fee Amount: $___' lines to be filled in per-application, and the Building Permit Application form itself has blank 'Rate ___ Permit Fee ___ Plan Review Fee ___' fields completed by county staff at intake rather than a published rate table. The county's own FY2026 budget shows a single county-wide 'Building Permit' revenue line (10-32-20000, $80,000 budgeted for 2026) and a single 'Building Inspector' expense line (10-4185-310, $65,000 budgeted for 2026) under 'Total Building Department' — confirming one county-wide program with no itemized per-permit-type fee schedule published for public reference. Applicants should call (435) 836-1302 or the Building Inspector directly for a fee quote before applying. RE-CHASED 2026-07-23 (new avenues, still open): confirmed Wayne County itself is NOT codified on American Legal Publishing or Municode (checked live — only the incorporated town of Torrey among Wayne County jurisdictions appears on American Legal Publishing's Utah list; the county's 2011 PDF Administrative Manual/Land Use Ordinance remain its only code); pulled the Utah Public Notice Website (utah.gov/pmn) sitemap for the Wayne County Commission public body and the county's live /agendas meeting archive (150+ Commission/Planning & Zoning meetings back to 2019) and live /documents resolution listing (Fire Ban, Landfill Hours, Data Center Moratorium, Cellular Telephones, Rural Health Care Tax, FY2026 budget resolutions) — none is a fee-schedule resolution. No dollar figure recoverable from any new source; gap remains genuinely unpublished.
- Same building department and inspector serve Loa, Bicknell, Torrey, and Hanksville (per Loa Town's own 'Building Permits & Inspections' page, which lists the identical Building Inspector, Eric Torgerson, and does not describe a separate municipal review process) — applicants in these towns should still expect to use the same county application and inspector.
- Statutory review-timeline floor: under Utah Code § 17-79-810 (effective 11/6/2025, renumbered from former § 17-36-55), once an application for plan review of a one- or two-family dwelling or townhome is determined complete (after a 3-business-day completeness-screening period per § 17-79-810(1)(f) and (3)(a)), the county must complete plan review within 14 business days per § 17-79-810(4)(a). This statutory floor applies because Wayne County has not published its own faster or more specific review-timeline commitment.
- Wayne County has not published a distinct solar-PV permit type, fee, or checklist (checked 2026-07-19, including the county's Documents page and a site search). The county uses a single unified 'Application for Building Permit and/or Certificate of Occupancy' form for all construction and repair work — the form lists an 'Electrician' trade-contractor line and includes 'Rough Electrical'/'Electrical Final' inspection items, with no separate electrical or solar permit category — so solar photovoltaic installations would be submitted through this same Building Permit process.
- EV charger (EVSE) installation is likewise treated as standard electrical work under this same unified Building Permit — the county publishes no distinct EV-charger or electric-vehicle-charging permit type, fee, or checklist anywhere on its site (checked 2026-07-19), and the single Building Permit Application form's 'Electrician' trade line and 'Rough Electrical'/'Electrical Final' inspection items are the only electrical-related categories on the form. As with the general fee schedule (see above), no published dollar figure exists — call (435) 836-1302 or the Building Inspector directly for a project-specific fee quote.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Wayne County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Wayne County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Wayne County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Wayne County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →