How to schedule
Inspections are requested through the building department below.
- Address
- 2549 Washington Boulevard, Suite 240, Ogden, UT 84401
- Phone
- (801) 629-8950
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM (excluding holidays)
- Website
- Official site
Published scheduling rules
- Apply online at https://egselfservice.ogdencity.com (Residential category) or in person at 2549 Washington Blvd, Suite 220. Schedule inspections by calling (801) 629-8950. (Residential Building Permit)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Foundation
Foundation walls before backfill
- 3
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 4
Insulation
After insulation installed, before drywall
- 5
Final
All work complete — address posted on site, approved plans on site, ladder available for attic/roof access, site open and accessible
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings, forms, rebar before concrete pour
- 2
Framing
Framing, fire separation, and egress verification
- 3
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 4
Final
All work complete, certificate of occupancy issued
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window wells and openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts; standard IBC inspection sequence.
- 2
Structural / Framing
Framing, floor and roof framing, and diaphragm connections verified against submitted structural calculations.
- 3
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against submitted plans.
- 4
Final
All work complete — address posted on site, approved plans on site, site open and accessible.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Fire-Rated Assembly
Wall construction and any fire-rated/occupancy separation assemblies verified before close-in.
- 2
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against submitted plans.
- 3
Final
Exit signage, emergency lighting, and all finishes verified complete before occupancy.
Applies to: Deck Permit
- 1
Footings
Verify footing depth below frost line (30 inches per Ogden Design Criteria), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify all utility clearances (power, gas, water) are obtained and any required asbestos clearance is complete before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, site conditions verified
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support for the EV charger circuit
- 2
Final
Charger connection, GFCI/AFCI protection (as applicable), and panel labeling verified
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition and replace damaged decking before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Ogden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Ogden building permits
Get alerts for Ogden
We'll email you when Ogden's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.