Building Permit in Pasco, Washington
Required for construction in Pasco. The city adopts whatever state-adopted code edition is current, and ties permanent utility service to the certificate of occupancy.
Reviewed 2026-09-16 · Source
When you need this permit
- Built to "the most current state-adopted International Building Code(s)" - PMC 16.05.010 names no edition year
- Cedar shakes or shingles, or materials of similar flame spread, are PROHIBITED for roof construction
- Permanent electrical, solid waste, water and sewer service require a certificate of occupancy
- Permit fees are determined under PMC 3.35.030, in a different title of the code
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
PASCO'S PERMIT FEES ARE IN A DIFFERENT TITLE OF THE SAME CODE. Show full citationHide
PASCO'S PERMIT FEES ARE IN A DIFFERENT TITLE OF THE SAME CODE. PMC 16.05.080, in full: "Permit fees shall be determined in accordance with PMC 3.35.030." Title 3 is revenue and finance, so the building title does not carry the schedule. PMC 3.35.030 WAS NOT OPENED for this entry and no amount is stated. ONE MORE FEE IS WORTH KNOWING ABOUT: PMC 16.05.090 provides that "A minimum fee as enumerated in PMC 3.35.030 shall be paid to the Building Official for incidental building and fire code inspections NOT related to issued, active building permits" - so an inspection outside an open permit is chargeable.Review timeline
Inspection process
Tips
- Do not plan a cedar roof here - the prohibition overrides the model code
- Do not occupy before the CO: provisional utilities can be discontinued if the dwelling is found occupied
- An inspection not tied to an active permit carries a minimum fee
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pasco building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Pasco's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Pasco yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Pasco lands. Privacy.
Other permits in Pasco
Building Permit in other cities
Compare building permit fees across Washington →
Look up this fee in a different city →
Now live
Build your Pasco project checklist
Describe your project once and get every permit, document, and fee it triggers in Pasco — in one checklist. Free, for any city and any number of projects.
Get started →