Building Permit in Sammamish, Washington

Required for construction in Sammamish. The city adopts the 2021 IBC and IRC as adopted by the State Building Code Council, supplies its own administrative code in place of Chapter 1, and publishes an ordered, binding inspection sequence.

Reviewed 2026-09-16 · Source

When you need this permit

  • Built to the 2021 IBC and 2021 IRC as adopted by the State Building Code Council
  • IRC Appendix Q (Tiny Houses) IS adopted; IRC Chapters 1, 11 and 25 through 43 are excluded
  • IBC Appendix E (Accessibility), ICC A117.1-2017 and Appendix H (Signs) are included
  • Administration is governed by SMC Chapter 16.20, not by model-code Chapter 1
  • Plan review is a separate and additional fee, payable when submittal documents are lodged

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building permit fee (set by council fee resolution)
SAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. Show full citationSAMMAMISH DOES NOT PUBLISH ITS PERMIT FEE AMOUNTS IN THE CODE - THIS ENTRY DECLINES TO STATE A FIGURE RATHER THAN INVENT ONE. SMC 16.20.340 directs the reader to "the fee schedule as established in the City of Sammamish fee resolution", which is a separate council instrument not read for this entry. WHAT THE CODE DOES FIX IS A FLOOR, AND IT IS AN UNUSUAL ONE: "In no case shall the building permit fee be less than the City's hourly inspection fee multiplied by the number of inspections expected to be performed for work authorized by the permit." The minimum is therefore tied to an expected inspection COUNT, not to a dollar amount - which matters here because the city publishes twelve required inspection stages. Plan review is a SEPARATE and ADDITIONAL fee (SMC 16.20.345), payable when submittal documents are lodged; the permit centre may take a deposit in lieu where the full amount is not yet known, applied against the total. Incomplete or changed submittals, and deferred submittal items, draw a further plan review fee. A reinspection fee may be assessed where work is not complete or previous corrections were not made (SMC 16.20.450).
Set by council fee resolution; see notes

Review timeline

Plan review
Not published — contact the department

How long did your Building Permit permit actually take in Sammamish?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Temporary erosion and sediment control inspection

    Made after all required silt fencing, construction fencing, straw bales, storm drain catch basin inserts (socks), entrance rocking and other required elements are in place, and prior to commencement of work (SMC 16.20.393).

  2. 2

    Footing and foundation inspection

    Made after poles or piers are set, trenches or basement areas are excavated, or excavations for footings are complete, any forms erected, and all required hold-down anchor bolts, hold-down straps and any required reinforcing steel are in place (SMC 16.20.395).

  3. 3

    Concrete slab and under-floor inspection

    Made after in-slab or under-floor reinforcing steel and building service equipment, conduit, slab insulation, piping accessories and other ancillary equipment items are in place, but before any concrete is placed (SMC 16.20.400).

  4. 4

    Exterior wall sheathing inspection

    Made after all wall framing is complete and strapping and nailing are properly installed, but prior to being covered (SMC 16.20.410).

  5. 5

    Roof sheathing inspection

    Made after all roof framing is complete. No roof coverings may be installed until the inspection is made and approved (SMC 16.20.415).

  6. 6

    IMC/IPC/Gas/NEC/IFC rough-in inspection

    Rough-in mechanical, gas piping, plumbing and fire suppression systems are inspected when the rough-in work is complete and, if required, under test (SMC 16.20.420).

  7. 7

    Electrical rough-in inspection

    Made after the roof, framing, fireblocking and bracing are in place and all wiring and other components to be concealed are complete, and prior to covering (SMC 16.20.423).

  8. 8

    Frame inspection

    Made after the roof deck or sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete, and the rough electrical and plumbing are in place (SMC 16.20.425).

  9. 9

    Flashing and exterior weather barrier inspection

    Made after flashing and weather barrier materials have been installed, but prior to any of that work being covered (SMC 16.20.430).

  10. 10

    Lath and gypsum board inspection

    Made after lathing and gypsum board, interior and exterior, are in place, but before any plastering is applied or gypsum board joints and fasteners are treated (SMC 16.20.435).

  11. 11

    Energy efficiency inspection

    Covers envelope items including wall insulation, to be made after exterior wall weather protection and all wall insulation and air vapor retarder, sheet or film materials are in place (SMC 16.20.445).

  12. 12

    Final inspection

    Made after all work required by the building permit is completed (SMC 16.20.465).

See the full Sammamish inspection guide — scheduling & re-inspection fees →

Tips

  • Work cannot proceed past a stage until that inspection is approved - the sequence is enforceable under SMC 16.20.480
  • The permit fee cannot fall below the hourly inspection rate times the expected number of inspections, and the city publishes twelve stages
  • A deposit may be taken in lieu of the full plan review fee and applied against the total
  • Changed or incomplete submittals, and deferred submittal items, draw an additional plan review fee

Frequently asked questions

Sammamish requires a building permit for: Built to the 2021 IBC and 2021 IRC as adopted by the State Building Code Council; IRC Appendix Q (Tiny Houses) IS adopted; IRC Chapters 1, 11 and 25 through 43 are excluded; IBC Appendix E (Accessibility), ICC A117.1-2017 and Appendix H (Signs) are included; Administration is governed by SMC Chapter 16.20, not by model-code Chapter 1; Plan review is a separate and additional fee, payable when submittal documents are lodged. If your project isn't listed, confirm with City of Sammamish at (425) 295-0500 before starting work.

The code does not state amounts. SMC 16.20.340 sets fees by "the fee schedule as established in the City of Sammamish fee resolution", a separate council instrument, so ask the city for the current schedule. What the code does fix is a floor: the building permit fee may not be less than the city's hourly inspection fee multiplied by the number of inspections expected for the permitted work. Plan review is charged separately and in addition.

Sammamish does not publish a plan-review timeline for this permit. Contact City of Sammamish at (425) 295-0500 for current turnaround.

You'll need: Submittal documents for plan review. See the required-documents checklist on this page for details on each.

SMC 16.20.390 requires the inspections set out in SMC 16.20.395 through 16.20.465. In code order these are temporary erosion and sediment control; footing and foundation; concrete slab and under-floor; exterior wall sheathing; roof sheathing; IMC/IPC/Gas/NEC/IFC rough-in; electrical rough-in; frame; flashing and exterior weather barrier; lath and gypsum board; energy efficiency; and final. The order binds: SMC 16.20.480 provides that work "shall not be done beyond the point indicated in each successive inspection" without the building division's approval first.

Apply through City of Sammamish at 801 228th Ave SE, Sammamish, WA 98075. Phone: (425) 295-0500. Official information: https://www.sammamish.us/.

The 2021 International Building Code and 2021 International Residential Code, each "as adopted by the State Building Code Council" in Chapters 51-50 and 51-51 WAC respectively. These adoptions name a fixed edition. Chapter 16.05 does contain rolling language - "as presently existing and as may be subsequently amended" - but SMC 16.05.180 applies it only to Chapter 51-19 WAC, the Washington State Historic Building Code, not to the building or residential codes.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-09-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sammamish building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Sammamish's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Sammamish yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Sammamish lands. Privacy.

Compare building permit fees across Washington

Look up this fee in a different city →

Embed this data card →

Now live

Build your Sammamish project checklist

Describe your project once and get every permit, document, and fee it triggers in Sammamish — in one checklist. Free, for any city and any number of projects.

Get started →